Tue Aug 9 13:44:16 2022, TD, JM, Tuesday 9 August    
|
14.00 CARME vacuum c. 1.8e-10 mbar - see attachment 1
|
Wed Aug 10 10:30:04 2022, TD, JM, Wednesday 10 August   
|
09.45 Found CARME electrical power off
|
Fri Aug 12 09:06:57 2022, TD, JM, Noise tests pt2 30x
|
10.07 DSSSD bias -100V leakage current -8.65uA
|
Sun Aug 14 06:50:58 2022, TD, JM, Sunday 14 August 10x
|
07.51 DAQ continues files 22Feb/R97
|
Mon Jan 29 15:32:08 2024, TD, JM, Monday 29 January contd. 16x
|
Test + and test - daisy chain cabling extended from DSSSD #1 to #2 to DSSSD #1 to DSSSD #4
terminated by 50 Ohm at end of daisy chain
|
Wed Apr 23 11:08:34 2025, TD, JM, Background Run 11x
|
12.08 DSSSD bias & leakage current - attachments 1-2
CAEN logger program crashed sometime this am - now restarted
|
Thu Apr 18 13:34:06 2024, TD, JG, Thursday 18 April 13x
|
14.30
|
Sat May 24 08:28:14 2025, TD, EM, Background runs R13-R16 29x
|
Summary: Target not running. Some background files written to disk, some with beam some without.
09.27 DAQ going
|
Wed Feb 23 21:27:29 2022, TD, CN, check 11x
|
Motor position ok
Data rate: 1030kbytes/s
T ok |
Fri May 10 21:23:35 2024, TD, CB, JM, 20Ne7+ test beam 18x
|
22.00
Carsten Brandau stopping e-target experiment Unattended beam overnight. No operators watching.
10^5 (nominal) 20Ne7+ at 380keV/u beam available |
Tue Jun 17 23:51:58 2025, TD, CB, JG, Run 96 - continued 23x
|
00.31 DAQ continues data file G22-205/R96_27
|
Wed Nov 10 14:41:12 2021, TD RSS + CB (remotely), Wrapping CARME in heating tape
|
ML reports that baking of the upstream section (gas jet interaction chamber plus e-target) has commenced - initially to 50 deg C to check thermocouples.
If OK baking
temperature will be ramped slowly (which I think means c. 10 deg C per h) to limits established for specific components by the e-target.
|
Tue Aug 10 12:22:56 2021, TD RSS, Tuesday 10 August  
|
Attachments 1-3 - 2 of 4 SAES D2000 installed at same ports used for STFC DL XHV tests |
Wed Aug 11 12:30:40 2021, TD RSS, Wednesday 11 August 8x
|
Attachments 1 & 2 - 2x SAES D-2000 re-fitted to side ports
all 4x SAES D-2000 now re-fitted to chamber
|
Thu Aug 12 09:16:42 2021, TD RSS, Thursday 12 August 13x
|
Attachment 1 - IE414/514 feedthrough wiring diagram
|
Thu Oct 14 15:54:47 2021, TD RSS, Thursday 14 October 
|
Attachment 1 - what is function of the 4x c/s holes indicated?
|
Sun Oct 17 11:48:48 2021, TD RSS, Sunday 17 October 14x
|
Looking downstream the RHS motor assembly has loose green/yellow (gnd?) see attachment 1
Install blank base plate to trial install in downstream CARME chamber. The rod is just through all of the mounting holes - see attachments 2 & 3
|
Sun Feb 27 12:49:44 2022, TD RSS, Sunday 27 February 07:00-15:00 6x
|
13.50 Cryostat set point 120K
|
Mon Jan 29 08:52:07 2024, TD JM, Monday 29 January 32x
|
09.50 CARME IE514 5.1e-11 mbar ( ambient temperature 16 deg C )
|
Wed Feb 23 18:58:12 2022, TD CN, Wednesday 23 February 15.00-23.00 shift 6x
|
Assorted screenshots of the CARME, CRYRING and gas jet target control systems in operation
|