  21   Tue May 5 05:04:00 2015 J.L. Tain, J. Agramunt, G. KissChange of degrader thicknessFor EURICA measurements degrader thickness
were increased
trying to decrease MACI and AIDA trigger
  
  22   Tue May 5 05:17:36 2015 J.L. Tain, J. Agramunt, G. KissAmbient background measurement

Failure of
a quadrupole triplet at BigRIPS (some time
after earthquake)

We take the chance of
  
  23   Tue May 5 05:29:26 2015 J.L. Tain, J. Agramunt, G. KissAmbient background measurementBeam still down. New background measurement
with new RIKEN tube below the MUSIC chamber
  
  24   Wed May 6 04:57:24 2015 J.L. Tain, J. Agramunt, G. KissNew degrader thicknessThe Al degrader thickness was reduced to 4.8mm   
  25   Wed May 6 05:10:14 2015 J.L. Tain, J. Agramunt, G. Kiss94Se setting measurementAfter the long shutdown the beam is back at
00:30 (06/05)
Intensity is slightly lower 26pnA and somewhat
  
  26   Wed May 6 11:41:24 2015 J. Agramunt, A. EstradeFirst online combined analysisScreen shot of the rudimentary on-line
analysis of the combined data:
BRIKEN-AIDA-BigRIPS
 Screenshot_from_2015-05-06_19_12_29.png 
  27   Thu May 7 08:36:56 2015 J.L. Tain, J. Agramunt, A. Estrade, G.Kiss, T. Davinson, C.GriffinFirst BRIKEN_v.0 beta-delayed neutron correlations?During the 98,100Kr setting run we observe

in the time correlation plot (middle right
 Screenshot_from_2015-05-07_16_01_27.png 
  28   Fri May 8 03:20:48 2015 J.Agramunt J.L.Tain K.GaborBnCorrelationWe run all the night until the end of beam
time, and the Bn correlations are more clear
now.
 BnCorr.pdf 
  29   Mon May 11 09:14:54 2015 G. Kiss252Cf_data_sheetThe activity of the 252Cf source, used
for the calibration was 3.7 MBq at 15.05.2006.
Unfortunately, uncertainty is missing from
 252Cf_15_05_2006_3p7MBq.jpg 
  30   Sat Jul 9 20:44:31 2016 J.L. TainBRIKEN neutron detectorSTART
Assembly and commissioning of BRIKEN neutron
detector 
  
  31   Sat Jul 9 21:00:54 2016 J.L. TainHardwareA list of the available hardware  Hardware.xlsxHardware.pdf 
  32   Sat Jul 9 21:08:08 2016 J.L. TainNeutron moderatorDrawings of the polyethylene neutron moderator
and table assembly
 Moderator-Table.pdfTable.pdfModerator-Shielding.pdf 
  33   Sat Jul 9 21:14:12 2016 J.L. Tain3He tubesDrawings and specs of 3He tubes  He3_GE_30cm-RIKEN.pdf1inch3He-ORNL.pdf2inch3He_ORNL.pdfHe3-252248-UPC-GSI.pdf 
  34   Sat Jul 9 21:21:38 2016 J.L. Tain3He tubesTube distribution in the moderator, pre-amplifiers
and digitizers
 TubeDistribution.pdfTubeDistribution.xlsx 
  35   Sat Jul 9 21:26:25 2016 J.L. TainEDACQElectronics and DACQ for July 2016 assembly:
hardware and connections
 EDACQ-July2016.pdf 
  36   Fri Jul 15 08:29:14 2016 Nathan Brewer, Shintaro GoExpected Performance and Voltage Setting for GermaniumExpected Resolution:
------------------------------
G7 should be ~2.0 keV FWHM at 600
  
  37   Fri Jul 15 11:47:31 2016 Nathan Brewer and Alvaro TolosaPreliminary Ge Calibration, Resolution and ConfigurationToday several tests (3) were done with
the germanium detectors with the voltage
configuration listed in the previous entry.
 9x 
  38   Mon Jul 18 09:32:50 2016 Shintaro GoHV controlsYou can start applying HVs on the detectors
using macro on the control-computer.
If you have already signed in the
  
  39   Mon Jul 18 18:40:32 2016 A. Tarifeņo-Saldivia and J. L. Tain3He tubes - TestingTest of individual 3He tubes

The tests were done using the ATOMKI MCA
 7x 
  40   Mon Jul 18 19:01:36 2016 J.L. Tain3He tubesAdjustment of HV and PA gain

We adjust the HV for each tube type and the
  