ID |
Date |
Author |
Subject |
Text |
 |
738
|
Wed Jun 11 10:13:42 2025 |
EW, CB, PJW | Run 67 | As run 66, optimisation of beam completed
DSSD4 now working and thresholds
to 0x30 (480keV), working switched to LEC |
 |
737
|
Wed Jun 11 09:16:55 2025 |
CB | ASIC Control Settings | 11 June 10:18
2025Apr08-13.45.30 settings
DSSD4 not working as of the screenshots |
17x |
736
|
Wed Jun 11 08:37:48 2025 |
CB, PJW | Run 66 | 09:38
As Run 67, no changes, CRYRING
operators attempting to improve beam intensity. |
 |
735
|
Tue Jun 10 22:38:59 2025 |
JM, CB, PJW | Run 65 | 23:40
Offline anlaysis shows two clear
peaks for DSSD1 and 2 at very low energies |
7x |
734
|
Tue Jun 10 16:46:39 2025 |
JM, CB, EW, AY, PC | 150 keV - Run64 | Run 64 started.
150 keV/u beam on target, Target
overlap confirmed with lifetime measurement |
42x |
733
|
Tue Jun 10 13:29:23 2025 |
EW, CB, JM | Thresholds changed | Experimented with slow comparator thresholds
as we go down to lower beam energies
Checked deadlayer loses with SRIM, |
   |
732
|
Tue Jun 10 09:57:50 2025 |
CB, JM, PJW, YuL, JG | Run 62 | 10:58
As Run 61, no target for background.
200 keV/A |
|
731
|
Tue Jun 10 09:44:33 2025 |
JG | MBS not running for a week | The MBS daq was not writing data since
June 2. 22:39 (run_0035.lmd)
This means, no detector and target |
|
730
|
Tue Jun 10 09:44:30 2025 |
JG | MBS not running for a week | The MBS daq was not writing data since June
2. 22:39 (run_0035.lmd)
The reason is that
the rfio server was running on atppc025 which |
|
729
|
Tue Jun 10 09:44:20 2025 |
JG | MBS not running for a week | The MBS daq was not writing data since June
2. 22:39 (run_0035.lmd)
The reason is that
the rfio server was running on atppc025 which |
|
728
|
Sun Jun 8 11:55:00 2025 |
EM, PC, JM, CB, EW, AY, CB, PJW, YuL | Run 58,59,60, 61 | 12:52
Started Run 58 - Beam energy
200 keV/u. |
50x |
727
|
Sun Jun 8 10:05:30 2025 |
EM, PC, JM | Run57 | 11:06
Run during beam change. We will
go down to 200 keV/u |
|
726
|
Sun Jun 8 09:07:22 2025 |
EM, PC, JM | Run56 | NOTE: RunR55 is missing
Run56: Background run with 250
keV/u. Target off using the usual procedure. |
 |
725
|
Sat Jun 7 10:23:26 2025 |
JM, CB | carme-gsi rebooted | 10:00
The computer screen controlling
the DAQ on carme-gsi appeared to have crashed. |
|
724
|
Sat Jun 7 10:06:27 2025 |
JM, EM, CB, DB, AY, PC, CB | Run 54 | 11:10
We have started a new run at the
same energy as R53 (250 keV/u) due to an |
50x |
723
|
Fri Jun 6 17:27:03 2025 |
AY, ST, JM, EM, DB | Run 53 | Run 53 started at 18:25 (started already
earlier but since then data is taken). Everything
is running again. We started at 3E12 at/cm2. |
11x |
722
|
Fri Jun 6 16:49:59 2025 |
CB, AY, ST | Beam overlap results for 200keV and 250keV | For 200keV the optimal horizontal position
is -5mm.
For 250keV the optimal horizontal |
|
721
|
Thu Jun 5 16:54:18 2025 |
EW, ST, CB | Run 52 - 0.3 MeV/A | Run 52 started at 17:53. Everything is
running again. We started at 3E12 at/cm2
D+ beam deuterium target. D+ beam |
14x |
720
|
Thu Jun 5 08:50:00 2025 |
JM, CF, CB, EW | Run 51 - background | 09:49
DSSD4 has been biased to 100V in
steps of 5V from 60V. It was previously stable |
  |
719
|
Wed Jun 4 10:44:36 2025 |
EW, CB, JM, OF, JG, ST | Run 50 - 0.35 MeV/A | 11:30
Run 50 started.
D+ beam deuterium target. D+ beam |
13x |
718
|
Wed Jun 4 00:10:39 2025 |
JM | Run 49 - beam only | 01:10
Gas target turned off via the shutter
valve. |
6x |
717
|
Tue Jun 3 14:54:29 2025 |
PMH, ST | Run 48 | Run 48 started. Everything is running again.
We started at 3E13 at/cm2
D+ beam deuterium target. D+ beam |
6x |
716
|
Tue Jun 3 11:16:07 2025 |
EW, EM, JM | Run 47, beam only background | Run 47 started. Target cooling down after
water cooler failure, beam only background
D+ beam deuterium target. D+ beam |
 |
715
|
Mon Jun 2 20:03:43 2025 |
JG, AG, CB, EW, EM | Run 45/46, 0.5 MeV/A | Run 45 started.
D+ beam deuterium target. D+ beam
energy is 0.5 MeV/u. (beam calc calculation |
13x |
714
|
Mon Jun 2 17:48:07 2025 |
JG, AG | Run 44 scraper tests | Same settings are Run 43 but with coasting
beam and scrapers set to: 30 / - 30
mm. |
 |
713
|
Mon Jun 2 17:25:31 2025 |
JG, AG | Run 43 scraper tests | Same settings are Run 42 but bunched beam
and scrapers set to: 30 / - 30 mm.
|
|
712
|
Mon Jun 2 16:35:35 2025 |
EW, AG | Run 42 and scraper tests | 17:00
Scraper tests conducted. We tried
moving in the scrapers both at a fixed position |
 |
711
|
Mon Jun 2 09:30:38 2025 |
JM, EW, ST | Run 41 | Run 41 started.
D+ beam deuterium target. D+ beam
energy is 0.75 MeV/u. (beam calc calculation |
6x |
710
|
Sun Jun 1 15:33:50 2025 |
EW, JM, CB | Run 40 | 16:30
Run 40 started.
D+ beam deuterium target. D+ beam |
10x |
709
|
Sun Jun 1 07:46:34 2025 |
JM, EM, CB | Run 39 | 08:45
Run 39 started.
D+ beam deuterium target. D+ beam |
7x |
708
|
Sat May 31 10:46:42 2025 |
TD | Run 38 - remote monitoring |
11.40 DAQ continues
File G22-205/R38
|
21x |
707
|
Sat May 31 09:58:21 2025 |
JM | Run 38 | 10:56
Run 38 started.
D+ beam deuterium target. D+ beam |
10x |
706
|
Fri May 30 21:49:08 2025 |
JM, NP, CB | Run 37 | 22:49
Run 37 started.
D+ beam deuterium target. D+ beam |
  |
705
|
Fri May 30 20:47:47 2025 |
JM, CB, NP | Run 36 | 21:47
Run 36 started.
D+ beam deuterium target. D+ beam |
 |
704
|
Fri May 30 20:06:48 2025 |
JM, CB, NP | Run35 | 21:00
Run 35 started.
D+ beam deuterium target. D+ beam |
8x |
703
|
Fri May 30 07:27:41 2025 |
CB LB JM NP EM | Waiting for deuterium | 08:27
No run going.
Temperatures OK - attach |
8x |
702
|
Thu May 29 18:04:47 2025 |
LB, CB, PMH, JM | Run 32,33,34 | Oven temperature increased, current up
to 3.5E7 pps.
Found beam-target overlap setting |
7x |
701
|
Thu May 29 14:39:52 2025 |
CB LB PMH | Run 31 | 15:40
Waiting for Serge to come in to
change beam energy. |
9x |
700
|
Wed May 28 16:40:48 2025 |
EH, SN, LB, OF, EBM, CB | Run 28/29/30 - 1.88 MeV/A | We start a new run with real data taking
condititon: beam is ok, target density is
1e12 cm-2, detectors are moving in-out periodically. |
37x |
699
|
Wed May 28 10:54:14 2025 |
LB | Run 27 | Run 27 running
28/05/2025
(ignore 26 - in-between run) |
    |
698
|
Tue May 27 22:20:11 2025 |
CB, LB,PW | Run 25 - 1.99/2.02 MeV/A | 23:20
JM thinks we cannot see 7Be locus
on run 24. Possibly the right arm cannot |
27x |
697
|
Tue May 27 15:18:46 2025 |
JG, CN, JM | run 24 | Run 24 running
27/05/2025
We start a new run with real data |
7x |
696
|
Tue May 27 12:49:48 2025 |
ML | Ion beam / electron beam settings so far. | Screenshots and ParamModi settings export
attached. |
    |
695
|
Tue May 27 08:38:29 2025 |
TD | [How To] Recover DAQ when one FEE64 stops sending data - short(er) version | 1) Select 'No Storage' [workspace 4, display
1, browser tab 'TapeServer']
If already in 'No Storage' mode please |
|
694
|
Tue May 27 05:24:05 2025 |
LB,SN, L. Cs. P. J. W. | Run 22, 23 - 1.95 MeV/A | 27/05/2025 ca. 6:00
We start a new run: beam is ok,
target density ok, detectors are moving in-out |
8x |
693
|
Tue May 27 05:03:41 2025 |
JM | DAQ restart | 06:00
FEE modules power cycled.
No issues on power cycle restart. |
7x |
692
|
Mon May 26 18:37:17 2025 |
LC, AG, LB, SN | Run 21 | Run 21 running
26/05/2025 19:42 p.m.
We start a new run with real data |
12x |
691
|
Mon May 26 08:56:56 2025 |
EM,LB | Run20 | Run 20 running
We start a new run since the laser
guys will do some measurements. |
8x |
690
|
Sat May 24 18:27:55 2025 |
EM, LC | Background runs continued R17-R19 | Summary: Target not running. Background
runs written to disk, some with beam some
without. |
36x |
689
|
Sat May 24 08:28:14 2025 |
TD, EM | Background runs R13-R16 | Summary: Target not running. Some background
files written to disk, some with beam some
without.
|
29x |
688
|
Fri May 23 09:19:40 2025 |
SN, TD | Target wait, switch lithium oven |
10.12 DAQ, Merger & Tape Server running OK
- no storage mode
|
18x |
687
|
Thu May 22 06:41:10 2025 |
JG, TD | R6 - R11 scrapers test / pulser walk | 07.00
JG found target off (target data stopped |
33x |
686
|
Wed May 21 14:38:22 2025 |
JM, TD | R4 and R5 - background | 15:30
Waiting for the target to cool
down. ETA is 16:30 for cooling to be finished |
7x |
685
|
Tue May 20 19:38:36 2025 |
JM | CARME restart | 19:00
Arrived at GSI.
We have 6Li1+ beam in the ring |
6x |
684
|
Sat May 17 11:19:06 2025 |
JM | Shifter intructions 2025 | EMERGENCY SHUTDOWNS
1. CARME motors: Q key
on keyboard while on workspace 1 of appc218 |
|
683
|
Tue May 13 15:07:42 2025 |
JM | Online monitoring code | CARME_Sort histogramming has been updated
to aid our understanding online.
> XY plots have been updated |
  |
682
|
Mon May 12 13:25:09 2025 |
JG | target/ring DAQ - overview | An MBS DAQ is running to collect two types
of data:
|
|
681
|
Sat Apr 26 22:01:37 2025 |
CB | Proxy bridge | Proxy bridge enabling anydesk and generic
Internet access dropped due to atppc025 being
rebooted. Found it dropped again late today. |
|
680
|
Wed Apr 23 11:08:34 2025 |
TD, JM | Background Run |
12.08 DSSSD bias & leakage current - attachments
1-2
|
11x |
679
|
Tue Apr 22 06:44:02 2025 |
TD | Tuesday 22 April |
07.40 DSSSD bias & leakage current - attachments
1-3
|
    |
678
|
Sun Apr 20 07:30:29 2025 |
CB | DSSD leakage currents over Easter | Just after midnight on 20/04 it appears
DSSD #4 leakage current has perfectly stabilised.
See attached. |
  |
677
|
Fri Apr 18 16:18:33 2025 |
JM | D+D BBN energies test | D+D minimum energy Ecm = 150 keV which
corresponds to Ed=150 keV/u or Ed=300
keV. Therefore we need a threshold |
16x |
676
|
Fri Apr 18 08:17:38 2025 |
JM | More testing | 09:10
Arrived at GSI. Leakage currents
status same as before, DSSD4 is still fluctuating. |
15x |
675
|
Thu Apr 17 08:51:29 2025 |
JM | Grounding cont. | 09:00
Came in to see the bias for DSSD4
which has been fluctuating for the past few |
29x |
674
|
Wed Apr 16 08:20:05 2025 |
JM | Grounding | 09:00
Leakage currents this morning again
appear to have lowered during the night. |
14x |
673
|
Tue Apr 15 12:23:10 2025 |
JM | Leakage current / CARME issues | 14/04/25
Arrived at GSI in the afternoon.
Found that the coolant loop on |
18x |
672
|
Thu Apr 10 10:53:14 2025 |
TD | Thursday 10 April | 11.50 DAQ continues
Data file APR25/R6_13
|
8x |
671
|
Thu Apr 10 07:02:12 2025 |
CB (remotely) | Current logging enabled - sort of | There appear to be issues with Shahab's
caenlogging program. It crashes occasionally,
with an error indicating the number of columns |
|
670
|
Wed Apr 9 10:02:21 2025 |
TD | CARME equipment in CRYRING area moved |
There was some tidying up of the CRYRING
hall in advance of this week's EC evaluation |
 |
669
|
Wed Apr 9 02:40:04 2025 |
TD | Wednesday 9 April | 03.37 DAQ continues
Data file APR25/R5_8
|
11x |
668
|
Tue Apr 8 10:46:13 2025 |
TD | Tuesday 8 April |
11.30 CRYRING vacuum and temperature - attachments
1-2
|
27x |
667
|
Mon Apr 7 08:59:41 2025 |
TD | Monday 7 April |
10.00 FEE64 power ON
CARME IE514 OFF
|
8x |
666
|
Sun Apr 6 14:21:53 2025 |
TD | [How To] Startup CARME |
- water flow/interlock checks
check water flow to/from inflow/outflow |
|
665
|
Sun Apr 6 11:40:48 2025 |
TD | Options DB reconstructed | Options directory corrupted unable to change
Options settings per https://elog.ph.ed.ac.uk/CARME/664
|
|
664
|
Sun Apr 6 10:17:49 2025 |
TD | Sunday 6 April |
11.15 CARME IE514 ion gauge remains OFF
ML says there are 2x ion gauges with |
15x |
663
|
Sat Apr 5 16:15:04 2025 |
TD | FEE64 power interlock installed |
Water flow and dew point sensors have been
installed on the outlet and inlet cooling |
11x |
662
|
Sat Apr 5 16:13:32 2025 |
TD | Saturday 5 April |
12.00 CARME IE514 ion gauge 4.2e-11 mbar
CARME IE514 OFF
|
7x |
661
|
Fri Apr 4 10:17:16 2025 |
TD | Friday 4 April |
10.43 Reboot carme-gsi - unable to open a
working terminal
|
|
660
|
Mon Mar 10 15:47:27 2025 |
TD | Analysis data files G22-201 R79_10 & R79_24 |
Analysis of data files G22-201 R79_10 and
R79_24 - attachments 1-2
|
 |