  682   Tue Oct 24 03:16:07 2017 TD, OHTuesday 24 October11.16 DAQ continues
      AIDA file Oct17/R8_107
 20x 
  683   Wed Oct 25 03:26:55 2017 TD, OHWednesday 25 October11.27 DAQ continues
      Not writing to disk
 7x 
  684   Wed Oct 25 18:36:46 2017 TD, OHThursday 26 October02.37 DAQ stalled - USB-controlled ac mains
relay fuse blown
      Not writing to disk
 28x 
  685   Fri Oct 27 01:58:44 2017 TD, OHFriday 27 October09.56 DAQ stopped OK yesterday

      BNC PB-4
 12x 
  687   Sat Oct 28 03:33:10 2017 TD, OHSaturday 28 October11.33 DAQ running OK - date transfer not enabled

      BNC PB-4
 13x 
  690   Sun Oct 29 05:16:35 2017 TD, OHSunday 29 October14.16 DAQ running OK - data transfer not enabled

      BNC PB-4
 14x 
  691   Mon Oct 30 01:10:28 2017 TD, OHMonday 30 October10.10 DAQ running OK - data transfer not enabled

      BNC PB-4
 8x 
  692   Tue Oct 31 00:34:10 2017 TD, OHTuesday 31 October09.34 DAQ running OK - data transfer not enabled

      BNC PB-4
 8x 
  695   Thu Nov 2 01:56:18 2017 TD, OHThursday 2 November 10.56 DAQ running OK - data transfer not enabled

      BNC PB-4
 16x 
  697   Fri Nov 3 23:09:36 2017 TD, OHSaturday 4 November08.09 DAQ running OK - data transfer not enabled

      BNC PB-4
 20x 
  716   Thu Jun 21 02:31:49 2018 TD, OHThursday 21 June10.20 DAQ continues OK

10.29 DAQ stop June18/R1
 30.png31.png32.png33.png34.png 
  717   Thu Jun 21 05:23:16 2018 TD, OHOffline analysis R1 - alpha background
Analysis of overnight alpha background run
(June18/R1_0 ... _2) indicates that all FEE64s
 8x 
  718   Thu Jun 21 06:48:22 2018 TD, OHDSSSD HV cablingThe DSSSD HV cabling has been changed in preparation
for configuration change
from 6x DSSSDs to 8x DSSSDs as follows:
 50.png51.png 
  720   Sat Jun 23 02:28:13 2018 TD, OHNew fuses fitted to USB-controlled ac mains relay
The input fuses of the USB-controlled ac
mains relay have been changed from 2x 5x20mm
 2290195.pdf 
  924   Sat Nov 18 02:28:26 2023 TD, NH, JBSaturday 18 November03.20 c. 3k per spill 13N beam to S4
      Observe scatter of events at all energies
for LEC
 10x 
  935   Fri Dec 8 12:55:38 2023 TD, NHFEE64 configuration
FEE64 configuration for 1x MSL type BB18(DS)-1000
24cm x 8cm DSSSD
  
  281   Mon Jun 6 11:17:30 2016 TD, ML & YSRe-configure merger to ignore nnaida19
19.00 Power-cycled and rebooted AIDA FEE64s
 11.png12.png 
  282   Mon Jun 6 13:46:45 2016 TD, ML & YS/var/log/messagesaidas1 log  messages 
  283   Mon Jun 6 13:52:10 2016 TD, ML & YSFEE64 power-cycle, FEE64 & aidas1 reboot
21.40 toggled merge input pause state  -
merge pause stopped at link 18 (nnaida19
  
  284   Mon Jun 6 14:24:07 2016 TD, ML & YSR1118 (AIDA)22.14 R1118 starts

      aidas1 has been rebooted