Entry  Tue Feb 18 14:39:26 2020, Thomas Chillery, Target Thicknesses Target_List.xls
Excel spreadsheet showing CH2 and natC target thicknesses attached
Entry  Wed Sep 18 14:01:13 2019, Thomas Chillery, Logbook Spreadsheet 181123_Logbook.xls
See attached for the logbook
Entry  Tue Dec 4 11:23:29 2018, Thomas Chillery, Chamber Dimensions IMG_3397.JPGIMG_3398.JPGIMG_3399.JPG
See attached pictures for measurements of the 7Be(p,p) chamber dimensions.

The target ladder center - Far S2 distance = 50 + 95 + 0.85 - (19.22+19.58)/2 = 126.45 mm
Entry  Tue Dec 4 09:40:31 2018, Thomas Chillery, Preliminary measurements of target activation using geiger counter 
On 29/11/2018 at 17:40 a rough measurement of the irradiated target activity was performed using a geiger counter.

The geiger counter was a calibrated Berthold LB124, which was placed a fixed 15mm distance from each target.

The calibration was such that 1cps = 37kBq.
Entry  Tue Dec 4 09:38:18 2018, Thomas Chillery, 181122 Electronics Map 181122_Electronics_Channel_Map.ods181122_Electronics_Channel_Map.xls
See attached for S2 electronics map, following channels from S2 outputs to ADC inputs

For the 19/11/2018 - 29/11/2018 beamtime only the Far S2 was in operation
Entry  Mon Dec 3 19:04:20 2018, Thomas Chillery, Raffaele Buompane, End of beamtime - Items to be shipped back to Edinburgh 
To be shipped back to Edinburgh for repair:





Item

Quantity


ECL - NIM Convertor
2


Quad HV Supply
1


Quad
Entry  Mon Dec 3 18:55:31 2018, Thomas Chillery, Raffaele Buompane, End of beamtime - Cleanup 8x
On 29/11/2018:

Dismounted S2 2323-18 (496um), 12um mylar, diode, and diodes 0.9um mylar.

Performed general cleanup of lab. Boxed away cables and other parts. See attached pictures 1, 2, 3, and 4.
Entry  Mon Dec 3 18:45:17 2018, Thomas Chillery, Raffaele Buompane, End of beamtime - Module settings 
Diode Ortec 571 Amplifier Settings:


Fine gain: 10 (0.5 ->1.5)
Course gain: 50
Shaping time: 0.5us
BLR AUTO: ON
NEG: ON (Instead
of POS)
OUT: ON (Instead of Delay)
Internal fine gain: 1X


Diode quad TFA settings:
Entry  Mon Dec 3 18:30:53 2018, Thomas Chillery, Raffaele Buompane, Calibration with alpha source - 12um mylar on Far S2 IMG_3356.JPGIMG_3363.JPG181128184505_ADC1_Ch9.png
On 28/11/2018:

Mounted 12um mylar in front of far S2 - see attached pictures 1 and 2

In air: Far S2 biased to -130.0V, leak I = 1.61uA. Diode biased to -70.1V, leak I = 0.01uA -> 0.00uA. Rate meter ~ 4500Hz.
Entry  Mon Dec 3 18:15:42 2018, Thomas Chillery, Raffaele Buompane, Calibration with alpha source - no mylar on Far S2 IMG_3337.JPG182812_S2_Alpha_NoMylar.jpg
On 28/11/2018:

At 13:35: Far S2 bias = -130.0V, leak I = 1.55uA. Diode bias = -70.1V, leak I = 0.00uA.

Pressures (mBar):
Entry  Mon Dec 3 17:59:48 2018, Thomas Chillery, Raffaele Buompane, Calibration with alpha source - 0.9um mylar on Far S2 IMG_3305.JPGIMG_3307.JPGIMG_3315.JPGIMG_3313.JPG181128123940_ADC1_Ch9.png
On 28/11/2018:

After pulser walkthrough (see eLog entry #67)

Dismounted targets from ladder - see picture 1 and 2 for upstream and downstream sides respectively
Entry  Mon Dec 3 17:51:46 2018, Thomas Chillery, Raffaele Buompane, Pulser Walkthrough 182811_PulserWalkthrough.jpg
On 28/11/2018:

Performed pulser walkthrough, Run # 181128090835


Run time: 1986s
Pulser ON, amplitude changed
Target: None
Beam: None
DT ~ 11%
See
Entry  Mon Dec 3 17:40:51 2018, Thomas Chillery, Carlo Bruno, Raffaele Buompane, Lab background 181127200709_ADC1_Ch9.png181127200709_ADC3_Ch16.png
On 27/11/2018:

Run # 181127200709


Run time: 46329s
Pulser ON, as before
No target
No beam
Lab background
DT ~ 12%
See
Entry  Mon Dec 3 17:34:38 2018, Thomas Chillery, Carlo Bruno, Raffaele Buompane, 6Li(p,p): Test measurement of 1.5MeV 6Li 1+ on thin CH2 50 181127193908_ADC1_Ch9.png181127193908_ADC3_Ch16.png
On 27/11/2018:

After tuning beam (see previous eLog entry # 64)

Run #181127193908
Entry  Mon Dec 3 17:02:48 2018, Thomas Chillery, Carlo Bruno, Lizeth Morales, Guiseppe Porzio, Raffaele Buompane, 6Li(p,p): Tuning 1.5MeV 6Li 1+ beam IMG_3285.JPGIMG_3292.JPG
On 27/11/2018:

Started tuning for 1.5MeV 6Li 1+. Set ladder to position #2 - Blank 10mm. Far S2 iris closed.

Run # 181127151653
Entry  Mon Dec 3 16:47:40 2018, Thomas Chillery, Carlo Bruno, Lizeth Morales, Finishing 3.0MeV 7Be measurements with CH2 XIX and natC III 181127085408_ADC1_Ch9.png181127085408_ADC3_Ch16.png181127090808_ADC1_24.png181127092128_ADC1_Ch9.png181127092128_ADC3_Ch16.png
On 27/11/2018:

At 8:40 Far S2 bias = -130.0V, leak I = 1.74uA. Diode bias = -70.1V, leak I = 0.00uA.

Pressures (mBar):
Entry  Mon Dec 3 16:39:42 2018, Thomas Chillery, Carlo Bruno, Tom Davinson, Raffaele Buompane, 3.0MeV 7Be on CH2 XIX 181126192446_ADC1_Ch9.png181126192446_ADC3_Ch16.png
On 26/11/2018:

Tuned beam for 3.0MeV 7Be 2+. Far S2 iris was closed during tuning.

After tuning, using 10mm aperture FCC = 5pA, using 3mm aperture FCC = 4pA.
Entry  Mon Dec 3 16:17:29 2018, Thomas Chillery, Carlo Bruno, Tom Davinson, Raffaele Buompane, David Rapagni, 3.0MeV 7Li on CH2 XIX and natC III 181126164509_ADC1_24.png181126183711_ADC1_Ch9.png181126183711_ADC3_Ch16.png
On 26/11/2018, after changing the far S2 mylar foil (see previous eLog entry #60):

Checked pulser frequency on oscilloscope: 19.31Hz

Began tuning 3MeV 7Li 2+.
Entry  Mon Dec 3 15:51:11 2018, Thomas Chillery, Carlo Bruno, Tom Davinson, David Rapagni, Changing far S2 protective mylar foil, preparing for 3.0MeV 7Li and 7Be IMG_3273.JPG
On 26/11/2018, after 6.0MeV 7Be and 7Li beam measurements:

At 11:15:

Far S2 bias = -130.0V, leak I = 1.60uA. Diode bias = -70.1V, leak I = 0.00uA.
Entry  Mon Dec 3 12:57:54 2018, Thomas Chillery, Carlo Bruno, Tom Davinson, David Rapagni, Finishing 6.0MeV 7Be 2+ and 7Li 2+ beam runs 181126105357_ADC1_Ch9.png181126105357_ADC3_Ch16.png
On 26/11/2018:

The accelerator and chamber setup were still operating after the overnight run.

Far S2 bias = -130V, leak I = 1.59uA. Diode bias = -70.1V, leak I = 0.00uA.
Entry  Mon Dec 3 12:32:54 2018, Thomas Chillery, Carlo Bruno, Tom Davinson, Lucio Gialanella, Raffaele Buompane, 6.0MeV 7Be on CH2 XVIII 181125121226_ADC1_Ch9.png181125121226_ADC3_Ch16.png181125223800_ADC1_Ch9.png181125223800_ADC3_Ch16.png
On 25/11/2018:

The beam was tuned for 6.0MeV 7Be 2+

Using 10mm aperture FCC = 12 pA
Entry  Mon Dec 3 11:54:55 2018, Thomas Chillery, Carlo Bruno, Tom Davinson, Raffaele Buompane, 7Li 6.0 MeV on CH2 XVI and XVIII, and on natC III 181125113734_ADC1_Ch9.png181125113734_ADC3_Ch16.png
On 25/11/2018:

At 8:45 the pressures read (mBar):


TPU1 = 1.0e-6
TPU2 = 3.2e-7
TPD1 = 6.5e-7
TPD2 = 6.1e-7
CHUP = Sensor Off
CHDW
Entry  Mon Dec 3 11:28:53 2018, Thomas Chillery, Carlo Bruno, Tom Davinson, Lucio Gialanella, Antonino d'Leva, 7Be 4.0MeV on CH2 XVI and natC III 181124120558_ADC1_Ch9.png181124120558_ADC3_Ch16.png181124182304_ADC1_Ch9.png181124182304_ADC3_Ch16.png
On 24/11/2018:

After the short test with 4.0MeV 7Li (see eLog #55) the beam was tuned for 4.0MeV 7Be 2+.

Run # 181124103943
Entry  Mon Nov 26 17:13:45 2018, Thomas Chillery, Carlo Bruno, Tom Davinson, Lucio Gialanella, Preparing chamber for 4MeV 7Be 2+ beam IMG_3231.JPGIMG_3232.JPG
On 24/11/2018:

At 8:35 the chamber pressures read (mBar):


TPU1 = 2.2
TPU2 = 2.2
TPD1 = 2.2
TPD2 = 2.0
CHUP = Sensor Off
CHDW = No Sensor


The
Entry  Mon Nov 26 17:10:13 2018, Thomas Chillery, Marialuisa Aliotta, Carlo Bruno, Tom Davinson, Raffaele Buompane, 7Li 4.0 MeV beam on natC target 3 
On 23/11/2018:

After the runs with 7Li on CH2 15, we moved the target ladder to position 5: carbon foil #3 (~590 ug/cm^2)

Run # 181123214406
Entry  Sat Nov 24 16:39:22 2018, Thomas Chillery, Marialuisa Aliotta, Carlo Bruno, Tom Davinson, Raffaele Buompane, 7Li 4.0 MeV beam on CH2 target 15 
On 23/11/2018:

Tuned beam for 4.0 MeV 7Li, charge state 2+

Measured transmission of beam through FCC using 3 mm and 10 mm size collimators: 66 pA with 10 mm -> 60 pA with 3 mm -> 91% transmission
Entry  Sat Nov 24 16:29:10 2018, Thomas Chillery, Marialuisa Aliotta, Carlo Bruno, Tom Davinson, Raffaele Buompane, Preparing setup for 7Li beam 
On 23/11/2018:

10:15 started pumping down chamber with Ecodry 2

RAL thresholds:
Entry  Sat Nov 24 15:07:00 2018, Thomas Chillery, Marialuisa Aliotta, Carlo Bruno, Lizeth Morales, Tom Davinson, Searching for causes of noise 
On 22/11/2018 in the afternoon:

We increased the ADC thresholds to 40 (previously 8).

For an alpha source with pulser connected, the event multiplicity dropped from ~63 to ~10. Dead time ~ 7%
Entry  Sat Nov 24 15:05:40 2018, Thomas Chillery, Marialuisa Aliotta, Carlo Bruno, Lizeth Morales, FAIR DAQ 
The FAIR DAQ IP address: 192.168.1.90

The data is saved in /Local_Parts/Part0DE/

After each run we should copy the data to the 7Be shift folder: /home/circe/7Be_pp/181122/
Entry  Thu Nov 22 11:53:08 2018, Thomas Chillery, Marialuisa Aliotta, Carlo Bruno, Lizeth Morales, DAQ tests with alpha source IMG_3329.JPGAlphaSourceCertificate.jpg
The target ladder is set for position 7 - the double alpha source.

Looking at the FAIR DAQ, for the Far S2 the first RAL amplifier (XV) shows:


Alphas at channel 700
Pulser centroid at channel ~2640, with 9 channel FWHM -> corresponds to 44 keV FWHM at 4.91 keV/channel


The
Entry  Thu Nov 22 11:34:07 2018, Thomas Chillery, Marialuisa Aliotta, Carlo Bruno, Lizeth Morales, Continuing Electronic Chain Tests 
This morning at 8:35am the pressures read (in mBar):


TPU1 = 2.0e-6
TPU2 = 4.5e-7
TPD1 = 8.1e-7
TPD2 = 7.9e-7
CHUP = 4.7e-7
CHDW = 1.1e-5


The
detectors were biased. Far S2 leak I = 1.54uA, near S2 leak I = 12.53uA.
Entry  Wed Nov 21 09:34:26 2018, Thomas Chillery, Marialuisa Aliotta, Carlo Bruno, Setting up chamber both for tests under vacuum and physics measurement IMG_3223.JPGIMG_3224.JPG
Today we mounted the far aperture used to control the far iris. No problems were encountered with this.

We mounted the target ladder with the following configuration, see also pictures 1 and 2:




Target #
Target


I
Blank
Entry  Wed Nov 21 09:28:06 2018, Thomas Chillery, Marialuisa Aliotta, Carlo Bruno, Lizeth Morales, Problem encountered with near iris arm 
On 20/11/2018:

After the electronics tests in air (see eLog entry #44) we started to setup the chamber for vacuum tests with an alpha source.

We started mounting the aperture used for controlling the near iris arm, however we encountered a problem. The iris arm got stuck and could not
Entry  Wed Nov 21 09:09:41 2018, Thomas Chillery, Marialuisa Aliotta, Carlo Bruno, Lizeth Morales, David Rapagni, Mounting Detectors / Continuing Electronic Chain Tests IMG_3209.JPG
On 20/11/2018:

At 9:00 we walked into the lab, David R reported he found all the pumps OFF. A thunderstorm occurred overnight causing a power outage.

Last night we had switched off the electronics (Preamp power, RAL amp rack, and NIM bin).
Entry  Wed Nov 21 08:53:06 2018, Thomas Chillery, Marialuisa Aliotta, Carlo Bruno, Lizeth Morales, Testing Electronic Chain - No Detectors 
On 19/11/2018:

During the vacuum test - see eLog entry #43 we performed noise tests on the preamplifiers with no S2 detector connected

First we performed a "tabletop" test - the preamplifiers were not connected to the chamber.
Entry  Wed Nov 21 08:45:03 2018, Thomas Chillery, Marialuisa Aliotta, Raffaele Buompane, Carlo Bruno, Testing Chamber Vacuum 
On 19/11/2018:

We mounted the following in the chamber:


Iris frames - no S2 detectors or mylar
Si pin diode mount with 0.9um mylar - no diode
Target ladder with blank
Entry  Wed Nov 21 08:37:24 2018, Thomas Chillery, Marialuisa Aliotta, Raffaele Buompane, Upstream Collimator IMG_3391_Modified.JPG
On 19/11/2018:

During the target ladder calibration (see elog entry #41) we also replaced the collimator (thickness ~24mm, diameter 3mm) located immediately
upstream from the target ladder - that is between the upstream and central sections of the chamber. We mounted an aluminium collimator (thickness ~1mm,
Entry  Wed Nov 21 08:18:14 2018, Thomas Chillery, Marialuisa Aliotta, Checking Target Ladder Calibration IMG_3204.JPGIMG_3205.JPGIMG_3200.JPG
On 19/11/2018:

There were three CH2 targets already mounted on the target frame, CH2 III, IV, and a damaged target. We dismounted these.

We noticed these previous target were mounted on the incorrect side of the target ladder, resulting in them being offset upstream from the central
Entry  Wed Jul 11 15:55:35 2018, Thomas Chillery, Electronics Channel Map Electronics_Channel_Map.ods
See attached for Electronics Channel Map spreadsheet.

This is valid for the February 2018 Beamtime; it maps out the Far S2 Strips onto the ADC channels

A map should be produced and updated for each beamtime to ensure S2 Strip -> ADC Channel is correctly documented.
Entry  Fri Apr 13 15:08:04 2018, Thomas Chillery, Lucio Gialanella, End of shift - lab cleanup 
Date: 07/04/2018

Began dismounting detectors:


All detectors powered off
Closed line and quadrupole valves
Preamp power off
Stopped turbos
Closed
Entry  Fri Apr 13 14:56:11 2018, Thomas Chillery, Lucio Gialanella, 7Be 5.0MeV Beam test on CH2 target IV with central S2 and downstream S2 channels 0-7  
Date: 07/04/2018

FC - 4 = 410 - 260 = 150 pA

We moved the target ladder to position V (35.022mm) - CH2 Target IV
Entry  Fri Apr 13 14:42:31 2018, Thomas Chillery, Lucio Gialanella, 7Be 5.0MeV Beam test on CH2 target III with central S2 and downstream S2 channels 0-7  
Date: 07/04/2018

To run the measurement we:


Opened the central iris (actuator setting = 14.0mm)
Opened the downstream iris (actuator setting = 1.5mm)
Set the
Entry  Fri Apr 13 14:31:59 2018, Thomas Chillery, Lucio Gialanella, Setting up for 7Be 5.0MeV beam 
Date: 07/04/2018

We changed to cathod 23 - 7Be

For beam tuning we:
Entry  Fri Apr 13 13:59:18 2018, Thomas Chillery, Lucio Gialanella, 7Li 5.0MeV Beam test with Central S2 and Downstream S2 first 8 channels 180407_7Li_5MeV_CentralS2_FrontStrip.png180407_7Li_5MeV_DWS2_FrontStrip.png180407_7Li_5MeV_CentralS2_BackStrip.png180407_7Li_5MeV_Diode.png
Date: 07/04/2018

At 12:10 we started the DAQ for 5.0 MeV 7Li in 2+ charge state bombarding CH2 Target III


Save name: RData_1/180407111531
DT = 0%
Trigger rate ~ 30 Hz
Event mult = 77.5


At
Entry  Fri Apr 13 08:24:47 2018, Thomas Chillery, Lucio Gialanella, Attempting to add downstream S2 to DAQ setup and fixing problems during setup 
Date: 07/04/2018 (Last day of April shift)

9:55 pressures read: CHUP = 1.3e-5 mBar, CHDW = 3.5 e-5 mBar

I noticed the preamp power (+/- 15V) was left on overnight. The +15V still draws 1.5A and -15V draws ~600mA as expected. During this shift no
Entry  Thu Apr 12 14:14:09 2018, Thomas Chillery, Raffaele Buompane, 7Be 5.0MeV Beam test with central S2 180406_7Be_5MeV_CentralS2_BackStrip.jpg180406_7Be_5MeV_Diode.jpg180406_7Be_5MeV_CentralS2_FrontStrip.jpg
Date: 06/04/2018

Before starting this beam test we lowered the channel thresholds on ADC 3 and 4 (modules 4 and 5) from 40 to 8

The diode Ortec 571 settings are:
Entry  Thu Apr 12 13:12:00 2018, Thomas Chillery, Raffaele Buompane, 7Li 5.0MeV Beam tests with Central S2 
Date: 06/04/2018 (after 16:40)

We powered the preamps for the two S2 detectors and the diode.

We biased the detectors:
Entry  Thu Apr 12 12:47:04 2018, Thomas Chillery, Raffaele Buompane, Central S2 Alpha Calibration 
Date: 06/04/2018

We connected the analogue signals of RAL X, XII, XIII, and "R" to the 3rd ADC (Module 4)

We connected the analogue signals of RAL "S", "Q", "u", and "w" to the 4th ADC (Module 5)
Entry  Fri Apr 6 14:54:12 2018, Thomas Chillery, Raffaele Buomparte, Tests - Attempting to solve noise issues 
Today we started by mounting the central and downstream preamp box lids.

The pumps were left running overnight, at 9:06 CHUP = 2.1e-5mBar and CHDW = 5.8e-5mBar.

We biased the detectors
Entry  Fri Apr 6 13:33:27 2018, Thomas Chillery, Raffaele Buomparte, David Rapagni, Jeremias Duartes, Tests - Attempting to solve noise issues 
On 05/04/18, after eLog #28

After the alpha calibrationrun Raffaele arrived and started beam tuning for 7Li 2+ at 5.0MeV using a LiO molecular source

We set the target ladder to position II (80.024 mm) - no target frame or target
Entry  Fri Apr 6 12:07:52 2018, Thomas Chillery, Raffaele Buomparte, David Rapagni, Jeremias Duartes, Tests - Attempting to solve noise issues, 15 min alpha calibration S2_2323-18_496um_Bias_Vs_Leakage_Current_050418.png
On 05/04/18:

At 9:00 the pressures read ~10mBar inside the chamber (static vacuum). We began venting the chamber.

During venting the cable daisy chain on top of the preamp boxes was removed, the downstream preamp box was removed. It was decided to also removed
Entry  Fri Apr 6 11:39:10 2018, Thomas Chillery, Raffaele Buompane, David Rapagnani, Lucio Gialanella, Tests - Pumping down chamber and starting electronics tests S2_2323-18_496um_Bias_Vs_Leakage_Current.pngS2_2623-26_505um_Bias_Vs_Leakage_Current.png20180404_Pulser_PreampLid_ON.jpg20180404_Pulser_DisconnectedFromFeedthrough.jpg
On 04/04/18:

We mounted S2 2323-18 (496um) in the downstream position with 12um mylar

We mount the central and downstream iris arms, we set the central arm position to 14.0mm and the downstream arm position toe 1.5mm - opening
Entry  Tue Apr 3 18:16:26 2018, Thomas Chillery, Lizeth Morales, Raffaele Buompane, Lucio Gialanella, Tests - Unpacking and Mounting Chamber Parts  IMG_2832.JPGIMG_2839.JPGIMG_2841.JPG
This morning I unpacked the chamber parts.

I mounted the downstream and central lids with the iris arm hooks to double check we could still successfully mount them, see previous eLog entry
(#25) for photos from this procedure performed in Edinburgh.
Entry  Tue Mar 27 16:36:01 2018, Thomas Chillery, Peter Black, Tests - Modifying Chamber Parts in Edinburgh 11x
Between 7th to 21st March modifications were made to the top of the CIRCE target chamber.

These modifications address the three key issues highlighted during the February shifts

1. The central S2 detector did not fit, because its connector pins came into contact with the chamber lid
Entry  Wed Mar 7 16:56:52 2018, Thomas Chillery, Peter Black, Tests - Modifying Chamber Parts in Edinburgh 
Today we began examining and modifying parts of the chamber shipped from CIRCE to Edinburgh.

The parts shipped were:


Chamber Collar
Central Lid
Downstream Lid
Two Metal Detector Masks
Two Iris Mounts
One
Entry  Tue Mar 6 15:55:04 2018, Thomas Chillery, Raffaele Buompane, End of February 2018 Shifts 
On 23/02/2018:

At the end of the February 2018 shifts the detectors bias settings were:

S2 bias = -130.3V, leak I = 2.42uA
Entry  Tue Mar 6 15:41:53 2018, Thomas Chillery, Raffaele Buompane, Pin Diode Pulser Walkthrough at End of February Shifts 180223_PulserWalk_PinDiode_ADC6CH31.png
On 23/02/2018:

After the alpha source calibration of the S2 (See eLog entry #21) we decided to perform a pulser walkthrough for the pin diode on ADC 6 CH 31.

The pulser was only connected to the pin diode preamp to ensure it wasnt being split.
Entry  Tue Mar 6 15:29:55 2018, Thomas Chillery, Raffaele Buompane, Collecting S2 Alpha Calibration Spectra at End of February Test Shifts 180223_Alpha_S2FrontStrip_ADC2CH20.png180223_Alpha_S2BackStrip_ADC4CH24.png
On 23/02/2018:

We moved the target ladder to position 7, 5.019mm, with the alpha source facing downsteam.

At 17:17 we started the DAQ for a 15 minute alpha spectrum on the downstream S2. Save name: /Remote_Objs/RData_1/180223172135
Entry  Sun Feb 25 15:59:38 2018, Thomas Chillery, Lizeth Morales, Raffaele Buompane, David Rapagnani, Lucio Gialanella, Measurement - 3.45MeV 7Li on CH2 Target III 180223_S2FrontStrip_ADC2CH20.png180223_S2BackStrip_ADC4CH24.png180223_PinDiode_ADC6CH31.png
On 23/02/2018 at 13:49 we started the DAQ in list mode.

After starting the DAQ we sent the 3.45MeV 7Li beam onto the CH2 930ug/cm2 target III.

The trigger rate ~ 2kHz, event multiplicity = 6.1, dead time ~ 9%.
Entry  Sun Feb 25 15:14:54 2018, Thomas Chillery, Lizeth Morales, David Rapagnani, Setup - Beam Tuning and Prepare Chamber for Measurement at 3.45MeV 7Li - Morning of 23rd 
On the morning of 23/02/18 we aimed to complete beam tuning of 7Li at 3.45MeV.

At 8:43 CHUP = 7.2e-6mBar, CHDW = 1.9e-5mBar.

The S2 bias was ramped to -130.3V, leak I = 1.67uA. The diode bias was ramped to -70.1V, leak I = 0.01uA. The preamp power was also switched
Entry  Fri Feb 23 13:15:05 2018, Thomas Chillery, Raffaele Buompane, David Rapagnani, Setup - Beam Tuning and Prepare Chamber for Measurement at 3.45MeV 7Li - Night of 22nd 
Checking SRIM 3.5 MeV 7Li is stopped in 9.06um mylar or 10.09 um CH2.

After the long run at 3.0MeV on 22/02/2018 we decided to put the 12um mylar back in front of the S2 and start tuning the beam for 3.45MeV 7Li.
We also decided to tune the beam to a higher current of ~ 100pA to try and improve the detection rates.
Entry  Thu Feb 22 18:04:12 2018, Thomas Chillery, Raffaele Buompane, David Rapagnani, Lucio Gialanella, Measurement - 3.0MeV 7Li on CH2 Target VII Nuclear_Reaction-master.xlsx180222_diode.jpg180222_ADC4CH24.jpg180222_ADC2CH7.jpgPinDiode_AlphaSpectra.jpg
Yesterday (21st) night we saw this low channel, high rate (1500Hz) noise on the diode spectrum - see eLog entry #15.

This morning the S2 bias was ramped to -130.3V, leak I = 1.43uA. Diode bias ramped to -70.0V, leak I = 0.01uA.

Starting the DAQ with no beam, the trigger rate is ~250 Hz, with most triggers coming from the diode. Inspecting with the oscilloscope we find
Entry  Thu Feb 22 14:55:09 2018, Thomas Chillery, ADC6 Settings ADC6_Settings1.jpgADC6_Settings2.jpgADC6_Settings3.jpgADC6_Settings4.jpgADC6_Settings5.jpg
DAQ Settings for ADC6 settings attached. ADC 6 has been used for the pin diode during the week starting 19/02/2018
Entry  Thu Feb 22 10:40:49 2018, Thomas Chillery, Raffaele Buompane, David Rapagnani, Lucio Gialanella, Measurement / Test - 3.0MeV 7Li on CH2 Target VII 180221_PinDiode.png180221_S2BackStrip_ADC4CH24.png180221_S2FrontStrip_ADC2CH7.png
On 21/02/2018 after beam tuning and pumping down at 18:07 the pressures read Up = 1.2e-5mBar, Down = 3.2e-5mBar. We were happy to power the detectors
and try to observe spectra from beam in both the S2 and pin diode.

Whilst waiting for the turbos to spin up the Pin diode was daisy chained with the +ve pulser, +15V, and -15V preamp power cables used with EDI
Entry  Thu Feb 22 07:58:48 2018, Thomas Chillery, Tom Davinson, Raffaele Buompane, David Rapagnani, Lucio Gialanella, Setup - Beam Tuning and Prepare Chamber for Measurement at 3.0MeV 7Li IMG_2738.JPG
On 21/02/2018 we reattempted the beam tuning. We expected this to be easier now the rogue mylar is removed from the beamline.

At 8:30 we started the roughing pumps. At 8:37 the turbos were switched on. By 8:55 the preassures read: Up = 1.6e-5, and Down = 4.3e-5
mBar.
Entry  Wed Feb 21 10:46:22 2018, Thomas Chillery, Tom Davinson, Raffaele Buompane, David Rapagnani, Setup - Pulser Settings and 20/02/2018 Pulser Walkthrough BKG_zoombeam1.jpg
The PB-5 Pulse Generator settings are as follows:

Fall Time = 100us

Rate = 2.00Hz
Entry  Tue Feb 20 17:03:08 2018, Thomas Chillery, Tom Davinson, Raffaele Buompane, David Rapagnani, Setup - Beam Tuning IMG_2712.JPGIMG_2709.JPGIMG_2724.JPG
The pumps were left on overnight, in the morning at 8:25 the pressure reads:

Up = 1.5e-5 mBar and Down = 4.0e-5 mBar.

We made a first attempt at collecting an alpha spectrum for the far S2 detector using ADC 2 and ADC 3. However ADC 3 appeared to be acting as
Entry  Tue Feb 20 16:57:49 2018, Thomas Chillery, Screenshots - ADC 2 and ADC 4 settings, and example pulser walkthrough 11x
 
Entry  Tue Feb 20 09:19:19 2018, Thomas Chillery, Tom Davinson, Raffaele Buompane, David Rapagnani, Setup - Testing Chamber Vacuum and Mounting Detectors and Alpha Source 
(Note: Tom Davinson is now in CIRCE until the 21st)

On 19/02/2018 we performed the following:

This morning we gave CIRCE technician Antonio slanted spacer boxes (for mounting preamps) and also the Al box (used for target ladder) for minor
Entry  Sat Feb 17 13:00:51 2018, Thomas Chillery, Test - S2 Detector Bias 
This morning whilst I was setting up the ribbon cabling (see eLog entry #8) I was considering collecting a voltage bias vs leakage current curve for
one/two of the S2 detectors, depending on time available.

This would involve using the central section of the chamber and the straight spacer box to mount the preamp on top of the lid.
Entry  Sat Feb 17 12:35:25 2018, Thomas Chillery, Setup - Electronic Cabling IMG_2697.JPGIMG_2702.JPGIMG_2704.JPGIMG_2706.JPG
Between 9:00 to 12:30 this morning Filipo was working on the weekend 14C measurements, allowing me to work in the lab during this period.

I unpacked four MALU 4532 Lecroy Logic Modules (sent to CIRCE two weeks ago). Three of these modules were installed into the 1434A CAMAC crate,
which already had one module installed from the July 2017 shift. One module remains out of the crate as a spare.
Entry  Fri Feb 16 18:28:42 2018, Thomas Chillery, David Rapagnani, Setup - Testing Chamber Vacuum 
By 16:40 I mounted all three chamber lids.

The central chamber lid includes the diode detector mount, the iris, a vacuum feedthrough, and an actuator with no hook.

The downstream chamber lid includes a vacuum feedthrough and an actuator with no hook.
Entry  Fri Feb 16 18:21:17 2018, Thomas Chillery, Iris arm problems  IMG_2677.JPGApertureArm_PetersSolution.jpg
After lunch we were still having problems with the aperture hook, see first attached image highlighting the arm is located in close proximity (but not
touching) the vacuum feedthrough and ribbon cable.

Meanwhile in Edinburgh Peter Black designed and built an additional component of the hook to assist in connecting it between the actuator and
Entry  Fri Feb 16 18:10:34 2018, Thomas Chillery, David Rapagnani, Setup - Electronics Rack and Aperture Iris 
This morning we moved the electronics rack to within ~2.5m of the target chamber, leaving room for the ribbons cables of ~5m length which connect the
preamps to the amplifiers in the rack.

Then I continued in attempts to solve the iris arm problem, see eLog entry #3.
Entry  Thu Feb 15 20:45:27 2018, Thomas Chillery, Planning - Target Chamber CAD diagram solid_target_11.pdf
Find attached the latest CAD diagram of the Target Chamber, drawn by Peter Black
Entry  Thu Feb 15 17:45:07 2018, Thomas Chillery, Raffaele Buompane, Setup - Problem: Connecting the actuator arm to the iris aperture arm ApertureAdjustmentHooks.JPGApertureArm_TwoScrews.JPGIrisArmProblemSketch.JPG
After lunch we attempted to connect the actuator arms to the iris arm used to change the iris diameter. We need two iris diameters: fully open for experiment
measurements and a 5mm diameter for beam focusing

To do this the original design uses a cuboid with two rods, one rod is connected to the actuator arm, and the other rod is connected to the iris
Entry  Thu Feb 15 17:34:28 2018, Thomas Chillery, Raffaele Buompane, Setup - Mounting Target Chamber Sections IMG_2621.JPG
This morning both myself and Raffaele mounted the beamline section of the target chamber.

We also mounted the turbo located immediately downstream from the target chamber, see attached IMG_2621.jpg image - the beam will enter from
the right of the image
Entry  Tue Aug 1 12:26:13 2017, Thomas Chillery, 10th - 22nd July 2017 Summary Report Summary.docx
Attached is a report summarising work performed on the electronics and target chamber in CIRCE from the 10th to the 22nd July 2017.

Outstanding problems have also been listed.
ELOG V3.1.4-unknown