126
|
Sun Nov 12 18:32:52 2017 |
MB DK | run 112 | Header: 4.4 MeV/u CH2_16 sample
Ender:
====================================================
|
|
|
192
|
Thu Oct 4 13:07:33 2018 |
KG | Schematics for gas-cell tests | in_atmosphere.png : schematic for testing
gas-cell in atmosphere
|
 |
|
199
|
Thu Oct 25 13:25:16 2018 |
KG | Current gas cell status | (Wrapped up)
Cell b : 15um Al exit, 12.5um Al entrance. |
|
|
55
|
Thu Nov 9 01:24:01 2017 |
Daid. Mirco | Run 54 | Header: Continue with 5.0 MeV/u and CH2
Ender: Checked control room, about 2:40.
Target current is 2 A (low...should be 430 |
|
|
56
|
Thu Nov 9 03:32:55 2017 |
Daid. Mirco | Run 55 | Header: Continue 5.0 MeV/u with CH2 after
target re-heating
Ender: End
|
 |
|
58
|
Thu Nov 9 05:35:44 2017 |
Daid. Mirco | Run 56 |
Header: 5.0 MeV/u CH2, Laser 2 is turned
off on purpose to check background.
|
|
|
59
|
Thu Nov 9 06:02:41 2017 |
Daid. Mirco | Run 57 | Header: Continue with 5.0 MeV/u and CH2.
Laser back on.
Ender:
|
|
|
92
|
Sat Nov 11 00:01:41 2017 |
Daid. Mirco | Trigger and scalars for 4.0 MeV/u | Tom et al. tuned the trigger this evening,
before we began the runs. (Run 82, or Run
83??)
|
|
|
53
|
Wed Nov 8 23:14:38 2017 |
Daid, Ruchi, Mirco | Run 53 | Header: Restart 5.0 MeV/u w/ CH2 after PS
comes back (3 rings until the morning)
Ender: End
|
|
|
46
|
Wed Nov 8 20:40:33 2017 |
Daid, Ruchi | Run 49 | Header: First test with RIB. Irises closed.
End: End
|
|
|
47
|
Wed Nov 8 20:46:23 2017 |
Daid, Ruchi | Run 50 | Header: First run with irises open. 30 min
run.
Ender: Call from PS-Booster. Stop run.
|
|
|
52
|
Wed Nov 8 23:06:48 2017 |
Daid, Ruchi | Run 52 (junk) | (Junk -- see comments)
====================================================
Run number : 52
|
|
|
60
|
Thu Nov 9 06:30:35 2017 |
Daid, Mirco | Spectra (Shift 1) | Screen shots for accumulated data before the
target went down. Should be (at least) runs
53 & 54 inclusive, possibly back to the start |
12x |
|
50
|
Wed Nov 8 22:08:55 2017 |
Daid | Run 51 | Header: Restart 5.0 MeV/u CH2 with 3 PS rings.
Ender: Stop run. We want good data with
a smaller file size for fast analysis, as |
|
|
54
|
Wed Nov 8 23:46:32 2017 |
Daid | Charge State Distributions | Faraday cup readout at the end of our chamber
should change based on whether or not the
target is in and also the 59Cu beam energy.
|
    |
|
109
|
Sat Nov 11 17:45:10 2017 |
DK, TD, ASM, RG, MD | Run 97 | Header: CH2 target in, Laser #2 off, 4.0 MeV/u
Ender: Stopped run to modify DAQ trigger
|
|
|
1
|
Fri Jan 27 11:02:03 2017 |
DK, PB | Notes from visit to CERN | Here I am simply digitizing my notes from
our visit to CERN 17~18 January 2017. They
may not be perfectly linear or organized, |
|
|
193
|
Mon Oct 8 12:05:25 2018 |
DK, PB | Gas cell supports | These are used to connect the gas cell to
the target ladder. We only had the one,
and it would be more convenient if each gas |
|
|
129
|
Sun Nov 12 23:52:10 2017 |
DK, MD, RG | Run 115 - short | Header: Continue 4.4 MeV / u @ CH2
Ender: Run stopped short as the IHS tripped
====================================================
|
|
|
167
|
Wed Nov 15 05:26:46 2017 |
DK, MD, CLW | Run 153 | Header: Continue with CH2 and 5.0 MeV/u
Ender: end of beam time
====================================================
|
|