89
|
Mon Sep 27 21:33:50 2021 |
CB (remotely) | CARME baking status -7 | Current temperature ~87 C, increasing
See plot and screen attached.
Thermocouple on CARME foot side (1-4) may |
|
100
|
Fri Oct 1 21:47:51 2021 |
CB (remotely) | CARME baking status -16 | Current temperature ~132 C (on manual mode
RE72-1: 132 C, RE72-2: 130 C)
See plot and screen attached.
|
|
164
|
Sun Nov 28 15:57:45 2021 |
CB (remotely) | Nov 2021 temperatures | Attached |
|
166
|
Tue Dec 7 09:39:59 2021 |
CB (remotely) | Gate valves closed | Dry run complete.
YR09 section valves closed. Section
isolated. Manual valve between electron target |
|
49
|
Tue Aug 31 18:56:35 2021 |
CB | CARME status | (ELOG does not allow more pictures to be added
to previous entry) |
9x |
115
|
Sat Oct 9 09:47:33 2021 |
CB | To do list for next week | 0. Give split-funnels to OG or Grossmontage
to clean. Mount back foot support for gate
valves. Critical when we split. |
|
194
|
Mon Feb 14 09:56:39 2022 |
CB | Shifters instructions 2022 | EMERGENCY SHUTDOWNS
1. CARME motors: Q key
on keyboard while on workspace 1 of appc218 |
10x |
236
|
Tue Feb 22 12:23:23 2022 |
CB | Slow comparator thresholds lowered - test run | 13:20 Stopped run.
Slow comp thresh 0x64 -> 0x32
on all FEEs |
|
282
|
Fri Feb 25 11:20:30 2022 |
CB | Pressure and temperature data saved | Saved pressure reading and temperature
data logs from internal target in /TapeServer/22Feb/OtherData
Leakage current data is saved in |
|
437
|
Wed Aug 30 10:28:36 2023 |
CB | Preparing for pumps on | We need to connect the non-bakeable (max
80C) wire of the ion pump belonging to the
vacuum division, and we also need to connect |
|
438
|
Thu Aug 31 08:36:34 2023 |
CB | NEG activation | Found CARME at 50C, a bit cooler than expected,
probably due to invasive tent changes yesterday
to mount missing wires. Increased heaters |
|
439
|
Fri Sep 1 08:11:40 2023 |
CB | NEG activation - 2 | 9:10 Set heaters temperature 300 ->
250 C in preparation for cooling down and
to help keep DSSD temperature down. Started |
|
440
|
Sat Sep 2 10:04:55 2023 |
CB | Turbo GV closed | Found CARME in XHV at 1.1E-11 mbar. Chamber
temperature around 30C cooling slowly.
Closed GV to top turbo. Pressure |
|
453
|
Sun Oct 15 09:35:03 2023 |
CB | Starting ramp down | 10:40 - Status as attached. Heaters setpoint/read
at 250 C, 150 C, 225 C. Power stable at 53%,
41%, 63% |
|
454
|
Mon Oct 16 08:28:02 2023 |
CB | NEG activation -1 | 9:00 - Michael's online vacuum pressure
plot is no longer working - an old image
is being displayed. CARME temperatures around |
|
455
|
Tue Oct 17 08:43:47 2023 |
CB | NEG activation -2 | 09:40 - Found temperature and pressure
stablised, but too high to comfortably activate
NEGs closest to detectors. Detector temperature |
|
495
|
Tue Feb 6 09:39:54 2024 |
CB | Detector bias tests | 10:30 Found ADC#4 on aida 1 and 4 are suddenly
noisy. See attach 1-2. Checkloaded multiple
times - no effect. |
13x |
527
|
Sun Feb 18 13:58:33 2024 |
AR, OF, JM | Run 42 - cooled beam on target | Run 42 - 15:00
Detectors IN (left arm pot =36.54
mm, right arm pot = 70.49 mm). Stationary. |
27x |
501
|
Fri Feb 9 07:57:38 2024 |
AR, CB, AB, JM | Run10 - First cool beam on target | 8:58
System wide checks okay, except
|
27x |
380
|
Mon Nov 28 13:14:33 2022 |
AR TD | Monday 28 November | |
12x |