821
|
Thu May 30 03:13:04 2019 |
TD | Thursday 30 May |
11.13 DAQ continues OK
|
16x |
546
|
Wed Mar 29 18:02:12 2017 |
OH, TD, DK, CG | Thursday 30th March | 02:02 Recovered DAQ from crash. Merger became
clogged and the system required a full restart.
Raspberry pi also
|
31x |
213
|
Thu May 5 11:10:36 2016 |
CG,PV,TD | Thursday 5 May 2016 | Detector configuration - see https://elog.ph.ed.ac.uk/AIDA/193
Ribbon cable to nnaida19 FEE adaptor PCB |
8x |
830
|
Thu Jun 6 08:55:15 2019 |
TD | Thursday 6 June | 16.40 DAQ continues OK
ASIC settings 2019May19-17.54.03
|
13x |
371
|
Thu Oct 6 11:16:40 2016 |
CG & TD | Thursday 6 October |
DSSSD bias voltages and leakage currents
OK - see attachments 1 & 2
|
9x |
933
|
Thu Dec 7 17:30:36 2023 |
NH, CC, VP, TD | Thursday 7 December |
Stack re-assembled - upstream to downstream
|
8x |
102
|
Thu May 7 01:32:39 2015 |
JA, TD, AE, CG & JLT | Thursday 7 May 2015 | 09.25 R69 continues
100Kr setting, degrader 4mm + 0.4mm
(variable) Al
|
|
644
|
Thu Jun 8 00:54:26 2017 |
OH, PW | Thursday 8 June 00:00-16-00 | 08:54 DAQ still running
09:01 BRIKEN and BigRIPS stop daqs
|
6x |
645
|
Thu Jun 8 08:11:39 2017 |
NN, PV | Thursday 8 June 16:00 - 24:00 (evening shift) | 16:13 DAQ still running
16:34 BigRIPS and BRIKEN stop their DAQ
|
22x |
769
|
Thu Nov 8 00:55:18 2018 |
CA, CB, TD, OH | Thursday 8th November | 09.57 DAQ still running (R29_29)
System wide checks ok, except nnaida7
ADC calibration failure
|
14x |
223
|
Thu May 12 16:55:37 2016 |
AE, VP, BM | Thursday May 12 | Continued work on beta-trigger for EURICA.
However the system seems to have different
noise condition than before, which
|
7x |
620
|
Thu Jun 1 00:00:25 2017 |
TD, PV, CB | Thusrday 1 June 08.00-16.00 | 07.57 run continues
BRIKEN start run 55
BigRIPS start run 1066
|
17x |
51
|
Thu Mar 5 12:11:44 2015 |
TD | To Do list - March 2015 | A draft 'to do' list in preparation for further
AIDA tests at RIKEN from mid-April.
|
|
56
|
Sat Apr 18 09:30:11 2015 |
CG | To do list 19/04/15 - 21/04/15 | To do (roughly in order):
Move shipped boxes
down from Gabor's office to the experimental |
|
15
|
Thu Oct 2 15:23:38 2014 |
Patrick Coleman-Smith and Chris Griffin | Trial with Filtered AIDA PSU | Assembled three more of the filter boards
and installed them in the AIDA PSU with the
first, wired to use the switchmode power |
|
214
|
Thu May 5 14:44:48 2016 |
Patrick | Trigger selection explanations | Please request more information if the
attached is not clear. |
|
7
|
Thu Sep 18 11:18:46 2014 |
Patrick Coleman-Smith | Trying the Liverpool HV supply | The SY1527 supply was delivered with three
modules.
A cable has been made with LEMO00 |
|
36
|
Tue Feb 17 06:32:24 2015 |
CG, AE, TD | Tues 17th Feb progress | 17/02/15
1515: Installed detector BB18 2977-7
with 3 modified kapton cables, one unmodified |
22x |
48
|
Tue Feb 24 03:04:59 2015 |
CG, TD | Tues 24th Feb progress | 24/02/15
1200: Update the FEE firmware on
nnaida1-16 without problem. |
9x |
287
|
Mon Jun 6 19:26:38 2016 |
CG, DK, BM, AE | Tues 7th June | 02.08 Tried updating AIDA SYNC on stats
page and got this message.
|