AIDA GELINA BRIKEN nToF CRIB ISOLDE CIRCE nTOFCapture DESPEC DTAS EDI_PSA 179Ta CARME StellarModelling DCF K40
  DESPEC, Page 32 of 36  ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Authordown Subject Text Attachments
  713   Wed Jul 23 15:04:26 2025 CC, MP, NKTest of AIDA05 with BB7 connected to Mesytec but not biasedAttachment1: AIDA05.1.8L when AIDA05 connected,
biased at 100 V with not-shielded cables,
after the DEGAS platform has been closed,
 Screenshot_from_2025-07-23_16-16-57.png 
  714   Wed Jul 23 15:56:00 2025 CC, MP, NKTest of AIDA05 with new bias moduleAttachment1: AIDA05.1.8L when AIDA05 connected,
biased at 101 V with shielded cables. BB7
is still connected but not biased (same configuration
 Screenshot_from_2025-07-23_17-08-56.png 
  717   Thu Jul 24 13:36:34 2025 CC, MP, NKAIDA05 connected and disconnected compared to AIDA09HT cable shielded, HT
of upstream AIDA from iseg, HT of downstream
AIDA from CAEN. Both channel 0 and 1 of CAEN
 10x 
  718   Thu Jul 24 15:50:01 2025 CC, MP, NKCheck of BB7 impactHT of upstream AIDA from iseg, HT
cable shielded, 100V, 17 uA. HT
of downstream AIDA from CAEN, AIDA#0. Both
 Screenshot_from_2025-07-24_16-49-27.pngScreenshot_from_2025-07-24_17-03-44.pngScreenshot_from_2025-07-24_17-22-49.pngScreenshot_from_2025-07-24_17-29-38.png 
  574   Mon Apr 15 09:23:43 2024 CC, JB, HMA, TDNoise in AIDA when connecting BB79:40 started up AIDA. TEMP OK. Noise condition
same as Saturday. Attachments 1-3.

9:56 BB7 premaps connected but
 13x 
  41   Tue Apr 2 07:39:44 2019 CB, TD, CATuesday 2nd April 201908:15 beam tuning in progress

08.30 System wide checks 
 36x 
  429   Wed May 11 19:08:41 2022 CB, PPWednesday 11th May - evening shift20:19 no beam yet.

Statistic check (screenshot attached).

Temperatures OK (screenshot attached).
 16.png22.png13.png14.png 
  308   Wed May 12 15:03:10 2021 CB, OHWed 12 16:00-20:0016:00 Shift change

Statistics OK (attach 1)
 15x 
  317   Fri May 14 14:57:32 2021 CB + OH, TD, NHFriday 14th May 16:00-20:0016:00 Shift taken over from CA

16:00 
 33x 
  249   Mon Apr 19 19:19:18 2021 CBMonday 19 April 20:00-24:00 shift20:19 
Statistics OK (attach 1)
No faults found
 11x 
  252   Tue Apr 20 10:54:41 2021 CBApril 20 12:00 - 16:00 shift11:55 CA got AIDA back online

12:00 Stats OK (attach 1)
 9x 
  324   Tue May 18 14:57:43 2021 CBTuesday 18th May 16:00 - 20:0015:58 Took shift over from OH and PP

Stats OK - attach 1
 11x 
  332   Wed May 19 14:54:36 2021 CBWednesday 19 May 16:00 - 20:0015:55 Took over from OH

16:00
 11x 
  443   Fri May 13 15:00:23 2022 CB13 March - 16:00-24:00 shift16:00 Took over remotely from OH, TD who remain
in GSI
 10x 
  142   Wed Mar 11 17:21:33 2020 CA, TD, OHWednesday 11 March 16.00-00.0018.25 DAQ currently running No Storage mode

ASIC settings 2019Oct31-13.24.23
 23x 
  15   Wed Jan 23 08:12:01 2019 CA, TD, NH, VPJanuary 22nd 2019Attachment 1 - 1.8.W waveform spectra with
pulser signal
 220119_18W.png220119_pulserpeaks.png220119_stats.png220119_Temp.png 
  16   Wed Jan 23 09:25:55 2019 CA, TD, NH, VPMACB and setup pics 23.01.19Pictures of leaking cooling pipe

MACB switch settings
 11x 
  17   Wed Jan 23 17:03:08 2019 CA, TD, NH, VPJanuary 23rd 2019Post White Rabbit update

Attachment 1 - 1.8.W pulser waveform spectra
 6x 
  18   Thu Jan 24 10:21:26 2019 CA, TD, NH, VPJanuary 24th 201910.30 AIDA setup and DAQ start complete
      writing to file TapeData/NULL/R1
 7x 
  22   Thu Jan 24 17:16:32 2019 CA, TD, NH, VPMACB time switch settingsAIDA@DESPEC MACB time switch settings before
and after WR are as follows.
 50668223_286084358731841_9104059387265155072_n.jpgdespecmacb.pdf 