Wed May 19 11:24:55 2021, RDP, Monday 19 April 12 noon shift  
|
System checks gave 11 passed/1 failed, except for ADC timimgs: 10 passed/2 failed.
FEE64 module aida09 global clocks failed, 6
|
Fri Apr 26 15:34:00 2024, RDP, 16:00 - 00:00 Friday 26 April 6x
|
This appeared in the system log:
Apr 26 16:30:51 aidas-gsi smartd[1076]: Device: /dev/sda [SAT], 1 Currently unreadable (pending) sectors
Apr 26 16:30:56 aidas-gsi smartd[1076]: Device: /dev/sdd [SAT], 2224 Currently unreadable (pending) sectors |
Thu May 13 19:52:36 2021, Philippos and Marc, Connection problem
|
At 20:15, We lost connection with AnyDesk.
Liliana restarted Anydesk on the AIDA DAQ PC. All seemed fine on AIDA DAQ but there was a more generic issue on the main DAQ, possibly the timesorter.
Helena restarted all after ~30mn and it's all working again now. |
Thu May 13 21:21:25 2021, Philippos and Marc, system wide checks 13x
|
Wide checks at Time 22:22 CET
Clock status test result: Passed 16, Failed 0
Understand status as follows |
Thu Jun 23 15:10:17 2022, Philippos Papadakis, Thursday 23 June 16:00-24:00 15x
|
16:20
System wide checks.
Clock status OK
|
Thu Oct 31 19:02:42 2019, Patrick, WR Timestamps
|
> All 12 FEEs have valid WR Timestamps
> Had to powercycle aida09 once as before raw readout was displaying upper 12 bits of WR timestamp as 0. Unsure of other method.
>
|
Tue Jun 11 15:01:07 2024, PP TD, 16:00-00:00 shift Tuesday 11/06/24 13x
|
All seems OK
Screenshots attached.
|
Sat May 14 03:14:00 2022, PP, Shift Checks 8x
|
4:13
AIDA stats OK
Leakage current OK |
Tue Apr 23 07:27:18 2024, PP, 08:00-16:00 Tuesday 24 April shift 8x
|
Checks 08:00-08:30
Screenshots are attached and everything looks OK. |
Tue Apr 23 09:21:01 2024, PP, 10:20 checks - aida02 is down 8x
|
Aida02 is down. Contacted Nick.
The rest looks stable, see screenshots.
10:53 CEST (NH): Rebooted aida02 via telnet |
Tue Apr 23 10:10:31 2024, PP, aida02 is back
|
Nick rebooted AIDA and aida02 came back at around 10:55.
AIDA was out of the DAQ from about 10:30 until 10:55 |
Tue Apr 23 10:52:39 2024, PP, Aida02 down and back
|
We lost aida02 at about 11:25 again. Nick fixed it about 11:50.
It is now back in the DAQ. |
Tue Apr 23 11:09:00 2024, PP, 12:00 checks 8x
|
Everything is OK now.
Screenshots attached. |
Tue Apr 23 13:15:43 2024, PP, 14:00 checks 8x
|
All looks good.
Screenshots attached |
Tue Apr 23 19:23:42 2024, PP, 20:30 checks 8x
|
All looks good.
Screenshots attached. |
Wed Apr 24 15:37:59 2024, PP, 16:00-00:00 shift Wednesday 24 April 8x
|
All seems OK.
Screenshots attached. |
Wed Apr 24 18:44:05 2024, PP, 19:30 checks 8x
|
All seems smooth.
Screenshots attached. |
Tue Jun 11 18:45:37 2024, PP, Mid-shift checks, 19:45 8x
|
All looks good.
Sceenshots attached. |
Wed Jun 12 11:06:55 2024, PP, Mid-shift checks, 12:00 8x
|
All seems normal.
Screenshots attached. |
Wed Jan 18 13:40:33 2023, PJCS TD, MACB settings with either Emulator or VITAR   
|
When using the VETAR connected to the HDMI port of the root MACB the settings for all the MACB in the system 0x3.
This setting takes the Clock and Data line from the input HDMI and outputs it via teh HDMI output ports.
When using the Emulator connected via the SMA connectors on the back of the root MACB then the setting for the root MACB |