ID |
Date |
Author |
Subject |
Text |
 |
72
|
Sun Oct 9 15:49:41 2016 |
JL Tain et al | Power shutdown | Due to maintenance operations of the Wako
electrical
company there is a risk of power shutdowns |
|
71
|
Sun Oct 9 04:20:47 2016 |
JL Tain et al | Noise | We check for the appearance of spurious signals
in the preamplifiers.
|
 |
70
|
Sat Oct 8 01:18:51 2016 |
JL Tain et al | DACQ | We increased the pretrigger delay for ADC5
from 350 to 400 |
|
68
|
Fri Oct 7 10:42:52 2016 |
JL Tain et al | Noise | We investigate the effect on the noise in
ORNL tubes of using a differential PA.
|
|
67
|
Fri Oct 7 08:35:15 2016 |
JL Tain et al | Noise | Low amplitude noise component.
The figure shows the composition of the low |
|
66
|
Fri Oct 7 08:09:47 2016 |
JLTain et al | Background | Background measurement overnight
Start: Oct-6 2242 Stop: Oct-7 10:45
|
 |
65
|
Thu Oct 6 14:50:30 2016 |
JL Tain, A Tolosa, A Tarifeno,... | 252Cf | First measurement with 252Cf source to check
the calibration.
AIDA was in place so the source was at the |
 |
64
|
Thu Oct 6 14:43:47 2016 |
JL Tain, A Tarifeno, A Tolosa, J Agramunt, N Brewer, S Go, ... | Electronics | We mount back all preamplifiers
Initially we used all the PA coming from
US, the repaired and the new ones.
|
|
63
|
Thu Oct 6 02:03:32 2016 |
JL Tain | START | We started the assembly of BRIKEN and AIDA
detectors in their final position
on Tuesday October 4:
|
6x |
62
|
Thu Aug 18 23:32:59 2016 |
NT Brewer | New preamps arrived at Oak Ridge and tested working. | Collaborators,
Attached is a phone photo of example
signals from the new preamps with 3 3He tubes |
 |
Draft
|
Thu Aug 18 22:39:35 2016 |
NT Brewer | New preamps arrived at Oak Ridge and tested working. | Collaborators,
Attached is a phone photo of example
signals from the new preamps with 3 3He tubes |
|
60
|
Fri Jul 29 09:52:28 2016 |
Keishi Matsui | accuracy of Cf-252's intensity in RIKEN | According to the reply from Japan
Radioisotope Association, the accuracy of
the Cf-252's intensity is +0%/-15%. |
|
59
|
Fri Jul 22 12:50:29 2016 |
J.L. Tain | END | 20/JUL/2016 20:00
End of the test measurements |
|
58
|
Wed Jul 20 17:21:59 2016 |
J. Agramunt, A. Tolosa | DACQ | DACQ configuration parameters
The last configuration file used was: 160718Conf_BrikenFull_cal5.xlsx
|
|
57
|
Wed Jul 20 17:18:59 2016 |
J.L. Tain, J. Agramunt, A. Tarifeño, A. Tolosa, K. Gabor, S. Go, K. Matsui... | Electronics | Measurement with preamplifiers after drying.
Amplifiers are brought back after ~12h and |
 |
56
|
Wed Jul 20 17:05:59 2016 |
J.L. Tain, J. Agramunt, A. Tarifeño, A. Tolosa, ... | Background | Background measurement with remaining tubes
(95) overnight
|
|
55
|
Wed Jul 20 16:55:48 2016 |
K.Gabor, K. Matsui, A. Tarifeño | Electronic | Drying of preamplifiers
PA8, PA9 and PA10 are removed and brought |
|
54
|
Wed Jul 20 16:50:12 2016 |
J.L. Tain, J. Agramunt, A. Tarifeño, A. Tolosa, S. Go... | 252Cf | Measurement of the 252Cf source at the central
position
|
|
53
|
Wed Jul 20 16:40:57 2016 |
S. Go, J.Agramunt, A.Tolosa, J.L. Tain,... | CLOVER | Calibration and resolution check
CLOVER detectors were calibrated in energy |
|
52
|
Wed Jul 20 16:12:58 2016 |
S. Go, ... | CLOVER | Mounting of the CLOVER detectors in position
CLOVER G7: right of beam
|
  |