319
|
Fri May 14 19:01:09 2021 |
JS | Friday 14th May 20:00-00:00 | 20:00 Taking over from CB
20:33 Doing full checks.
|
27x | |
|
719
|
Mon Oct 13 15:04:53 2025 |
JPB, NH, GB, MP | Dismount AIDA and realign the cables | We have dismounted the AIDA stack and bPlast
and realigned the cables so that they can
fit into the adaptors.
|
 | |
|
639
|
Wed Jun 5 08:34:47 2024 |
JB. AM, MP, MY | Detector bias tests | We are trying to bias each system on its
own and in sequence biasing each other detector
system to see the interdependence. |
14x | |
|
571
|
Thu Apr 11 08:27:21 2024 |
JB, TD | 11 April noise tests |
TO-DO for 11.04.2024
- Try bringing
bPlast drain wire ground back to the PSU
ground for PN 300 and R&SRMP4040.
- |
48x | |
|
577
|
Thu Apr 18 08:57:48 2024 |
JB, TD | Thursday 18 April | 09.52 DAQ continues file S100_alpha/R5
note merger not functioning correctly
due to aida03, aida04 & aida09 out of WR |
36x | |
|
533
|
Mon Mar 11 15:19:44 2024 |
JB, NH, Priyanka, Michael Armstrong, Helena Albers | To Do: AIDA PCB tests | To do:
1) Disconnect ribbon cables
from p+n junction FEE64 adaptor PCBs of upstream |
| |
|
537
|
Thu Mar 14 13:00:23 2024 |
JB, NH, MA, AM, GA | Mounting and biasing DSSD 2 | new Downstream DSSD2: 3208-2/3208-5/3208-8
Covered with black cloth. |
| |
|
536
|
Thu Mar 14 12:13:17 2024 |
JB, NH, MA | Mounting and biasing DSSD 1 | Upstream bPlast mounted
new Upstream DSSD: 3208-2/3208-5/3208-8
|
| |
|
535
|
Wed Mar 13 13:02:19 2024 |
JB, NH, HA, MA | DSSD 1 biasing tests | Dismounted Snout and biased DSSSD1 channels
leftmost waifer working
middle waifer reaches 90V then |
| |
|
530
|
Thu Mar 7 15:15:29 2024 |
JB, NH, CC | AIDA HV Bias Test IV Curve |
AIDA I-V
Test
Voltage |
| |
|
552
|
Wed Mar 27 14:22:35 2024 |
JB, NH | Installing FEE64s of DSSSD2 | Mounted on frame:
DSSD 1 (Upstream) :
3208-2/3208-5/3208-8 |
14x | |
|
637
|
Mon Jun 3 14:40:34 2024 |
JB, NH | 03 June 2024 | 15:40 reseated FEE64s adaptors of aida01,
aida09, aida13 & aida16.
TEMP OK. HV OK. System wide checks |
10x | |
|
727
|
Mon Oct 27 11:55:00 2025 |
JB, MP, GB, NH | Changing ground setup from 25102025 | 12:55 We are going to try the follow changes
to the AIDA scheme of 241012025.
|
9x | |
|
677
|
Mon Dec 16 13:07:04 2024 |
JB, MP, CC | AIDA timing test | https://elog.gsi.de/despec/Implantation+Stack/9?suppress=1
- Day 1 ELOG
Day2: |
16x | |
|
678
|
Tue Dec 17 12:45:36 2024 |
JB, MP, CC | AIDA timing test |
|
  | |
|
683
|
Wed Jan 8 16:47:05 2025 |
JB, MP, CC | AIDA timing test |
|
| |
|
684
|
Thu Jan 9 12:46:43 2025 |
JB, MP, CC | AIDA timing test |
|
   | |
|
734
|
Wed Oct 29 14:11:01 2025 |
JB, MP | 207Bi source test - data taking | 15:10 MP entered and check the water pressure
OK.
15:10 DSSSDs biased - OK.
|
7x | |
|
740
|
Wed Nov 5 13:23:38 2025 |
JB, MP | 207Bi source test - FWHM tests | 14:10 started up the DAQ. HV and TEMPS OK.
Peak threshold with 1V pulser measured at |
8x | |
|
681
|
Wed Jan 8 10:08:29 2025 |
JB, GB, SD, MP, CC, JG | AIDA noise test with platform in position | Yesterday we spent time essentially performing
a dry run to get AIDA DAQ and bPlast into
the time sorter, there were some issues with |
   |
|