  12   Sun May 3 09:04:07 2015 J.L. Tain, J. Agramunt, G. KissSummary of neutron measurements
U: (Up: 2 RIKEN tubes at 40cm from AIDA)
D: (Down: 12 RIKEN tubes at 80cm from AIDA)
  
  348   Wed Oct 25 01:02:14 2017 RGStatus of the YSO arrayThe presently used detector has 48x48x5
mm3 YSO array with 1x1mm2 segments. They
are separated with ESR.  We use H8500
  
  210   Wed Mar 29 13:31:37 2017 J Agramunt, R. Caballero, T. Davinson, C. Griffin, O. Hall, D. Kahl, G. Kiss, J. Liu, S. Nishimura, V. Phong, JL TainStart of parasiticStart of parasitic Ca beam
(main experiment "New isotope search", Ahn
et al.)
 170329_Conf_BrikenFull.xlsx 
  358   Tue Oct 16 03:15:03 2018 ATD & JLTStart of REP run preparation (RIBF148)16-Oct-2018

- Start DACQ computer: OK!
 Screenshot_from_2018-10-16_14-57-33.png 
  134   Tue Nov 8 02:49:19 2016 PV, LiuSpecification of the dE silicon detectorThe specification and picture of the dE silicon
detector is shown in the attached photos.
The detector  has an effective area of 134
 spec_de_1.jpgspec_de_2.jpgIMG_1340.JPG 
  190   Tue Nov 29 00:30:42 2016 PV,SNSillicon dE bias voltage increasedWe increase the bias voltage of the dE
detector from 20 V to 100 V

Leakage current:
  
  123   Mon Nov 7 04:37:33 2016 Phong,Liu,...Si de and AIDA plastic calibration60Co source placed close to the detectors:

ROOT files: 
  
  145   Tue Nov 8 17:00:27 2016 NTB, CG, ATSi Delta EAt least during the timeframe in between
~ 21:30 (11/08) - 23:30 (11/09) (161108_2323_717273Ni.root)
we see that the silicon dE have a very low
  
  321   Mon Jun 12 02:45:44 2017 Iris Dillmann ATSetup detectors. Id of Ancillary@BRIKENAttachment 1: Setup detectors 
Attachment 2: example of configuration file
(valid only for RIBF127). The Id of the ancillary
 Setup-26May2017.pngOfflineConf_Signals.csv 
  171   Sat Nov 26 06:30:30 2016 ATSetupSetup for parasitic experiments

Energy 41Al @ F11 is around 145MeV/u
  
  330   Mon Oct 16 05:52:14 2017 BRIKEN collaborationSTART preparationWe start to check every thing for the coming
run
 171016_Conf_BrikenFull.xlsx 
  293   Wed May 24 06:42:05 2017 JLT,AT,AM,RY,SGSTART PreparationWe start to check every thing for the coming
run
  
  63   Thu Oct 6 02:03:32 2016 JL TainSTARTWe started the assembly of BRIKEN and AIDA
detectors in their final position
on Tuesday October 4:
 6x 
  101   Thu Nov 3 04:40:02 2016 AllSTARTStart of commissioning preparation

 161103Conf_BrikenFull.xlsx 
  131   Mon Nov 7 13:44:26 2016 Alvaro, Ale, Jorge, JoseRunning Gasific and run protocolPreliminary  GasificShort.pdf 
  162   Fri Nov 25 03:41:40 2016 ATRun setupsRun setups during preparation of Fallon Parasitic
experiments (Kanungo experiment beam time)
can be found on 
 RUNsum_kanagoda.pdf 
  270   Sat Apr 1 02:07:49 2017 ID DK JARun 55Date: 1/04/2017
Start:10:04
BRIKEN run: 55
  
  252   Fri Mar 31 10:35:22 2017 PV CG JARun 40Date: 31/03/2017
Start: 
BRIKEN run: 40
  
  251   Fri Mar 31 09:23:45 2017 CG PV JARun 39Date: 31/03/2017
Start: 17:22
BRIKEN run: 039
  
  250   Fri Mar 31 08:23:32 2017 CG PV JARun 38Date: 31/03/2017
Start: 16:21
BRIKEN run: 038
  