648
|
Mon Jun 10 15:07:24 2024 |
Marc | 16:00-00:00 shift Monday 10/06/24 | Evening shift
5pm full checks:
DSSSD
bias & leakage current ok - attachment |
31x |
619
|
Sun Apr 28 16:26:47 2024 |
Betool Alayed | 16:00-00:00 Sunday 28 April | 19:24 pm screenshots
and
17:18 pm screenshots |
10x |
657
|
Wed Jun 12 15:41:07 2024 |
Betool Alayed | 16:00-00:00 Wed 12 Jun 24 | 5pm full checks:
DSSSD bias & leakage current
ok - attachment # 1-2 |
27x |
660
|
Thu Jun 13 21:06:44 2024 |
Robert Page | 16:00 to 00:00 shift on 13/6/2024 | Elog went down around the end of the last
shift, so final screenshots were not uploaded
at that point. |
26x |
606
|
Thu Apr 25 15:02:50 2024 |
Marc | 16:00 - 0:00 Thursday 25 April |
16:20:
Spill length:4s (was 3.5s
before) - Extraction time 1.5s (see attachement
#1)
|
8x |
613
|
Sat Apr 27 15:13:06 2024 |
Norah | 16:00 - 00:00 Saturday 27 April | 14:50 Checks
Leakage current is 20.021
and HV status is Max Voltages ! Is it normal |
15x |
610
|
Fri Apr 26 15:34:00 2024 |
RDP | 16:00 - 00:00 Friday 26 April | This appeared in the system log:
Apr 26 16:30:51 aidas-gsi smartd[1076]:
Device: /dev/sda [SAT], 1 Currently unreadable |
6x |
645
|
Sun Jun 9 16:38:30 2024 |
Norah , Muneerah, JB | 16:0-00:00 9 June 2024 | AIDA02 and AIDA06 gave zero attachment
1. After connecting with Tom to fix it, now
it works. |
   |
616
|
Sun Apr 28 15:09:34 2024 |
Betool Alayed | 16:0-00:00 28 April 2024 | 16:00 aida04 not producing data
power cycle all FEE64s to recover DAQ |
|
620
|
Sun Apr 28 20:35:57 2024 |
Betool Alayed | 16:0-00:00 28 April 2024 | 21:30 screenshots
and
23:24 screenshots |
10x |
588
|
Mon Apr 22 15:17:07 2024 |
DSJ | 16.00-0.00 22/04/24 | First checks of shift. All looks ok.
Screenshot of HV, temps,
rates, Merger attached. Attachments 1-4. |
26x |
231
|
Fri Apr 16 15:52:08 2021 |
DSJ | 16 April 16.00 shift | Clock status test result: Passed 12, Failed
0
|
12x |
197
|
Sat Mar 13 23:08:08 2021 |
CA | 14th March 00:00-08:00 | 00:08 DAQ continues ok - writing to file R46_221
ASIC settings 2019Dec19-16.19.51
|
22x |
597
|
Tue Apr 23 13:15:43 2024 |
PP | 14:00 checks | All looks good.
Screenshots attached |
8x |
96
|
Wed Nov 13 09:10:37 2019 |
CA, NH, OH | 13th November 2019 | 10:10 moved HV cables from 11 and 12 to 10
and 9 - all detectors biased in same configuration
|
   |
443
|
Fri May 13 15:00:23 2022 |
CB | 13 March - 16:00-24:00 shift | 16:00 Took over remotely from OH, TD who remain
in GSI
|
10x |
573
|
Sat Apr 13 14:04:44 2024 |
JB | 13 April Noise checks | 15:04 bPlast was left powered over night.
Powering up to check noise conditions - also
to check shifting of Germanium baseline (no |
9x |
594
|
Tue Apr 23 11:09:00 2024 |
PP | 12:00 checks | Everything is OK now.
Screenshots attached. |
8x |
572
|
Thu Apr 11 22:04:50 2024 |
JB | 12.04.2024 AIDA-bPlast noise optimisation | 15:00 Platform in, biasing detector. Temp
OK Attachment 1. test - Pulser OFF.
|
    |
571
|
Thu Apr 11 08:27:21 2024 |
JB, TD | 11 April noise tests |
TO-DO for 11.04.2024
- Try bringing
bPlast drain wire ground back to the PSU
ground for PN 300 and R&SRMP4040.
- |
48x |