AIDA GELINA BRIKEN nToF CRIB ISOLDE CIRCE nTOFCapture DESPEC DTAS EDI_PSA 179Ta CARME StellarModelling DCF K40
  CARME  ELOG logo
ID Date Author Subject Text Attachments
  660   Mon Mar 10 15:47:27 2025 TDAnalysis data files G22-201 R79_10 & R79_24
Analysis of data files G22-201 R79_10 and
R79_24 - attachments 1-2
 R79_10.txtR79_24.txt 
  659   Tue Jul 2 17:43:32 2024 TDOffline analysis G22-201/R89Offline analysis data file G22-201/R89_0 to
R89_13 (c. 6h40m data)
 9x 
  658   Wed Jun 19 12:11:22 2024 CB, RSSCARME statusDSSD off

FEEs off

Motors out, pin inserted, compressed
  
  657   Wed Jun 19 12:08:34 2024 CB + variousRun 101-105Run 101: no target. See ELOG entry by TD.

Run 102: ??

Run 103: ??
  
  656   Wed Jun 19 12:06:50 2024 CB, OF, SSRun 98/99/100 - higher energy10:21 June 17

New energy: 1.125 MeV/u

Target in. Run 98 started.
  
  655   Wed Jun 19 12:04:02 2024 CB + OF, SSRun 96/97Run 96 - as run 89, while we wait for beam
energy change at higher energies

Run stopped around 08:56
  
  654   Wed Jun 19 12:01:29 2024 TD23:00-07:00 Wednesday 19 June23.18 DSSSD bias & leakage current OK - attachment
1
      FEE64 temps OK - attachment 2
 23x 
  653   Wed Jun 19 12:00:56 2024 CBRun 93/94/95 - background04:00 17 June

Moved the detectors back to the
usual configuration (as per run 89).
 6x 
  652   Wed Jun 19 11:54:26 2024 CBRun 91/92 - moving detectors~ 2:00 17 June

 

Run 91
 Screenshot_from_2024-06-18_03-07-50.pngScreenshot_from_2024-06-18_03-53-51.pngScreenshot_from_2024-06-18_04-20-15.pngScreenshot_from_2024-06-18_04-20-18.pngScreenshot_from_2024-06-18_04-20-21.png 
  651   Mon Jun 17 23:10:08 2024 CBRun 9000:10

As run 89, detectors moved fully
out.
 Screenshot_from_2024-06-18_01-21-47.pngScreenshot_from_2024-06-18_01-21-55.png 
  650   Mon Jun 17 16:26:00 2024 JM, RSS, CBRun 8917:20

(Run 87 Junk and Run 88 does not
exist)
 19x 
  649   Mon Jun 17 06:26:45 2024 JM, OF, AK, CBChange to 5+ beam07:00

We are changing to 5+ beam so that
we can access higher energies and possibly
 7x 
  648   Mon Jun 17 05:47:35 2024 JMRun 8606:50

No sign of the resonance during
night shift. New run started but when operators
  
  647   Mon Jun 17 04:01:16 2024 JMRun 8505:00

Cooler voltage setpoint 247.45
V.
  
  646   Mon Jun 17 02:05:37 2024 JMRun 8403:00

Cooler voltage setpoint 247.7 V.

FC20 read value 247.15 V.
  
  645   Mon Jun 17 00:05:13 2024 JMRun 8301:00

Cooler voltage setpoint 247.6 V.

FC20 read value 247.05 V.
  
  644   Sun Jun 16 22:49:22 2024 JMRun 8223:38

Cooler voltage setpoint 247.5 V.

FC20 read value 246.95 V.
  
  643   Sun Jun 16 22:40:11 2024 JMTarget overlap test - R8123:10

Beam set to bunched mode to observe
beam lifetime. 
 Beam-overlap-updated2.png 
  642   Sun Jun 16 19:01:30 2024 ML, EMRun 8020:00

Ecooler setpoint 246.8

Readout 246.25
  
  641   Sun Jun 16 13:51:11 2024 CB EM MLRun 7914:51

Ecooler setpoint 246.9

Readout 246.35
 7x 
  640   Sun Jun 16 13:29:05 2024 RSS CBRun 78Target clogged?   
  639   Sun Jun 16 06:02:31 2024 RSSRun 77Run 77 started at 06:48

Cooler voltage setpoint 247.0 V.

 
 20x 
  638   Sat Jun 15 21:14:56 2024 JM, JS, LCRun 7622:15

New run 76 - beam on target with
definite target overlap [coasting]
 Screenshot_from_2024-06-15_22-16-53.png 
  637   Sat Jun 15 13:30:18 2024 JM, JSRun 7514:30

New run 75 - beam on target with
definite target overlap [coasting]
 Screenshot_from_2024-06-15_15-53-57.pngScreenshot_from_2024-06-15_15-54-30.pngScreenshot_from_2024-06-15_15-54-55.png 
  636   Sat Jun 15 06:10:21 2024 EM, PMHRun 747:00

Cooler voltage setpoint 247.4 V.

 
 6x 
  635   Sat Jun 15 00:46:45 2024 TDCRYRING hall temperature transientCRYRING hall temperature transient - evening
of Friday 14 June
 Capture.PNG 
  634   Fri Jun 14 22:18:18 2024 RSS, CB, USRun 73Beam is back.New run started.

 

Cooler voltage setpoint 247.3 V.
 20x 
  633   Fri Jun 14 19:59:14 2024 US, LC, CBNew run with name of 72 is started due to target issue21:00

Target is lost. Background run
is being collected.
 Screenshot_from_2024-06-14_21-08-22.pngScreenshot_from_2024-06-14_21-08-22.png 
  632   Fri Jun 14 14:52:02 2024 JMBeam-Target Overlap ScanThe orbit of the beam in the ring was re-configured
so that the beam position is more central.

With the target density at ~6e11
 20240614_153532.jpgBeam-overlap-updated.png 
  631   Fri Jun 14 14:48:02 2024 CB NP ML[How To] Change target pressure. EMERGENCY ONLY!ONLY FOLLOW THESE INSTRUCTIONS if E1 turbo
is below 820 Hz, pressure in E1 is above
2.5E-1 mbar and experts (Nikos, Andreas)
 20240614_142435.jpg20240614_142440.jpg 
  630   Fri Jun 14 14:46:54 2024 LC, JM, CB, TD, USRun 71 - beam on target 15:45

New run 71 - beam on target with
definite target overlap [coasting]
 Screenshot_from_2024-06-14_16-35-44.pngScreenshot_from_2024-06-14_16-36-06.pngScreenshot_from_2024-06-14_16-36-28.pngScreenshot_from_2024-06-14_19-49-02.png 
  629   Fri Jun 14 13:45:21 2024 JM, JS, CB, TD, EHRun 70 - beam on target14:45

New run 70 - beam on target with
definite target overlap
 7x 
  628   Fri Jun 14 10:21:24 2024 JS, TDRun 68Frank has been tuning the beam since 08:00

detectors moved fully out

11:20
 9x 
  627   Thu Jun 13 23:01:07 2024 RSS, JS, EHRun 67 - Night shiftRun 67

00:01


      DSSSD bias & leakage
 20x 
  626   Thu Jun 13 21:07:30 2024 LCS, USRun 67- beam on target22:05

The energy is changed to 247.4
V.
 7x 
  625   Thu Jun 13 14:46:17 2024 TDR66 beam overlap test
15.45 Start data file G22-201/R66 
      Beam/target overlap test
  
  624   Thu Jun 13 09:48:25 2024 TD, LCSRun 65 - beam on target10:47

The energy is changed to 247.4
V.
 14x 
  623   Thu Jun 13 06:21:53 2024 TD, LCSRun 64 - contd07.22 E1 pump 799Hz, 2.8A, 2.6e-1 mbar, 4.8e+11/cm2

07.24 DSSSD bias & leakage current OK - attachment
 13x 
  622   Thu Jun 13 00:50:33 2024 JM, JSRun 64 - beam on target01:50

Right arm at 64.60 mm

Left arm IN at 36.54 mm
  
  621   Wed Jun 12 07:16:47 2024 RSS, YL, JM, TD, CBStatus07:56 Gleb has taken the beam to try settings
for the 5+ charge state. As soon as the target
is ready, the 1+ charge state will be given
 6x 
  620   Tue Jun 11 21:16:50 2024 TDRun 63 continuedRun 63 continued

22.06 DSSSD bias & leakage current OK - attachment
 17x 
  619   Tue Jun 11 20:10:25 2024 JMRun 63 - Beam only background21:00

Claude has achieved optimal cooling
parameters for the beam
  
  618   Tue Jun 11 19:44:48 2024 OF, SSTarget out and at HeTarget has been moved out and H2 switched
off. Changed to He.

Nikos will repair nozzle tomorrow
  
  617   Tue Jun 11 12:26:07 2024 RSS, JS, JM, CBRun 62 - Beam optimization + Target changeBeam optimization and target change   
  616   Tue Jun 11 08:34:50 2024 JM, RSS, JSRun 61 - beam on targetNew run 61

Right arm at 64.60 mm

Left arm IN at 36.54 mm
 Screenshot_from_2024-06-11_11-47-57.pngScreenshot_from_2024-06-11_11-48-20.pngScreenshot_from_2024-06-11_11-48-32.pngScreenshot_from_2024-06-11_11-48-44.png 
  615   Tue Jun 11 04:36:17 2024 CB, RSS, JSRun 60 - as 59, left servo in05:36

Run started.

Conditions as before, except left
 11x 
  614   Mon Jun 10 20:31:12 2024 JM, AK, EH, CBRun 59 Beam on target21:32

New run 59

Right arm at 64.60 mm
 18x 
  613   Mon Jun 10 18:22:47 2024 JMElectron cooler calculationsIon beam energy is calculated using Beamcalc
(https://web-docs.gsi.de/~lestinsk/beamcalc/electron.php)

Electron current is set to 4.3
 space-charge-2.pngspace-charge-1.pngBeamCalc.png 
  612   Mon Jun 10 14:26:52 2024 EH, AKRun 5815:30

Merger OK, Tape server OK

ADC data item statistics OK
 8x 
  611   Mon Jun 10 12:49:56 2024 RSS, DB, CB, JM R58 Space Charge Test
13:53

      DSSSD bias & leakage
current OK - attachment 1

      FEE64
temperatures OK - attachment 2

      ADC
 Screenshot_from_2024-06-10_13-52-45.pngScreenshot_from_2024-06-10_13-53-04.pngScreenshot_from_2024-06-10_13-53-17.pngScreenshot_from_2024-06-10_13-53-28.png 
  610   Mon Jun 10 07:40:47 2024 RSS, DBBeam08:26: There is no beam and Gleb is informed.

08:46: Beam is back.
  
  609   Mon Jun 10 05:24:49 2024 TD, RSS, DBR5706:45 New data file G22-201/R57

      Right arm at 64.60 mm
 16x 
  608   Sun Jun 9 22:14:23 2024 TD, PM, AGRun 56 - Data taking23:15 New run 56 with

      Right arm at 64.60 mm
 31x 
  607   Sun Jun 9 13:45:24 2024 CB PMH AGRun 55 - Data taking14:45

New run 55 with:

Right arm at 64.60 mm
 18x 
  606   Sun Jun 9 09:45:27 2024 JM, CBBeam-Target OverlapTarget density this morning had stabalised
at 7e11 at/cm2

This is sufficient to test the
 Beam-overlap.png 
  605   Sun Jun 9 08:30:49 2024 JM, CBRun 54 - beam on target09:30

New run 54 with:

Electron cooler setpoint
 7x 
  604   Sat Jun 8 20:32:17 2024 LB, JMRun 52 - beam on targetNew run 52 with:

Electron cooler setpoint
244.2 V
 Screenshot_from_2024-06-08_22-56-26.pngScreenshot_from_2024-06-09_00-17-44.pngScreenshot_from_2024-06-09_00-18-46.pngScreenshot_from_2024-06-09_01-50-54.pngScreenshot_from_2024-06-09_01-51-27.png 
  603   Sat Jun 8 17:46:12 2024 TD[How To] Cycle Left DSSSDs
Interactive Motion Program [workspace 6,
display 2]
  
  602   Sat Jun 8 14:49:14 2024 TDR51 - contd
15.40 DSSSD bias & leakage current OK - attachments
1-2
 30x 
  601   Sat Jun 8 10:13:52 2024 CB, JM, TDRun 50/51 - data taking11:13

ML enabled ring signals remotely.

Used FakeMotion.dat (read FakeMotion.dat
 8x 
  600   Sat Jun 8 06:13:21 2024 CBRun 47/48/49 - target issues & tests07:00

After putting the target back,
we observe strong periodic (5 s) fluctuations
 Screenshot_from_2024-06-08_07-15-27.pngScreenshot_from_2024-06-08_07-15-33.pngScreenshot_from_2024-06-08_10-13-16.pngScreenshot_from_2024-06-08_10-13-23.pngScreenshot_from_2024-06-08_10-13-26.png 
  599   Sat Jun 8 00:14:39 2024 LBRun 46 - background with beamRUN 46- started at 00:50

Horizontal beam position = 4.0
mm, vertical beam position = -5.0 mm.
 22x 
  598   Fri Jun 7 22:33:13 2024 LBRun 45 - tests on beam-target overlapTried to double check beam-target overlap
by changing beam horizontal coordinate.

In the tablethe counts in the 4000-5200
 Screenshot_from_2024-06-07_23-11-06.pngScreenshot_from_2024-06-07_23-12-17.pngScreenshot_from_2024-06-07_23-32-22.pngScreenshot_from_2024-06-07_23-43-43.pngScreenshot_from_2024-06-07_23-50-54.png 
  597   Fri Jun 7 15:53:35 2024 TDDSSD leakage current increase - temperature increase in CRYRING hallRe-increase in DSSSD leakage current c.
14-15.00 6.6.24 

There was a significant temperature
 Capture.PNG 
  596   Fri Jun 7 14:09:04 2024 JM, CB, DR, CN, LBRun 44 - 15N Data Taking15:35

Electron cooler voltage set point
= 244.3 V
  
  595   Fri Jun 7 10:05:40 2024 CBRun 41/42/43 - 15N data taking start11:05

Confirmed overlap is at 4 mm under
new settings.
 8x 
  594   Thu Jun 6 16:23:10 2024 LB CB JMRun 39 - Run 40 15NStarted run 39.

 

We have the 15N+ beam with 426
 15x 
  593   Thu Jun 6 05:44:45 2024 DR YL DB LB CB JMRun 38 - 15N Tests06:45

All system checks OK

Target density 3.4e11
 8x 
  592   Wed Jun 5 13:34:02 2024 JMRun 37 - Change in thresholds14:20

Target nozzle currently being replaced.
No beam
 Screenshot_from_2024-06-05_14-36-44.png 
  591   Wed Jun 5 13:21:45 2024 JM, CBRun 36 - pulser walkthrough14:00

Access to the cave as Nikos and
Andreas have begun work on the target.
 Screenshot_from_2024-06-05_14-20-18.pngScreenshot_from_2024-06-05_14-21-26.pngScreenshot_from_2024-06-05_14-27-43.pngScreenshot_from_2024-06-05_14-25-44.png 
  590   Wed Jun 5 08:34:04 2024 JM. DB, PCTarget nozzle change09:30

Target density has not improved
despite efforts last night. Mid 10 - low
  
  589   Tue Jun 4 19:19:26 2024 TD[How To] Recover DAQ when one FEE64 stops sending data1) STOP DAQ [workspace 2, display 1, browser
tab 'Run Control']
   all FEE64s should change status from 'going'
  
  588   Tue Jun 4 18:08:04 2024 Boudefla Dounia - CB - LB - SDRun 3419:08

Beam energy = 3 MeV.

Horizontal beam position = 4.0
 19x 
  587   Tue Jun 4 15:25:36 2024 BD US CBRun 3316:26

Merger OK, Tape server OK

ADC data item statistics looks
 Screenshot_from_2024-06-04_18-33-23.pngScreenshot_from_2024-06-04_18-33-38.pngScreenshot_from_2024-06-04_18-35-26.pngScreenshot_from_2024-06-04_18-36-55.png 
  586   Tue Jun 4 14:13:17 2024 JM, CB, DB, USRun 32- beam only background15:15

Run 32 started - Beam, no target

Beam energy = 3 MeV.
  
  585   Tue Jun 4 06:56:02 2024 DFF, PC, LB, JM,NP,ABRun 31 contd8:13

Since 6:40 the target density dramatically
dropped to 10^9 since then it has been unstable
 Screenshot_from_2024-06-04_10-53-58.pngScreenshot_from_2024-06-04_10-58-02.png 
  584   Tue Jun 4 00:04:39 2024 DR, EHRun 31Beam energy = 3 MeV

Horizontal beam position = 4.0
mm, vertical beam position = 0.0 mm.
  
  583   Mon Jun 3 21:37:20 2024 CN, EM, CBRun30Beam energy = 3 MeV

Horizontal beam position = 7.0
mm, vertical beam position = 0.0 mm.
 Screenshot_from_2024-06-03_23-15-37.pngScreenshot_from_2024-06-03_23-16-18.pngScreenshot_from_2024-06-03_23-17-16.png 
  582   Mon Jun 3 15:17:41 2024 CN, EM, CBRun29 16:15

In the previous run while working
on the target it was discovered that the
 Screenshot_from_2024-06-03_18-04-47.pngScreenshot_from_2024-06-03_18-05-11.pngScreenshot_from_2024-06-03_18-06-09.pngScreenshot_from_2024-06-03_18-06-40.pngScreenshot_from_2024-06-03_20-35-00.png 
  581   Mon Jun 3 15:10:12 2024 CN, EM, CBRun2816:10

We start a new run after doing
some test with the motor. Injection time
 Screenshot_from_2024-06-03_16-12-44.pngScreenshot_from_2024-06-03_16-13-11.pngScreenshot_from_2024-06-03_16-14-11.pngScreenshot_from_2024-06-03_16-16-37.png 
  580   Mon Jun 3 11:46:07 2024 SD, SHB, JM, CN, EMRun 2712:46 (attachments 1-4)

Run 27 started - Beam no target

Beam energy = 3 MeV
 12x 
  579   Mon Jun 3 08:43:22 2024 SD, SHBRun 2609:44

Run 26 started - Beam no target

Beam energy is being increased
 8x 
  578   Sun Jun 2 23:38:17 2024 JM, EMRun 25 00:38

Run 25 started - Beam on target

Beam energy = 1.5 MeV.
 32x 
  577   Sun Jun 2 22:46:47 2024 JM, EM, NPRun2423:47

Run 24 started - Beam on target

Beam energy is 1.5 MeV.
 Screenshot_from_2024-06-02_23-53-00.pngScreenshot_from_2024-06-02_23-53-47.pngScreenshot_from_2024-06-02_23-56-22.png 
  576   Sun Jun 2 14:30:16 2024 TDOffline analysis G22-201/R22_0 - R22_11Offline analysis data file G22-201/R22_0 to
R22_11
 8x 
  575   Sun Jun 2 13:04:41 2024 JM, AG, CB, DRRun 23 - vertical beam position and beam lifetime tests14:05

Run 22 stopped. Run 23 started
we will now adjust the vertical beam position
 Screenshot_from_2024-06-02_14-04-55.png 
  574   Sun Jun 2 08:47:01 2024 CB, AGRun 22 - longer rung with 20 min storage09:47

12 seconds pre acc

200x cycles
 Screenshot_from_2024-06-02_09-47-53.pngScreenshot_from_2024-06-02_09-48-06.pngScreenshot_from_2024-06-02_11-21-59.pngScreenshot_from_2024-06-02_11-22-27.pngScreenshot_from_2024-06-02_13-02-31.png 
  573   Sun Jun 2 06:41:00 2024 CB, AGRun 21 - tests07:41

Switching to bunched beam to check
D vs H content.
 10x 
  572   Sat Jun 1 21:56:17 2024 JM, EM, EM, TY, CB, AGRun 2022:56

Run 20 started - beam on target

Beam energy is 1.5 MeV. Horizontal
 18x 
  571   Sat Jun 1 16:38:13 2024 TDOffline analysis G22-201/R17Offline analysis data file G22-201/R17

Sort program variables https://elog.ph.ed.ac.uk/CARME/240530_180659/variables.dat
 8x 
  570   Sat Jun 1 13:33:50 2024 TDOffline analysis APR24/R3 (alpha background)
Offline analysis data file APR24/R3 (alpha
background)
 9x 
  569   Sat Jun 1 07:16:15 2024 CB, AB, EM, JMRun 19 - beam target overlapMorning shift

08:16 - as run 18, target off

9:00 Increased storage time to
 19x 
  568   Fri May 31 21:53:20 2024 CB EM, JM,EM ABOvernight beam tests22:53

Run 15 started

Beam tests. We increased the storage
 17x 
  567   Fri May 31 21:03:21 2024 CB, EMRun1422:03

Before this run we checked quickly 
beam with the target on but it does not make
 Screenshot_from_2024-05-31_22-05-57.pngScreenshot_from_2024-05-31_22-07-01.pngScreenshot_from_2024-05-31_22-07-49.png 
  566   Fri May 31 19:12:01 2024 CB, EMRun 13 - test with beam20:00

The beam is set at the correct
energy, operators cross-checked it again.
 Screenshot_from_2024-05-31_20-13-46.pngScreenshot_from_2024-05-31_20-27-58.pngScreenshot_from_2024-05-31_20-32-59.png 
  565   Fri May 31 06:01:55 2024 JM, TY, PW, EM, CBRun 12 - beam on target07:00

Run 12 started. D+ beam is incident
on the target at 1.5 MeV
 12x 
  564   Thu May 30 13:31:01 2024 JM, CB, PW, YLRun 11 - beam on target overlap14:30

Run 11 started. D+ beam in the
ring at 1.5 MeV.
 Screenshot_from_2024-05-30_14-33-19.pngScreenshot_from_2024-05-31_02-09-35.pngScreenshot_from_2024-05-31_06-57-12.png20240531_073828.jpg 
  563   Thu May 30 09:30:33 2024 CB, PW, YL, TDRun 1010:30

Merger OK, Tape server OK

ADC data item statistics looks
 13x 
  562   Thu May 30 08:33:21 2024 CB, PW, YLRun 8 & 9- detector motion tests09:34 - Moved to Run 9 in preparation of
moving detectors. No target yet. Beam in
the ring at 750 keV/A.
 7x 
  561   Thu May 30 07:25:53 2024 Yuri, Phil, NikosGas targetThe cave is closed and beam is back

The d intensity is about half of
the intensity before the break
  
  560   Thu May 30 06:00:51 2024 Yuri Nikos ...Open the caveNikos needs to enter the cave to work on
the target cooling.

 
  
  559   Wed May 29 17:42:06 2024 TDOffline analysis APR24/R2 (pulser walkthrough)ADC offsets using pulser walkthrough data
from data file APR24/R2
 17x 
  558   Wed May 29 16:46:21 2024 NP, AB, PMRun7 - Measurements only with ion beam.18:19 Start or run 7: In beam has been
optimzed up to now by Zoran and Claude. ~7E7
particles at injection. From now on, only
 Screenshot_from_2024-05-29_21-49-57.pngScreenshot_from_2024-05-29_21-50-14.png 
  557   Wed May 29 09:49:35 2024 JM, CBThreshold changes / D+ beam09:00

R4 alpha background continues,
currently R4_12
 Screenshot_from_2024-05-29_11-00-20.pngScreenshot_from_2024-05-29_11-01-30.pngScreenshot_from_2024-05-29_11-01-47.pngScreenshot_from_2024-05-29_11-02-03.png 
  556   Wed May 29 08:10:32 2024 JMRun4 - alpha background09:00

R4 alpha background continues,
currently R4_12
  
  555   Tue May 28 15:25:21 2024 TD, JM, CBPulser testsR3 started

Pulser ON. Approx 2 kHZ.

1.8*w waveforms attachments 1+2
 Screenshot_from_2024-05-28_16-14-56.pngScreenshot_from_2024-05-28_16-15-43.pngScreenshot_from_2024-05-28_16-16-18.pngScreenshot_from_2024-05-28_16-20-05.pngScreenshot_from_2024-05-28_16-28-46.png 
  554   Tue May 28 12:38:31 2024 TD, JM, CBRun 2 - Alpha background run
13.35 FEE64 temperatures OK - attachment
1
 Screenshot_from_2024-05-28_13-35-03.pngScreenshot_from_2024-05-28_13-34-30.pngScreenshot_from_2024-05-28_13-33-19.pngScreenshot_from_2024-05-28_13-36-30.pngScreenshot_from_2024-05-28_13-37-16.png 
  553   Mon May 27 15:25:08 2024 JMStartup27/05/24

The carme-gsi computer has been
moved from the server room into the shifter
  
  552   Fri May 10 21:23:35 2024 TD, CB, JM20Ne7+ test beam22.00

Carsten Brandau stopping e-target
experiment Unattended beam overnight. No
 18x 
  550   Sun Apr 28 23:12:11 2024 TDMonday 28 April00.09 DAQ continues data file R3_21

      DSSSD bias & leakage current OK - attachment
 21x 
  549   Sat Apr 27 23:16:02 2024 TDSunday 28 April
00.12 DAQ continues data file R3_15
 37x 
  548   Fri Apr 26 23:41:16 2024 TDSaturday 27 April
00.34 DAQ continues data file R3_9
 37x 
  547   Fri Apr 26 07:05:01 2024 TDFriday 26 April
08.02 DAQ continues data file R1_14
 19x 
  546   Thu Apr 25 02:31:25 2024 TDThursday 25 April
03.27 DAQ continues - file APR24/R1_7
 39x 
  545   Wed Apr 24 13:18:09 2024 TDExamples of poor CARME cable management/routing
Have observed some instances of poor CARME
cable management/routing
 20240424_125858.jpg20240424_125929.jpg 
  544   Wed Apr 24 12:48:35 2024 TDWednesday 24 April
      Replace AIDA ASIC mezzanine of aida01
 21x 
  543   Tue Apr 23 17:44:41 2024 TDTuesday 23 April
18.43 ASIC settings 2024Feb08-15.59.09
 12x 
  542   Fri Apr 19 02:47:59 2024 TDFriday 19 April
03.45
 12x 
  541   Thu Apr 18 13:34:06 2024 TD, JGThursday 18 April
14.30 
 13x 
  540   Wed Mar 6 10:47:11 2024 JG, TDWednesday 6 March - PEXARIA5 WR test
Courtesy Nik Kurz, JG has installed a PEXARIA5
PCIe card adjacent to CARME - BuTIS single-mode
 temps.PNGstats_1.PNGstats_2.PNGwr_0949.PNG 
  539   Wed Feb 21 07:38:32 2024 TDWedneday 21 February
10.54 23.2.24 Bias OFF
 24x 
  538   Tue Feb 20 14:12:32 2024 JMShutdownCARME DAQ shutdown. FEEs turned OFF and
all MIDAS server windows closed.

Detector bias turned OFF.
 Screenshot_from_2024-02-20_15-11-40.png 
  537   Tue Feb 20 13:20:44 2024 OF, AG, JG, MLR48 status checkDoing afternoon check. Checked the leakage
currents, all ok. Attachment 1

Temperatures ok, attchment 2
 Screenshot_from_2024-02-20_14-22-05.pngScreenshot_from_2024-02-20_14-22-49.pngScreenshot_from_2024-02-20_14-29-39.pngScreenshot_from_2024-02-20_14-34-55.png 
  536   Tue Feb 20 09:57:57 2024 OF, AG, MLRun 48 status checkDoing morning check. Checked the leakage
currents, all ok. Attachment 1

Temperatures ok, attchment 2
 Screenshot_from_2024-02-20_11-06-48.pngScreenshot_from_2024-02-20_11-08-05.pngScreenshot_from_2024-02-20_11-12-26.pngScreenshot_from_2024-02-20_11-13-58.png2024-02-20_11-37-46-304.png 
  535   Tue Feb 20 09:51:37 2024 JMRun 48 beam on targetRun 48 started   
  534   Tue Feb 20 08:41:08 2024 OF, AGstill no beam CRYRINGWe have mosty empty injections into CRYRING.
Only sporadically the beam with good intensity
is injected.
  
  533   Tue Feb 20 07:50:10 2024 JMDAQ restartDAQ restarted. Run46. All appears OK, aida01
shows high rates across ASIC 4 even with
no beam which could not be resolved via ASIC
  
  532   Mon Feb 19 21:46:32 2024 EH, EM, CBRun 45 + end of late shift22:54
We have moved the gas jet target out (y=4000),
the density has dropped to zero.
 14x 
  531   Mon Feb 19 08:45:22 2024 JM, JG, SHB, EM, EHRun 44 - cooled beam on target09:43

Run 44 started cooled beam
on target
 35x 
  530   Mon Feb 19 06:01:17 2024 SHB, JM, JGRun 42 morning shift07:00

Observed reduction in YR09 presure
over last few hours in ML online plot. Beam
 6x 
  529   Mon Feb 19 05:10:48 2024 TDRun 42 night shift contd.06.03 DAQ continues file G22-86/R42_32

      DSSSD bias & leakage current - attachments
 6x 
  528   Sun Feb 18 22:03:56 2024 TDRun 42 night shift
23.03 DAQ continues file G22-86/R42_21
 47x 
  527   Sun Feb 18 13:58:33 2024 AR, OF, JMRun 42 - cooled beam on targetRun 42 - 15:00

Detectors IN (left arm pot =36.54
mm, right arm pot = 70.49 mm). Stationary.
 27x 
  526   Sun Feb 18 13:10:18 2024 TDSunday 18 February - DSSSD 0 aida01 and aida04 *.*.L spectra
DSSSD 0 aida01 1*L spectra, aida04 **L spectra
 Screenshot_from_2024-02-18_13-58-29.pngScreenshot_from_2024-02-18_13-59-55.pngScreenshot_from_2024-02-18_14-01-19.pngScreenshot_from_2024-02-18_14-08-36.pngScreenshot_from_2024-02-18_14-09-44.png 
  525   Sun Feb 18 07:53:51 2024 HW AGRun 40 Morning Shift08:57 Doing morning check. Checked the
leakage currents, all ok. Attachment 1

Tempritures of, attchment 2
 27x 
  524   Sun Feb 18 00:16:55 2024 JM CBRun 40 - night shift01:17

Run 40 continues.

Beam intensity looks OK. Oscillates
 15x 
  523   Sat Feb 17 14:29:03 2024 JM, CB, AR, ABRun 40 - cooled beam on target15:27

Run 40 started cooled beam on target

Detectors IN (left arm pot =36.5
 31x 
  522   Sat Feb 17 13:21:44 2024 JM, CBBeam on target - motors tests14:01

Run 36 started.

We put both detectors to the fully
 Screenshot_from_2024-02-17_14-33-51.pngScreenshot_from_2024-02-17_14-36-27.pngScreenshot_from_2024-02-17_14-39-38.png 
  521   Sat Feb 17 06:19:27 2024 JM, CBRun 35 - contd07:10

FEE temperatures OK

System checks OK
 Screenshot_from_2024-02-17_07-20-01.pngScreenshot_from_2024-02-17_07-21-27.pngScreenshot_from_2024-02-17_09-09-35.pngScreenshot_from_2024-02-17_09-13-44.pngScreenshot_from_2024-02-17_09-14-35.png 
  520   Fri Feb 16 22:03:27 2024 TDRun 35 - night shift
22.51 DAQ continues file G22-86/R35_36
 49x 
  519   Fri Feb 16 10:02:41 2024 JM, OF, CB, AR, EMRun 35 - cooled beam on target11:01

Run 35 started cooled beam on target

Detectors IN (left arm pot =36.5
 27x 
  518   Thu Feb 15 21:07:00 2024 JM, AB, AR, OFRun33 - cooled beam on target22:27

Run 33 started cooled beam on target.

Detectors IN (left arm pot =36.5
 22x 
  517   Thu Feb 15 13:18:30 2024 JGMBS DAQ: target & ring valuesWe are running an MBS DAQ to record the
attached list of slow control values of the
ring and the target. In most cases this is
 2024_jet_daq.txt 
  516   Thu Feb 15 12:40:52 2024 JM. CB, AR, ABRun30 - uncooled beam on targetRun started 13:40

Target density 4.3e11, Beam injection
is ~1e7, Pressure in the ring is ~1e-10 mbar.
 29x 
  515   Thu Feb 15 10:39:50 2024 JM, JG, ML, AG, CBRun29 - beam optimisation11:27

Run 29 started. Beam energy is
1.3435 MeV/u with a cooler voltage of 751.3
  
  514   Wed Feb 14 16:52:46 2024 JM, AR, CB, JGRun28 - beam on target  

Beam energy - 1.361 MeV/u

17:12
 42x 
  513   Wed Feb 14 14:59:13 2024 JM, CB, NP, ML, AG, ABRun 27 -Beam on target optimisationRun 27 Started to check optimsation of
the beam - target overlap.

Beam intensity at injection is
 Target-overlap-scan-optimized.pdf 
  512   Wed Feb 14 14:06:28 2024 CB AR JMPulser Walkthrough
15:06
Run25

Pulser walkthrough

EGG
Ortec 448 Pulser

Amplitide 90,000-10,000
@ 10,000 step
Normalise 5.0
Attenuators
  
  511   Wed Feb 14 08:44:32 2024 CB AR JMMotors test and turbo ONRun number changed 09:44 - Now run 23

Moving motors with the injection

Ring signal very weird, moving
 11x 
  510   Tue Feb 13 17:19:43 2024 JM, AR, NP, AB, RSSRun22 - cooled beam on target (definitely maybe)18:05 We believe we have an overlap between
the beam and the target. Run 22 started.

         
 48x 
  509   Tue Feb 13 08:34:44 2024 Hw, JM, AR, CB, NP, AB, RSSStatus of DAQ - beam overlapCheck the status of the DAQ system, with
Tom. All correct. See attachments:

1 Leackage currents
 10x 
  508   Mon Feb 12 01:40:48 2024 TD, JM, CB, AR, RSSRun17 - Run20
02.35 DAQ continues file G22-88/R17_30
 49x 
  507   Sun Feb 11 13:28:46 2024 JM, CB, TDRun16 - beam on target13:37 Run started - no beam in the ring
(One of the ring magnets was still on RED
when it should have been set to green by
 30x 
  506   Sun Feb 11 07:03:34 2024 TDSunday 11 February
02.02 DAQ continues G22-86/R15_21
      alpha background
 20x 
  505   Sat Feb 10 17:05:13 2024 TDRun 15 - background
17.55 DAQ continues G22-86/R15_11
      alpha background
 20x 
  504   Sat Feb 10 10:00:44 2024 AR RSS JM CBRun 13, 14System checks: all ok

Attatchment 1: Rates ok

Attatchment 2: Temperatures ok
 23x 
  503   Fri Feb 9 17:04:39 2024 JM, AR, CB, NHRun12 - Background    
  502   Fri Feb 9 11:58:04 2024 TD + CB, JM, AR, NH, ABRun10 contd, Run11
12.46 DAQ continues G22-88/R10_14
 27x 
  501   Fri Feb 9 07:57:38 2024 AR, CB, AB, JMRun10 - First cool beam on target8:58

System wide checks okay, except

   
 27x 
  500   Thu Feb 8 17:11:50 2024 CB, EHPulser walkthrough
17:30 File G22-88/R8

Pulser walkthrough

EGG
Ortec 448 Pulser

Amplitide 90,000-10,000
@ 10,000 step
Normalise 5.0
Attenuators
 4.png3.png 
  499   Thu Feb 8 14:59:59 2024 JM, TDChange p+n FEE64 settingsASIC settings for the pn FEEs has been reset
to the default aida settings. This was done
to combat the observed dropping of several
  
  498   Thu Feb 8 11:22:28 2024 JMShifters instruction 2024EMERGENCY SHUTDOWNS

1. CARME motors: Q key
on keyboard while on workspace 1 of appc218
  
  497   Wed Feb 7 13:50:20 2024 Elena Hanu, Carlo Bruno, Michael LestinskyAfternoon shift14:50

 

Temperature, Statistics fine (see
 Screenshot_from_2024-02-07_14-53-36.pngScreenshot_from_2024-02-07_14-56-37.pngScreenshot_from_2024-02-07_14-51-21.png 
  496   Wed Feb 7 10:09:14 2024 CB, JG, EMMorning Shift 11:00

Changed slow comp threshold to
0x32 (500 keV). Checkloaded.
 Screenshot_from_2024-02-07_11-10-08.pngScreenshot_from_2024-02-07_11-10-59.pngScreenshot_from_2024-02-07_11-15-53.pngScreenshot_from_2024-02-07_11-20-38.png 
  495   Tue Feb 6 09:39:54 2024 CBDetector bias tests10:30 Found ADC#4 on aida 1 and 4 are suddenly
noisy. See attach 1-2. Checkloaded multiple
times - no effect.
 13x 
  494   Mon Feb 5 20:15:31 2024 CB, TDDetector move in/out signals17.43 setup signals from detector movement
controller.
 20240205_174307.jpg 
  493   Mon Feb 5 19:43:52 2024 CB, TD, MLBuTIS reference for VETAR2
16.40 CB/ML install fibre optic cable from
patch panel beneath dipole downstream of
 20240205_173029.jpg20240205_172957.jpgScreenshot_from_2024-02-05_16-43-18.png 
  492   Mon Feb 5 12:48:50 2024 CB TDPulser walkthough - Run4
13.41 DAQ start - file G22-88/R4
 Screenshot_from_2024-02-05_14-04-33.pngScreenshot_from_2024-02-05_14-05-16.png 
  491   Mon Feb 5 05:45:26 2024 CB TDRun3 - end06.40 DAQ continues file G22-88/R3_42

      DSSSD bias OK - attachment 1
 47x 
  490   Sun Feb 4 08:40:04 2024 CB TDRun3 - contd09.30 DAQ continues file G22-88/R3_17

      DSSSD bias OK - attachment 1
 22x 
  489   Sat Feb 3 15:05:10 2024 CB, TD[How To] Restart Anydesk1. Check Proxy server is correct

localhost : 8080

incoming connections 7070
  
  488   Sat Feb 3 00:13:03 2024 CB TDRun1 end - R3 start
01.07 DAQ continues file G22-88/R1_46
      background alpha
 50x 
  487   Fri Feb 2 09:58:58 2024 TDTapeServer not writng data to disk - plus fix DAQ and NewMerger appear to be cofigured correctly.

Can allocate device, create volume and open
 7x 
  486   Fri Feb 2 08:59:36 2024 JM, TD, CBRun1 start - pulser widths spreadsheetCurrent pulser widths excel spreadsheet attached

09.58 DSSSD bias OK - attachment 1 
 20x 
  485   Thu Feb 1 14:45:09 2024 JM, CBNewMerger setupTo include alll 16 FEE modules in the NewMerger
we edited the file /MIDAS/DB/EXPERIMENTS/MERGE/Options/carme-gsi
from MERGE.LinksAvailable string 5 to MERGE.LinksAvailable
  
  484   Thu Feb 1 10:04:11 2024 JM, CBShaping time testingArrived at the control room to find we
had lost connection to the power relay. We
rebooted the nnrpi1 and re-connected according
 31x 
  483   Wed Jan 31 09:49:38 2024 JM, TDOptimising - Wednesday 31Removed ground from DSSD #1 to the chamber
and set MACBs so that timestamp is from the
NIM WR emulator not the VME VETAR2.
 25x 
  482   Tue Jan 30 14:04:30 2024 NH[HowTo] Update MACB FirmwareThis is how to update the MACB firmware using
the opensource tool xc3sprog
 xusbdfwu.rulesxilinx.tar.gzxc2c128.mapmacb_apr20.jed 
  481   Tue Jan 30 09:14:50 2024 JM, TDTuesday 30 January
09.00 CARME IE514 5.1e-11mbar
 32x 
  480   Mon Jan 29 15:32:08 2024 TD, JMMonday 29 January contd.
Test + and test - daisy chain cabling extended
from DSSSD #1 to #2 to DSSSD #1 to DSSSD
 16x 
  479   Mon Jan 29 08:52:07 2024 TD JMMonday 29 January
09.50 CARME IE514 5.1e-11 mbar ( ambient
temperature 16 deg C )
 32x 
  478   Sat Jan 27 20:38:15 2024 PJCS[INFO] Steps to diagnose White Rabbit problemsThis is a suggested sequence of actions
to help with the current problem with the
White Rabbit timestamp distribution. Test
  
  477   Mon Jan 22 16:29:31 2024 TDSaturday 20 January11.00 No WLAN/WiFi
      came-gsi private LAN appears to be
OK
 30x 
  476   Fri Jan 19 11:17:50 2024 JG, TDFriday 19 January
12.20 CARME IE514 4.1e-11mbar, ambient temperature
16.7 deg C
 18x 
  475   Thu Jan 18 17:21:00 2024 TDThursday 18 JanuaryNetwork ( dhcpd.conf ) and MIDAS startup.tcl/Options/ASIC
settings/rfs filesystems configured
 Capture.PNG 
  474   Wed Jan 17 19:21:20 2024 TDAIDA spares
Spare AIDA hardware 
  
  473   Wed Jan 17 19:15:47 2024 TDWednesday 17 January
CAEN N1419ET remote control via carme-gsi
and nnrpi1 - see https://elog.ph.ed.ac.uk/CARME/472
  
  472   Wed Jan 17 10:31:05 2024 TDRemote control of CAEN N1419ET from nnrpi1
Login to nnrpi1 from carme-gsi using ssh
 Capture.PNG 
  471   Tue Jan 16 16:01:48 2024 TDChange CARMEraspberrypi to nnrpi1
Change RPi from CARMEraspberrypi to nnrpi1
to provide carme-gsi access to Rly16 to control
 Capture.PNG 
  470   Tue Jan 16 14:36:30 2024 TDCARME configuration
FEE64
 dhcpd.confOptionsSettingsstartup.tclrfs 
  469   Tue Jan 16 08:57:44 2024 JG, DR, TDTuesday 16 January10.00 Outflow manifold returned from workshop
with leaking attachment point welding re-worked.
 8x 
  468   Mon Jan 15 18:51:28 2024 JG, DR, TDMonday 15 January
Cooling water manifolds
  
  467   Sun Jan 14 12:31:32 2024 JM, CBFEE positions mac addresses*Updated following FEE changes. Correct
as of 31/01/24

FEE modules are labelled according
 CARME-FEEs.jpg 
  466   Sat Jan 13 14:32:21 2024 CB, JMLeaky manifold and cable managementFound two leaks in the welding of the manifolds,
marked them in tape. Manifold to be repaired
on Monday. Remember to re-install missing
 20240112_111838.jpg20240112_105936.jpg20240113_183019.jpg 
  465   Sat Jan 13 14:25:05 2024 CB, JMBias tests with all FEEs connectedConnected all FEEs.

The two top fees corresponding
to the bottom right detector are connected
 Screenshot_2024-01-13_15-24-40.png20240113_150158.jpg 
  464   Thu Jan 11 19:57:20 2024 CB, JMAll FEE holders mountedAfter discussions with Davide, changed
the holes in the FEE holders for the bottom-right
detector to slots in order to slightly change
  
  463   Wed Jan 10 19:27:08 2024 CB, JMManifold and more bias testsMounted water manifold on CARME with help
from GSI plumber. Connected all the hoses
with Swagelok self-locking connectors. Tested
  
  462   Wed Jan 10 10:22:41 2024 CB, JMSome FEEs mounted - issues with Det#2 (bottom left)Started mounting some FEEs. We ran into
some mechanical issues due to the new ERNI
connectors on the new flexi-rigid adaptor
 Screenshot_2024-01-10_11-59-39.pngScreenshot_2024-01-10_12-56-36.png 
  461   Mon Jan 8 19:29:57 2024 CB, JMManifold repaired + fee assembly in bench Davide extracted the stuck blind plugs
and re-threaded all missing ports. Completed
manifold assembly, except for main inlet/outlet
 20240108_164756.jpg20240108_163218.jpg20240108_163916.jpg20240108_164010.jpg 
  460   Mon Jan 8 19:27:36 2024 CB, JMLeak current tests overnight Left bias in overnight. Leakage current
decreased and stabilised. See attached. Bias
off as we prepare to mount the fees.
 Screenshot_2024-01-08_09-56-20.png 
  459   Sun Jan 7 15:38:57 2024 CB, JMManifolds mostly assembled + bias overnight checkAssembled most of the connectors on the
new (green) manifolds. Two blanking pulgs
stuck when mounting - cannot remove them
 Screenshot_2024-01-07_16-38-26.png 
  458   Fri Jan 5 12:29:10 2024 JM, CBFurther bias testsBiased detectors this morning to 150V,
the leakage current for all detectors appears
stable and is ~3.5 uA. We have also replaced
  
  457   Thu Jan 4 13:15:10 2024 CB, JMTent removed - bias testRemoved tent, octagon, Neg cables.

Disconnected and removed Baking
Pi, TC08, thermocouples.
 Bias.png 
  456   Wed Oct 18 16:47:36 2023 JG, CBPower outageLocal power outage at the CRYRING today,
while JG was trying to activate the ion pumps.
Unlcear what caused it.
  
  455   Tue Oct 17 08:43:47 2023 CBNEG activation -209:40 - Found temperature and pressure
stablised, but too high to comfortably activate
NEGs closest to detectors. Detector temperature
 Screenshot_2023-10-17_09-45-23.pngScreenshot_2023-10-17_11-04-09.pngScreenshot_2023-10-17_14-56-55.pngScreenshot_2023-10-17_17-58-24.pngScreenshot_2023-10-17_17-58-51.png 
  454   Mon Oct 16 08:28:02 2023 CBNEG activation -19:00 - Michael's online vacuum pressure
plot is no longer working - an old image
is being displayed. CARME temperatures around
 Screenshot_2023-10-16_17-17-30.png 
  453   Sun Oct 15 09:35:03 2023 CBStarting ramp down10:40 - Status as attached. Heaters setpoint/read
at 250 C, 150 C, 225 C. Power stable at 53%,
41%, 63%
 Screenshot_2023-10-15_10-35-47.pngScreenshot_2023-10-15_17-56-00.png 
  452   Tue Oct 3 08:48:36 2023 TDTuesday 3 October09.40 CARME IE514 1.79e-8 mbar, ambient temperature
20.7 deg C
 1000007432.jpg1000007431.jpg1000007434.jpg 
  451   Mon Oct 2 08:41:43 2023 TDMonday 2 October09.35 CARME IE514 1.95e-8 mbar, ambient temperature
20.8 deg C
 6x 
  450   Sun Oct 1 10:24:50 2023 TDSunday 1 October11.20 CARME IE514 3.53e-9 mbar, ambient temperature
20.6 deg C
 12x 
  449   Sat Sep 30 10:58:14 2023 TDSaturday 30 September10.50 CARME IE514 7.14e-10 mbar, ambient temperature
20.8 deg C
 9x 
  448   Fri Sep 29 08:54:29 2023 TDFriday 29 September
09.50 CARME IE514 9.0e-11 mbar, ambient temperature
21.3 deg C
 11x 
  447   Thu Sep 28 09:19:50 2023 TDThursday 28 September
10.20 CARME IE514 8.6e-11 mbar
 1000007142.jpg1000007143.jpg 
  446   Wed Sep 27 15:56:41 2023 TDWednesday 27 September
16.55 CARME IE514 8.2e-11 mbar
 1000007129.jpg1000007127.jpg1000007128.jpg 
  445   Tue Sep 26 10:13:14 2023 TDELOTECH PID Temperature Controller R4000 manual ( German and English )   BA-Isoheat_R4000-XX-X-000-X-X_DE_V1.03.pdfR4000-XX-X-000-X-X_EN_V1.30.pdf 
  444   Tue Sep 26 08:08:42 2023 TDTuesday 26 September09.07 IE514 pressure 6.4e-11 mbar, ambient
temperature +20.3 deg C
 7x 
  443   Mon Sep 25 16:33:32 2023 TDRemoved tape from heaters TC
17.33 IE514 pressure 6.4e-11 mbar, ambient
temperature +20.8 deg C
 1000007072.jpg1000007067.jpg1000007070.jpg 
  442   Fri Sep 22 12:35:46 2023 JMBakeout plotsAttached are plots for the previous bakeout
of CARME which may aid in the bakeout to
come in the following week.  
 Heater-chamber-temps.pngpressure-chamber-temp.pngHeater-power-chamber-temp.pngHeater-power-temp.png 
  441   Wed Sep 13 15:00:39 2023 MLVacuum and Heater temperature plots from GrafanaAttached are the plotted curves from vacuum
and heater temperature (actual and set values
from ISOHEAT controllers) during the bakeout
 Screenshot_2023-09-13_15-56-34.pngScreenshot_2023-09-13_15-58-06.pngScreenshot_2023-09-13_15-59-37.pngScreenshot_2023-09-13_15-59-01.pngScreenshot_2023-09-13_15-58-31.png 
  440   Sat Sep 2 10:04:55 2023 CBTurbo GV closed Found CARME in XHV at 1.1E-11 mbar. Chamber
temperature around 30C cooling slowly.

Closed GV to top turbo. Pressure
  
  439   Fri Sep 1 08:11:40 2023 CBNEG activation - 29:10 Set heaters temperature 300 ->
250 C in preparation for cooling down and
to help keep DSSD temperature down. Started
  
  438   Thu Aug 31 08:36:34 2023 CBNEG activation Found CARME at 50C, a bit cooler than expected,
probably due to invasive tent changes yesterday
to mount missing wires. Increased heaters
  
  437   Wed Aug 30 10:28:36 2023 CBPreparing for pumps onWe need to connect the non-bakeable (max
80C) wire of the ion pump belonging to the
vacuum division, and we also need to connect
  
  436   Wed Aug 30 09:33:13 2023 CB, OGNEG cables repaired Repaired Neg wires for D2000 with Oemer's
help.

Cable #2 is fine. 
 20230830_102519.jpg20230830_102514.jpg 
  435   Mon Aug 14 09:22:56 2023 JMBakeout14/08/23

Temperature in the baking volume
is ~ 42 C and the pressure is 4.6e-8 mbar.
 20230814_150430.jpg20230815_094400.jpgHeater-power.pngHeater-ITC-temp.pngPressure-ITC-temp.png 
  434   Sat Aug 12 15:06:51 2023 JMInitial bakeout tests12/08/23

Baking testing. Aim to find relationship
between heater temperature setpoint and the
 20230813_114600.jpg20230813_132550.jpg20230813_170829.jpg20230813_205613.jpg20230813_210238.jpg 
  433   Sat Aug 12 11:57:51 2023 JMUpdated thermocouple positions and heater channel layoutsHeater channel layouts for the interaction
chamber and carme in attached documents. 

Updated thermocouple positions;
 6x 
  431   Thu Aug 10 07:51:43 2023 JMBaking tent and heater testing09/08/23

Attached is the current pumpdown
plot taken from grafana. 
 8x 
  430   Thu Jul 27 09:43:56 2023 RSSThermocouples connected -2
10:30  IE514 1.80e-08mbar

Most
of the CARME is covered by the baking tent.
The tent needs to be closed and a bit covered
 IMG_9920.jpgIMG_9919.jpg 
  429   Wed Jul 26 08:28:09 2023 RSSBuilding tent
09:26  IE514 1.96e-08mbar
 IMG_9897.jpgIMG_9899.jpgIMG_9901.jpgIMG_9902.jpg 
  428   Tue Jul 25 09:12:15 2023 RSSBuilding tent
10:10  IE514 2.0e-08mbar

Upstream
part of the CARME is covered.
 BD01C0C8-5181-49B8-8751-AD4C99A459CC.jpeg7B3836F1-8A7E-491B-AFDC-46033BF84760.jpeg 
  427   Mon Jul 24 10:40:14 2023 RSS, TDPump down continues11.40 Pirani 1.00e-3 mbar IE514 2.23e-08mbar

15.15 7d/24h vacuum plots
 vacplot.pngvacplot24.png 
  426   Sun Jul 23 10:13:48 2023 RSS, TDBuilding tent11.15 Pirani 1.0e-03mbar IE514 2.72e-08mbar

16.35 Pirani 1.0e-03mbar IE514 2.61e-08mbar
 DBE0DA2E-2F69-469C-B645-3E33E3D82138.jpeg857185AC-3571-41E9-88AE-9F624445135B.jpegE69ED1D1-444E-478A-A3B4-481023B4024D.jpeg610048A3-25F5-459C-9EF1-83EFEFDE51C9.jpeg 
  425   Sat Jul 22 09:19:59 2023 RSS, TDThermocouples connected10.20 Pirani 1e-03mbar IE514 3.26e-08mbar

 10x 
  424   Fri Jul 21 08:21:54 2023 TD, RSSBaking tent manual09.20 Pirani 1.00e-3 mbar IE514 3.90e-8 mbar

      Today - install TCs, connect to Pico
 CARME-baking-guide_(1).pdf 
  423   Thu Jul 20 08:29:26 2023 TDInstalling tent. Two NEG power cable broken.09.28 Pirani 1.00e-3 mbar IE514 5.45e-8 mbar

12.10 Bakeout tent frame installed
 11x 
  422   Wed Jul 19 08:17:26 2023 TDLeak testing09.16 Pirani 1.00e-3 mbar IE514 8.77e-8 mbar
      Leak tester c. 5e-12 mbar.l/s (leak
tester valved off)
  
  421   Tue Jul 18 08:16:28 2023 TDPumping down. Issues found with one detector.09.15 Following overnight pumping of CARME
chamber by Leybold turbo
      Pirani 1.00e-3 mbar IE514 2.83e-7 mbar
  
  420   Mon Jul 17 08:45:11 2023 TDClosing CARME again
Grosmantage are scheduled to arrive 10.00
to inspect COF600 seals and their fit to
 20230717_093106.jpg 
  419   Fri Jul 14 08:27:17 2023 TDCARME open - inspecting seal
09.20 CARME chamber at atmospheric pressure
as expected.
  
  418   Thu Jul 13 08:46:44 2023 TDReplacing wire seal
09.30 CARME chamber status
 20230713_135351.jpg20230713_135416.jpg 
  417   Thu Jul 13 00:12:45 2023 JM, CBCARME closedThe CARME chamber was closed and pushed
back into position on the ring. 

Prior to moving back onto the ring,
 Bias110723.pngfullyin.jpgfullyin-measured.jpg 
  416   Thu Jul 13 00:12:19 2023 JM, CBBellow replacedThe left (inside ring) bellow for the motors
rod was replaced.

Replacing the bellow involved;
 20230705_164523.jpg 
  415   Thu Jul 6 15:26:39 2023 JMLeak updateThe leak on the actuator arm bellows has
been attempted to be sealed using UHV vacuum
seal spray. The spray had the opposite to
 pumping.png 
  414   Wed Jul 5 19:27:13 2023 JMPump down and leak testCARME and the interaction chamber have
been pumping for ~26 hours, P=4.15e-7 mbar,
attached figures show the current pump down
 pumping_1.pngpumping-zoom.pngsignal-2023-07-05-15-13-30-512.jpg 
  413   Tue Jul 4 17:08:08 2023 JMLeak test and ventingThis morning the pressure achieved was
1.44E-7 mbar. Leak testing showed an overall
leak rate of 1.5E-10 mbar l/s, this is below
 20230704_135455.jpg20230704_174524.jpg 
  412   Mon Jun 26 14:49:05 2023 JM, TDCARME vented26/06/23

This morning the pressure was 4e-7
mbar. The bolts on the windows and the large
  
  411   Sun Jun 25 14:30:06 2023 JM, TDMotors bias testThe motors were moved using the pneumatic
only, in and out for several cycles to gauge
the effect on the vacuum. For the left arm
  
  410   Sun Jun 25 10:08:30 2023 JM, TDPump-down 23/06/23

Pumpdown started with the scroll
pump 17:15 . The turbo-pump was started 17:55.
 Figure_1.png20230625_120640.jpg20230625_120648.jpgpump-down.png 
  409   Sun Jun 25 09:41:06 2023 JM, TDNormal turbo-pump operationAttached are images showing the messages
for normal turbo-pump operation
 6x 
  408   Sat Jun 24 10:38:42 2023 JM, TDSection 9 closed, begin pumping 23/06/23

The CARME chamber and interaction
chamber were connected and section 9 has
 23-06-23-VI.png24-06-23-VI.png 
  407   Thu Jun 22 18:58:02 2023 JM, TDSlide back onto ringThe wire seal has been tightend further
to 160 Nm. Open neg feed-through flange has
also been fully tightend. 
 20230622_112534.jpg20230622_112827.jpg20230622_120307.jpg 
  406   Wed Jun 21 18:47:36 2023 JM, TDClosing CARMEInternal CARME installations complete. 


New strain reliefs (flange
side) installed on each cable harness.
2x
 20230621_104911.jpg20230621_104918.jpg20230621_110010.jpg21-06-23-VI.png 
  405   Fri May 26 09:08:06 2023 JM, CBDetector movement Hopefully we will not be opening the chamber
for quite some time so find attached images
of all four installed detectors and a video
 20230525_135756.jpgdetector-movement-in.mp4 
  404   Fri May 26 08:53:54 2023 JM, CBStrain reliefs (flange side) installedStrain reliefs on the flange side of the
cable harness have been installed for two
detectors (top right and bottom right detectors). 
 strain-relief-flange-side.jpgstrain-relief1_(1).mp420230526_140923.jpgV-I-plot.png 
  403   Wed May 24 09:54:56 2023 JM, CBMaximum detector positionsThe detectors were moved into the beam
axis using the motors to check the maximum
distance they can be moved in without collision
 9x 
  402   Wed May 24 08:35:12 2023 JM, CBStrain reliefs (detector side) installedThe new MACOR strain reliefs on the (detector
side) have been installed. See attached photos

The two pieces  of MACOR are
 20230524_092010.jpg20230524_092017.jpg20230524_092101.jpg20230524_093000.jpg20230524_092159.mp4 
  401   Mon May 15 07:34:22 2023 TDMonday 15 May08.35 DSSSD#3 bias -149.95V leakage current
-6.418uA temperature +19.6 deg C ( https://web-docs.gsi.de/~lestinsk/tempplot.php
)
  
  400   Sun May 14 11:55:12 2023 TDSunday 14 May12.44 DSSSD#3 bias -149.95V leakage current
-6.448uA temperature +19.7 deg C ( https://web-docs.gsi.de/~lestinsk/tempplot.php
)
  
  399   Sat May 13 11:34:25 2023 TD, RSSSaturday 13 May
12.34 DSSSD#3 bias -149.95V leakage current
-6.763uA temperature +21.2 deg C ( https://web-docs.gsi.de/~lestinsk/tempplot.php
  
  398   Fri May 12 16:24:20 2023 RSS, TDV-I testSince yesterday evening, the bottom right
detector was at -150 V. In the morning, the
current was quite stable ~ 6.77 uA. The bias
 8x 
  397   Thu May 11 21:22:54 2023 RSS, TDV-I testToday, the foil was opened, the pins on
the bottom right detector were checked and
looked fine, the right-hand arm was moved
 7x 
  396   Wed May 10 19:06:18 2023 RSS, TDV-I testTo test the detectors, adaptors were installed
on the feed through flanges. A negative bias
voltage was applied in steps of 10 V from
 detector_1.pngdetector_2.pngdetector_3.pngdetector_4.png 
  395   Tue May 2 15:02:09 2023 CB, JMAll detectors and harnesses mounted Completed mounting harnesses and detectors.

The strain relief support for the
bottom most two detectors on the feedthrough
 20230502_153410.jpg20230502_153503.jpg20230502_153509.jpg20230502_153511.jpg 
  394   Mon May 1 18:21:18 2023 CB, JMAll detectors mounted Mounted four detectors on Carme ad well
as four cable harnesses.

 
 20230501_191533.jpg20230501_191511.jpg20230501_145740.jpg 
  393   Mon May 1 08:26:09 2023 CB, JMLeft hand detectors remounted (31 April)

Remounted 3335-12 on top and new
3335-1 on bottom of left hand plate. Used
  
  392   Sun Apr 30 10:01:39 2023 CB, JMLeft hand detectors unmounted (29 April)

Inspected CARME after opening.
See attached. Some key takeaways.
 26x 
  391   Sat Apr 29 10:12:58 2023 CB, JMCARME opened(28 April)

Mounted rails on dolly. The rails
don't smoothly connect to those on the
 8x 
  390   Thu Apr 27 19:43:23 2023 CB, JMPreparing to open Removed turbo pump and set aside in a box.
Considering switching to the other turbo
to avoid degradation due to lack of use.
 20230427_123456.jpg20230427_161602.jpg 
  389   Wed Apr 26 16:49:28 2023 CB, JMCARME dolly mostly built Disconnected cables from CARME motors and
turbo. The turbo has to go to allow Carme
to slide out. Crane may be required to lift
 20230426_152121.jpg20230426_162619.jpg20230426_162627.jpg 
  388   Tue Apr 25 13:22:19 2023 JMCARME venting CARME venting using nitrogen gas bottle. 

Coolant pipes dismounted from the
chamber
 20230425_134119.jpg20230425_132944.jpg 
  387   Mon Apr 24 21:24:26 2023 JMPreparation for CARME dismountCARME currently in vacuum, pressure ~3E-10
mbar. Chamber to be vented tomorrow afternoon
by vacuum division. We have active both pirani
 20230424_155635.jpg20230424_155607.jpg20230424_150526.jpg 
  386   Wed Mar 22 16:33:32 2023 TDNIM WR source
Test of NIM WR source at Edinburgh
 8x 
  385   Wed Jan 18 13:32:36 2023 PJCSMACB settings with either Emulator or VETARWhen using the VITAR connected
to the HDMI port of the root MACB the settings
for all the MACB in the system 0x3.
 macb_apr20.jedmacb_apr20.vhdzybo.jpgMACB.jpg 
  384   Thu Dec 8 14:41:19 2022 PJCSResults of tests on AIDA PSU in DL T9We opened one up and soldered a co-ax cable
to one of the +6v power contacts at the output
of the filter board.
 8x 
  383   Thu Dec 1 08:56:59 2022 AR TDThursday 1 December Photos of noise observed at each of the
AIDA PSU outputs by digital oscillscope.

DAQ GOing with waveforms enabled.
 11x 
  382   Wed Nov 30 08:52:59 2022 AR TDWednesday 30 November9:40

DSSD bias and leakage current values:

-99.99 V
 26x 
  381   Tue Nov 29 14:37:56 2022 AR TDTuesday 29 November16:20

DSSD bias and leakage current values:

-99.99 V
 22x 
  380   Mon Nov 28 13:14:33 2022 AR TDMonday 28 November   12x 
  379   Mon Oct 3 16:03:33 2022 OH, CBTTT14 PhotosPhotos of the new TTT14 DSSD delivered to
GSI.
Photos of detectors are broken up by photos
  
  378   Sun Aug 14 06:50:58 2022 TD, JMSunday 14 August
07.51 DAQ continues files 22Feb/R97
 10x 
  377   Sat Aug 13 10:23:59 2022 JM, TDNoise tests pt3 and pulser walkWaveforms and discriminator ON. Pulser
re-connected to all fees via daisy chain.
V=100v, I=8.36uA
 15x 
  376   Fri Aug 12 15:12:37 2022 JM, TDCARME measurementsmeasurement 1 -string
intermediate (smaller) chamber - 2144
(mm) circumference,  measured half circumference
 9x 
  375   Fri Aug 12 09:06:57 2022 TD, JMNoise tests pt2
10.07 DSSSD bias -100V leakage current -8.65uA
 30x 
  374   Thu Aug 11 09:25:13 2022 JM, TDNoise tests
Moved pneumatic motor in and out several
revolutions
 14x 
  373   Wed Aug 10 10:33:03 2022 TD, ML, JM, NPMeeting at YR09 to discuss options for CARME operations to February 2022
Initial discussions of proposals to provide
open CARME chamber and provide access to
 20220810_111638.jpg20220810_095036.jpg20220810_095150.jpg20220810_095159.jpg 
  372   Wed Aug 10 10:30:04 2022 TD, JMWednesday 10 August
09.45 Found CARME electrical power off
 4.PNG3.PNG2.png1.png 
  371   Tue Aug 9 16:07:33 2022 JM, TDAnydesk setup command lineTo log into appc218 desktop:
same login and password as to carme@atppc022.gsi.de

To start anydesk
  
  370   Tue Aug 9 13:44:16 2022 TD, JMTuesday 9 August
14.00 CARME vacuum c. 1.8e-10 mbar - see
attachment 1
 Capture_1.PNG20220809_163450.jpg20220809_135840.jpg20220809_135833.jpg20220809_135801.jpg 
  369   Thu Mar 3 15:14:21 2022 JM, OHCARME packing upPulser walkthrough taken for motor position
23.1mm and motor position 67.43mm.

Points taken at 30,50,70,90,110,130,150,170,190,210,230
  
  368   Wed Mar 2 22:29:48 2022 CB, SDLast shift with beam22:30 Shift handed over. DAQ OK. Target
OK. Beam OK.

 
 9x 
  367   Wed Mar 2 21:16:06 2022 JM, PMCurrent status22:16

Temperature setpoint = 113k

Not observed noise burst again
  
  366   Wed Mar 2 19:25:25 2022 JM, PMCurrent status20:25

Observed short burst of low energy
noise on aida1, lasted <30s (attachment
 10x 
  365   Wed Mar 2 17:21:35 2022 JM, PMCurrent status18:21

Temperature setpoint = 113k

Target density OK S1 varies between
 8x 
  364   Wed Mar 2 14:15:16 2022 JM, PMCurrent status15:15

Temperature setpoint = 113 K

Target density is OK for now. S1
 6x 
  363   Wed Mar 2 09:38:50 2022 Spillmann, Uweion source restarted 

detector position

out: 23.1mm
  
  362   Wed Mar 2 06:00:49 2022 Spillmann, Uwewaiting07:00
Target density is hovering between
2.0e-8 and 2.3e-8
  
  361   Wed Mar 2 03:40:40 2022 David, GeorgeTemperature Cycle04:40
Target density is hovering between
2.0e-8 and 2.3e-8, sometimes dipping below
  
  360   Wed Mar 2 01:24:48 2022 David, GeorgeIon Source Update02:25
Zoran was unable to ignite the ion
source.
  
  359   Tue Mar 1 23:43:15 2022 David, GeorgeBeam Intensity Drop00:38
Intensity in the ring dropped by 2
orders of magnitude to 5e5 on injection
  
  358   Tue Mar 1 23:30:04 2022 David, GeorgeCurrent status00:30
Pressure in S1 slightly decreased
from before but still high enough to measure
 2022-03-02_00-39-47xytotal.png2022-03-02_00-39-20exRate.png2022-03-02_00-38-44extotal.png 
  357   Tue Mar 1 22:10:26 2022 David, GeorgeCurrent statusRing current 6.67e7 particles/s

pressure at S1: 2.3-2.8e-8

Merger, Tape server (WS3):
 2022-03-01_23-14-43aida.png2022-03-01_23-13-57exrate.png2022-03-01_23-13-40xyto.png2022-03-01_23-13-10extot.png 
  356   Tue Mar 1 21:34:06 2022 PM, LVcheckno change:

Check Clock Status': Passed
5, Failed 0
 14x 
  355   Tue Mar 1 20:41:28 2022 PM, LVcheckno change:

Check Clock Status': Passed
5, Failed 0
 14x 
  354   Tue Mar 1 19:41:24 2022 PM, LVtarget temperature walkthroughA target temperature walkthrough has been
initiated at 20:41 since the target density
at S1 had slightly decreased (with ~0.1-0.2)
  
  353   Tue Mar 1 19:40:28 2022 PM, LVcheckno change:

Check Clock Status': Passed
5, Failed 0
 12x 
  352   Tue Mar 1 18:43:41 2022 PM, LVcheckno change:

Check Clock Status': Passed
5, Failed 0
 14x 
  351   Tue Mar 1 17:36:04 2022 PM, LVcheckno change:

Check Clock Status': Passed
5, Failed 0
 14x 
  350   Tue Mar 1 16:57:34 2022 CB, LV, PMHNew runBeam issues due to too long storage time
in the last hours. Motors moved out and not
moving.
  
  349   Tue Mar 1 14:01:01 2022 MS, SHBcheck'Check Clock Status', 'Check
ADC Calibration' and 'Check the White
rabbit decoder status' : no change
 11x 
  348   Tue Mar 1 12:58:32 2022 CB, MS, SS, MLSynced pneumatic motionNew run R84

Attempting to sync pneumatic movement
with ring. Still see something on t out ->
  
  347   Tue Mar 1 12:33:21 2022 MS, SHBcheck'Check Clock Status', 'Check
ADC Calibration' and 'Check the White
rabbit decoder status': no change
 11x 
  346   Tue Mar 1 10:43:36 2022 MS, SHBcheck 'Check Clock Status', 'Check
ADC Calibration' and 'Check the White
rabbit decoder status': same
 11x 
  345   Tue Mar 1 10:35:59 2022 MS, SHBnext run on tape server tabold potentiometer position 19.1 mm

new run number: 83

new potentiometer position : 27.58
  
  344   Tue Mar 1 08:02:26 2022 SHB, MScheck 

'Check Clock Status', 'Check
ADC Calibration' and 'Check the White
 11x 
  343   Tue Mar 1 06:35:42 2022 SHB, MScheckdetector motors are still out

'Check Clock Status', 'Check
ADC Calibration' : Clock status test
 11x 
  342   Tue Mar 1 06:04:04 2022 SHB, MSpositionsjust FYI: current positions saved in files
are x=1000 and y=-750. this information is
good in case of crash.
  
  341   Tue Mar 1 05:23:02 2022 JM, EMCurrent status 06:20

Servo motors moved to fully out
position as some work on the beam was neccessary.
 2022-03-01_06-42-53-ExRate.png 
  340   Tue Mar 1 04:07:31 2022 JM, EMTemperature cycleHave been unable to achieve decent target
density with temperature cycling so far.
Will attempt to go up to 300 k and back down
  
  339   Tue Mar 1 03:34:28 2022 JM, EMCurrent statusTemperature setpoint = 116 k

Detector IN potentiometer = 34.89
mm
 7x 
  338   Tue Mar 1 03:19:50 2022 JM, EMTemperature Cycle04:20

Did another temperature cycle (118
K -> 125 K -> 95 K -> 116 K) trying
  
  337   Tue Mar 1 02:15:29 2022 JM, EMCurrent status03:15

The nozzle motor control at the
target crashed, but operation has been restored.
 6x 
  336   Mon Feb 28 23:54:02 2022 JM, EMCurrent Status, Temperature cycle00:51

Temperature setpoint = 116 K

Detector position IN potentionmeter
 2022-03-01_00-57-44-Exrate.png2022-03-01_00-58-41-ExTotal.png2022-03-01_00-58-14-EyTotal.png 
  335   Mon Feb 28 22:34:51 2022 JM, EMCurrent status23:35

Temperature setpoint = 116 K

Detector position IN, potentiometer
 2022-02-28_23-40-14-xyTotal.png2022-02-28_23-39-56-Exrate.png2022-02-28_23-39-26-goodEvents.png2022-02-28_23-38-58-correlation8.png2022-02-28_23-38-31-ADCitems.png 
  334   Mon Feb 28 14:47:52 2022 CB, TDMonday 28 February 15:00-23:00
15.51 1.8.W spectra 20ms, 2ms, 200us, 20us
FSR - attachments 1-8
 17x 
  333   Mon Feb 28 14:42:48 2022 CB, TDCryostat set to 115K
Cryostat set to 115K
  
  332   Mon Feb 28 14:38:15 2022 TDNewMerger statistics
Screenshots of all NewMerger statistics
 37x 
  331   Mon Feb 28 13:56:02 2022 JG, CBTemperature cycle to 125K14:45

Rutherford rate was decreased significantly
for longer period.
  
  330   Mon Feb 28 13:16:39 2022 JG, AK, CBCurrent status14:16

beam intensity at injection: 7e7
ions
 8x 
  329   Mon Feb 28 11:57:22 2022 JG, AK, CBCurrent status12:55

beam intensity at injection: 9e7
ions
 8x 
  328   Mon Feb 28 10:55:48 2022 JG, USCurrent status11:55

beam intensity at injection: 8e7
ions
 8x 
  327   Mon Feb 28 09:31:48 2022 JG, AK, CBCurrent status10:35

beam intensity at injection: 1e8
ions
 8x 
  326   Mon Feb 28 08:36:35 2022 JG, AK, CBCurrent status09:35

beam intensity at injection: 8.2e7
ions
 8x 
  325   Mon Feb 28 07:35:51 2022 JGcurrent logger crashedThe current logger did crash in the evening
of 25.02. and stopped logging since then,
it seems.
 Screenshot_from_2022-02-28_08-38-35.png 
  324   Mon Feb 28 07:31:25 2022 JG, AKCurrent status08:30

Temperature setpoint = 110 k

Rutherford rates shaky, peak max
 8x 
  323   Mon Feb 28 06:12:58 2022 JG, AK, USCurrent status07:20

Temperature setpoint = 110 k

Rutherford rates shaky, peak max
 8x 
  322   Mon Feb 28 05:04:47 2022 JM, OFTemperature cycle to 125K06:01

Rutherford rate was decreased compared
to previous values. Max rate ~ 50 counts
 2022-02-28_06-30-39-Exrate.png 
  321   Mon Feb 28 04:14:26 2022 JM, OFCurrent status05:20

Temperature setpoint = 110 k

Rates are stable however are slightly
 9x 
  320   Mon Feb 28 03:16:37 2022 JM, OFCurrent status04:24

Temperature setpoint 110 K

Rates appeared stable throughout
 6x 
  319   Mon Feb 28 02:16:00 2022 JM, OFCurrent status03:21

Temperature setpoint 110 K

Rutherford rate stable. Min peak
 6x 
  318   Mon Feb 28 01:16:02 2022 JM, OFTemperature decrease 115K to 110K02:15

Density remains stable at
155 K
 20220228_021455.jpg20220228_023832.jpg20220228_025416.jpg 
  317   Mon Feb 28 00:24:05 2022 JM, OFCurrent status01:23

Temperature setpoint = 115 k

Rutherford rates still appears
 7x 
  316   Sun Feb 27 23:17:33 2022 JM, OFCurrent status00:20

Temperature setpoint 115 K

Rutherford rate appears fairly
 10x 
  315   Sun Feb 27 22:03:51 2022 JM, OFCurrent Status23:00

Target Temperature setpoint 95
K
 9x 
  314   Sun Feb 27 20:38:06 2022 Rui-Jiu Chen, YuriCurrent statusRing current ~5.0e7 particles/s

SW3

- Merger OK
 13x 
  313   Sun Feb 27 20:19:06 2022 Rui-Jiu Chen, Yuriopen the valves of target.    
  312   Sun Feb 27 19:01:02 2022 Rui-Jiu Chen, YuriCurrent statusRing current ~5.96e7 particles/s

SW3

- Merger OK
 13x 
  311   Sun Feb 27 18:46:42 2022 Rui-Jiu Chen, YuriChange target temperaturetime             
Temperature            
E1 current(A)                
  
  310   Sun Feb 27 17:00:45 2022 Rui-Jiu Chen, Yuricurrent statusRing current ~7.76e7 particles/s

SW3

- Merger OK
 13x 
  309   Sun Feb 27 16:30:35 2022 Rui-Jiu Chen, YuriChange target temperature again1. change T from 95 k to 140 k.

2. keep T at 140k for 15 minutes.

3. change T from 140 k to 95 k.
  
  308   Sun Feb 27 15:41:33 2022 Rui-Jiu Chen, Yuricurrent status16:38 change target temperature from 95
k to 140 k.

16:48 change target temperature
 13x 
  307   Sun Feb 27 15:02:16 2022 Rui-Jiu Chen, YuriChange target temperature16:00 change temperature from 95 k to 120k.

16:07 change temperature from 120
k to 95k.
 14x 
  306   Sun Feb 27 14:05:30 2022 Rui-Jiu, RaganCurrent statusRing current ~7.61e7 particles/s

SW3

- Merger OK
 14x 
  305   Sun Feb 27 13:34:24 2022 RSS TDCurrent status14:33: 95K-->140K

14:44: 140K --> 95K

Ring current ~6e7 particles/s
  
  304   Sun Feb 27 12:49:44 2022 TD RSSSunday 27 February 07:00-15:00
13.50 Cryostat set point 120K
 6x 
  303   Sun Feb 27 12:00:13 2022 RSS TDCurrent statusRing current ~7.7e7 particles/s

Merger, Tape server (WS3):
1414 kB/s writing ok
 13-xy-2022-02-27_13-01-36.png13-yrate-2022-02-27_13-01-06.png13-xrate-Screenshot_from_2022-02-27_13-00-50.png 
  302   Sun Feb 27 11:00:08 2022 RSS TDCurrent status12:00: 95K-->120K

12:07: 120K --> 95K

Ring current ~6e7 particles/s
 12-xy-2022-02-27_12-16-19.png12-yrate-2022-02-27_12-15-42.png12-xrate-2022-02-27_12-15-03.png 
  301   Sun Feb 27 10:00:07 2022 RSS TDCurrent statusRing current ~9e7 particles/s

Merger, Tape server (WS3):
1414 kB/s writing ok
 11-xy-2022-02-27_11-01-22.png11-ey-rate2022-02-27_11-00-46.png11-ex-rate-2022-02-27_11-00-27.png 
  300   Sun Feb 27 09:00:09 2022 RSS TDCurrent status10:00: 95K-->120K

10:08: 120K --> 95K

Ring current ~7e7 particles/s
 7x 
  299   Sun Feb 27 08:00:23 2022 RSS TDCurrent statusRing current ~7.5e7 particles/s

Merger, Tape server (WS3):
1414 kB/s writing ok
 9-xy-2022-02-27_09-00-57.png9-ey-2022-02-27_09-00-03.png9-ex-2022-02-27_08-59-48.png 
  298   Sun Feb 27 06:58:51 2022 RSS TDCurrent status7:59: 95K-->120K

8:06: 120K --> 95K

Ring current ~7e7 particles/s
 8-xy-2022-02-27_08-10-15.png8-ey-2022-02-27_08-09-46.png8-ex-2022-02-27_08-09-29.pngScreenshot_from_2022-02-27_07-16-30.png 
  297   Sun Feb 27 06:23:42 2022 RSS TDCurrent statusRing current ~6e7 particles/s

Merger, Tape server (WS3):
1414 kB/s writing ok
 6x 
  296   Sun Feb 27 05:45:53 2022 David, Pierre-MichellCurrent status6:05: 95K-->120K

6:12: 120K --> 95K

Ring current 8e7 particles/s
 2022-02-27_06-50-09exrat.png2022-02-27_06-48-23eytot.png2022-02-27_06-48-05extot.png2022-02-27_06-47-47xytot.png 
  295   Sun Feb 27 04:54:46 2022 David, Pierre-MichellCurrent statusRing current 8e7 particles/s

Merger, Tape server (WS3):
1664 kB/s writing ok
 2022-02-27_05-56-59exra.png2022-02-27_05-56-31exto.png2022-02-27_05-56-13xytot.png 
  294   Sun Feb 27 03:49:36 2022 David, Pierre-MichellCurrent status04:06 85K -->120K : 04:13 120K -->95K

current ring 8e7 p/s

Merger, Tape server (WS3):
 2022-02-27_04-53-12xytot.png2022-02-27_04-52-51exrst.png2022-02-27_04-52-31extot.png 
  293   Sun Feb 27 02:38:52 2022 David, Pierre-MichellCurrent statusWe have decreased the temperatur> 95K
--> 90K. At 95K the target was stable,
but let's try to increase the density
 2022-02-27_03-43-36aida.png2022-02-27_03-42-55xyto.png2022-02-27_03-42-14exra.png2022-02-27_03-41-49extot.png 
  292   Sun Feb 27 01:46:56 2022 David, Pierre-MichellCurrent statusSo far looks like with a temperature of
95K the target is maintained with a reasonable
density throughout long periods of time.
 2022-02-27_02-50-15exrate.png2022-02-27_02-49-47extot.png2022-02-27_02-49-28xytot.png 
  291   Sun Feb 27 00:53:24 2022 David, Pierre-MichellCurrent statusWe have recovered the beam at 01:49, after
such a long time we had no target so we increased
from 80K to 120K at 01:52. 02:01 update 120K-->95K
 7x 
  290   Sun Feb 27 00:07:15 2022 David, Pierre-MichellNo beam, valve closedAt 00:37 we lost the beam due to a high
pressure burst in the tarjet which resulted
in a valve closed at YR09VV...
  
  289   Sat Feb 26 23:20:13 2022 David, Pierre-MichellUpdate statusIn this last hour we have been playing
with the cryostat temperature as dictated
by Nikos, in order to have the target working
 7x 
  288   Sat Feb 26 22:22:27 2022 David, Pierre-MichellStarting to take dataAt 23:22 we started recording data under
the new conditions.

Merger, Tape server (WS3):
 11x 
  287   Sat Feb 26 04:36:38 2022 RSS TDSaturday 26 February 07:00-15:0005:36 E4 pressure c. 1.7e-9mbar *not* 3e-10mbar
as reported earlier
      See attachments 1 & 2
 27x 
  286   Fri Feb 25 19:20:22 2022 MS, PJWcheck'Check Clock Status', 'Check
ADC Calibration' and 'Check the White
rabbit decoder status'  no changes
 11x 
  285   Fri Feb 25 17:48:22 2022 MS, PJWcheck'Check Clock Status', 'Check
ADC Calibration' and 'Check the White
rabbit decoder status' - no changes
 11x 
  284   Fri Feb 25 16:01:04 2022 MS, PJWcheck        

'Check Clock Status': Clock
status test result: Passed 5, Failed 0
 7x 
  283   Fri Feb 25 15:38:40 2022 JM, CB, PJWRun 55, 56, 59 root histogramsRun55 - detector out, start 22/2/22 13:20,
end 23/2/22 10:49

Run 56 - detector moved in, start
 6x 
  282   Fri Feb 25 11:20:30 2022 CBPressure and temperature data savedSaved pressure reading and temperature
data logs from internal target in /TapeServer/22Feb/OtherData

Leakage current data is saved in
  
  281   Fri Feb 25 09:58:08 2022 GHC, CB, ML, EMCurrent status10:58
Started new run: 77
  
  280   Fri Feb 25 08:14:47 2022 George, EstherCurrent status9:14
Beam intensity around ~7.5e7

Pressures OK
  
  279   Fri Feb 25 06:57:09 2022 George, EstherCurrent status08:00
Beam seems to be back
Intensity ~7.8e7
 2022-02-25_08-03-21leakage.png 
  278   Fri Feb 25 06:28:12 2022 George, EstherCurrent Status07:30
Some signals on the beam monitor,
seems they are optimising it.
 2022-02-25_07-33-44exRate.png2022-02-25_07-35-11xyTotal.png 
  277   Fri Feb 25 05:04:16 2022 Rui-Jiu Chen, AlexcheckStill  no beam in CRING.

Motor fully out position.

SW3
 14x 
  276   Fri Feb 25 03:20:29 2022 Rui-Jiu Chen, AlexCurrent statusGleb Vorobyev tried for few hours to fix
the ion source but without success.

So, there will be no beam in CRYRING
  
  275   Fri Feb 25 03:01:11 2022 Rui-Jiu Chen, AlexcheckStill  no beam in CRING.

Motor fully out position.

SW3
 14x 
  274   Fri Feb 25 01:12:49 2022 Rui-Jiu Chen, Alex Check Still  no beam in CRING.

Motor fully out position.

SW3
 13x 
  273   Fri Feb 25 00:00:40 2022 Rui-Jiu Chen, AlexCheckThere are some problems with ion source. 
No beam in CRYING.

Motor fully out position.
 14x 
  272   Thu Feb 24 23:15:25 2022 Rui-Jiu Chen, AlexProblems with ion souce.    
  271   Thu Feb 24 22:45:08 2022 Jordan, George, Rui-Jiu Chencheck- Motor fully out position.

SW3

- Merger OK
 14x 
  270   Thu Feb 24 14:31:25 2022 JM, ML, CNBeam Tuning Run 7615:30

1.5 MeV/u beam currently being
tuned
 6x 
  269   Thu Feb 24 09:43:16 2022 JG, MScheckBeam is still beeing tuned. Target is off.

 

- Motor on manual
 13x 
  268   Thu Feb 24 08:30:36 2022 JG, MSAIDA5 calibration test failed - solvedUPDATE: THE PROBLEM IS SOLVED FOR NOW:

Doing the calib for the 5th time
eventually worked.
 Screenshot_from_2022-02-24_09-09-36.pngScreenshot_from_2022-02-24_09-29-24.png 
  267   Thu Feb 24 08:15:23 2022 JG, MScheckBeam is still beeing tuned. Target is off.

There is a problem with ADC calibration
of aida5: see entry https://elog.ph.ed.ac.uk/CARME/268
 13x 
  266   Thu Feb 24 07:25:53 2022 OH (Remote)Recover of system after crash08:00 Woke up to message from Carlo explaining
the server had crashed.
      Anydesked into the machine.
  
  265   Thu Feb 24 05:09:47 2022 CB, PE, EMInlet valve at target closed + problems with turbopumpThe turbo pump E1 is continuing to draw
too much current and the rotation frequency
has steadily decreased from 817 Hz at the
  
  264   Thu Feb 24 04:17:35 2022 CB, TD (remotely)MIDAS DAQ no longer workingDAQ server crashed around 24:00

Rebooted server but could not could
not rescue remotely - could not contact raspberry
 Bad_Time_2022-02-24_04-34-12.pngBadTime_WRTime_2022-02-24_04-34-53.png 
  263   Wed Feb 23 22:29:50 2022 PE, EM, CB (remotely)check - 23:30Motor position ok

Data rate: 1030kbytes/s

T ok
  
  262   Wed Feb 23 21:27:29 2022 TD, CNcheck Motor position ok

Data rate: 1030kbytes/s

T ok
 11x 
  261   Wed Feb 23 20:52:56 2022 CN, TDSystem wide checks
Attachments 1-5 aida01-aida05 options
 11x 
  260   Wed Feb 23 20:06:43 2022 TD CNE141 kinematics
Assuming DSSSD is 1000um thick we can expect
to observe protons for E_lab=11MeV as follows
 E141_kinematics.txt 
  259   Wed Feb 23 19:22:55 2022 CN, TDcheck 

- Motor checked , OK

SW3
 10x 
  258   Wed Feb 23 18:58:12 2022 TD CNWednesday 23 February 15.00-23.00 shift

Assorted screenshots of the CARME, CRYRING
 6x 
  257   Wed Feb 23 16:57:35 2022 CB, CNOptimising motor motionOptimised motor motion during run R58

Moved 2 mm in (20.3 potentiometer)

29.47 potentiometer
  
  256   Wed Feb 23 10:56:06 2022 Laszlo, ThanassisCurrent status11:55
Temps OK
System Check OK
 10x 
  255   Wed Feb 23 09:50:19 2022 Laszlo, ThanassisMoving detector inWe are moving the detector in run 56   
  254   Wed Feb 23 08:58:30 2022 Laszlo, ThanassisCurrent status10:00
Temps OK
System Check OK
 10x 
  253   Wed Feb 23 07:58:38 2022 Laszlo, ThanassisCurrent status09:00
Temps OK
System Check OK
 10x 
  252   Wed Feb 23 06:58:19 2022 Laszlo, ThanassisCurrent status08:00
Temps OK
System Check OK
 11x 
  251   Wed Feb 23 06:00:25 2022 Jordan, GeorgeCurrent status07:00
Pressure Stable
Temps OK
 2022-02-23_07-06-36exRate.png2022-02-23_07-06-11exTotal.png2022-02-23_07-05-42xyTotal.png 
  250   Wed Feb 23 04:55:48 2022 Jordan, GeorgeCurrent status05:55
Temps OK
System Check OK
 2022-02-23_06-00-29xyTotal.png2022-02-23_05-59-36exRate.png2022-02-23_05-59-05exTotal.png 
  249   Wed Feb 23 03:52:13 2022 Jordan, GeorgeCurrent status04:52
Pressure seems to be climbing a little
but still stable (just peaked at end of check)
 2022-02-23_04-58-19-XYtotal.png2022-02-23_04-57-17-Ex-total-hist.png2022-02-23_04-56-36-Ex-rate-hist.pngpressures-1hour.jpgpressure-6hours.jpg 
  248   Wed Feb 23 02:52:09 2022 Jordan, GeorgeCurrent status03:52

Temps OK

System Checks OK
 2022-02-23_03-58-03xyTotal.png2022-02-23_03-57-34exTotal.png2022-02-23_03-56-52exRate.png 
  247   Wed Feb 23 01:56:59 2022 Jordan, GeorgeCurrent status02:56

Temps OK

write speed ~1.2Mb/s
 2022-02-23_03-01-54xyTotal.png2022-02-23_03-00-54exTotal.png2022-02-23_03-00-11exRate.png2022-02-23_03-10-45-aida1-1*L.png 
  246   Wed Feb 23 00:54:17 2022 Jordan, GeorgeCurrent status02:04

Temps OK

Data Rate - ~1.1Mb/s
 2022-02-23_02-02-53extotal.png2022-02-23_02-02-00lowEnergyXYtot.png2022-02-23_01-59-14exRate.png 
  245   Tue Feb 22 21:57:13 2022 George, JordanCurrent status23:53

Temperatures OK

System checks OK - white rabbit
 2022-02-22_23-53-38-lowenergy-xytotal.png2022-02-22_23-50-45-Ex-rate-hist.png2022-02-22_23-49-20-Ex-total-hist.png20220223_002946.jpg 
  244   Tue Feb 22 21:09:39 2022 David, YuriCurrent statusPressure seems as before 19:10.

Merger, Tape server (WS3)
checks: DONE, writing ~1 MB/s, refreshing
 2022-02-22_22-12-55xytotal.png2022-02-22_22-12-21exrate.png2022-02-22_22-12-00extotal.png 
  243   Tue Feb 22 20:08:40 2022 David, YuriCurrent statusRecently the pressure started to raise
a bit, we have increased the temperature
from 129.1 K to 129.2 K. Current pressure
 2022-02-22_21-14-23exrate.png2022-02-22_21-14-01xytotal.png2022-02-22_21-13-11extotal.png 
  242   Tue Feb 22 19:28:35 2022 David, YurivacuumAt 19:10 Frank called us that vacuum in
sections 08 and 10 got worse by about 1.5
times. There is a possible danger that vacuum
  
  241   Tue Feb 22 19:11:18 2022 DavidCurrent statusStill trying to recover previous pressures,
more details in the next entry.

Merger, Tape server (WS3)
 2022-02-22_20-16-26eyrate.png2022-02-22_20-15-34.eytotal.png 
  240   Tue Feb 22 18:23:02 2022 David. YuryVacuum problemAt 19:10 the vacuum has increased suddenly
everywhere in the ring, roughly a factor
1.5.
  
  239   Tue Feb 22 17:32:38 2022 DavidCurrent statusMichael is modifying
the settings of the electron cooler -->
changed beam from bunched to coasting
 12x 
  238   Tue Feb 22 16:09:08 2022 David, YuryCurrent statusMerger, Tape server (WS3) checks:
DONE, writing ~1 1273kB/s, refreshing
is fine
 12x 
  237   Tue Feb 22 14:32:04 2022 David, YuryCurrent statusMerger, Tape server (WS3) checks:
DONE, writing ~1 MB/s, refreshing
is fine
 12x 
  236   Tue Feb 22 12:23:23 2022 CBSlow comparator thresholds lowered - test run13:20 Stopped run.

Slow comp thresh 0x64 -> 0x32
on all FEEs
  
  235   Tue Feb 22 12:01:46 2022 RSS, OF, ML, CB Beam OFF, Target ON Run 54 01:00

Beam optimisation since 09:25.

Target ON and open to the ring
 9x 
  234   Tue Feb 22 10:30:00 2022 RSS, OF, ML Beam OFF, Target ON Run 54 11:30

Beam optimisation. No beam since
09:25.
 10x 
  233   Tue Feb 22 10:06:50 2022 RSS, OF, MLPMT channelYR00DA1ZB is the channel for PMT rate.   
  232   Tue Feb 22 09:10:48 2022 OHAnalysis of R54_14Results of the fortran analyser programs for
R54_14
 R54_14_analyser.txt 
  231   Tue Feb 22 08:31:25 2022 RSS, OF, ML Beam OFF, Target ON Run 54 09:30

Beam optimisation. No beam since
09:25.
 10x 
  230   Tue Feb 22 07:27:28 2022 RSS, OF, ML Beam ON, Target ON Run 54 08:30

Beam ON ~1.0E7 pps

Target ON and open to the ring
 10x 
  229   Tue Feb 22 06:30:09 2022 RSS, OF Beam ON, Target ON Run 54 07:30

Beam ON ~8.0E6 pps

Target ON and open to the ring
 10x 
  228   Tue Feb 22 05:47:18 2022 JM, CB, LV, PM, AKBeam ON, Target ON Run 54 - 2 events at 10MeV!06:47

Beam ON ~2.0E6 pps, still fluctates
between 1e6 and 6e6 (like a step function)
 11x 
  227   Tue Feb 22 05:12:38 2022 JM, CB, LV, PM, AKBeam ON, Target ON Run 54 06:00

Beam ON ~1.5E6 pps, still fluctates
between 1e6 and 6e6 (like a step function)
 11x 
  226   Tue Feb 22 04:09:28 2022 JM, CB, LV, PM, AKBeam ON, Target ON Run 54 - first event at 10MeV !05:00

Beam ON ~2E6 pps, still fluctates
between 2e6 and 6e6 (like a step function)
 11x 
  225   Tue Feb 22 03:05:06 2022 JM, CB, LV, PM, AKBeam ON, Target ON Run 54 04:00

Beam ON ~5.5E6 pps, but it fluctates
between 2e6 and 6e6 (like a step function)
 9x 
  224   Tue Feb 22 02:02:11 2022 JM, CB, LV, PM, AKBeam ON, Target ON Run 54 03:00

Beam ON ~7E6 pps

Target ON and open to the ring
 10x 
  223   Tue Feb 22 00:32:35 2022 JM, CB, LV, PM, AKBeam ON, Target ON Run 54 01:30

Beam ON ~6E6 pps

Target ON and open to the ring
 2022-02-22_01-38-53-Ex-histogram.png2022-02-22_01-38-17-XYtotal.png 
  222   Mon Feb 21 21:04:08 2022 SHB, JM, CB, OH (remotely)Schottky RF view from the beam inside   pio-2022.02.21.21.54.46.895.PNG 
  221   Mon Feb 21 20:56:51 2022 SHB, JM, CB, OH (remotely)DAQ connection for ion currentsignals from ICT and CRYRADIO are now connected
to AIDA2 and AIDA5 respectively. ICT is set
to factor 200 and CRYRADIO to 40 for now.
 cry.jpg 
  220   Mon Feb 21 18:03:58 2022 SHB, JM, CB, OH (remotely)Info: signals on ion intensity for experimentCurrently 4 possibilities to have a look
at the beam, all of them are OK to check
whether there is beam or not, but some of
  
  219   Mon Feb 21 17:26:19 2022 JM, CB, SHB, OH (remotely)Beam ON run 5321/2/22 16:00

Call from main control room, beam
is ON, probably has been for several hours
 9x 
  218   Mon Feb 21 12:10:47 2022 RSS, JGAlpha background run50Beam OFF. Run started 20/2/22 18:42

System checck OK, except white
rabbit all fail
 220221_1506_aida03_1*W.png 
  217   Mon Feb 21 10:59:48 2022 RSS, JGAlpha background run50Beam OFF. Run started 20/2/22 18:42

System checck OK, except white
rabbit all fail
  
  216   Mon Feb 21 09:07:37 2022 RSS, JGAlpha background run50Beam OFF. Run started 20/2/22 18:42

System checck OK, except white
rabbit all fail
  
  215   Mon Feb 21 08:05:45 2022 RSS, JGAlpha background run50Beam OFF. Run started 20/2/22 18:42

System checck OK, except white
rabbit all fail
  
  214   Sun Feb 20 22:04:21 2022 JM, CBAlpha Background run 50 Beam OFF. Run started 20/2/22 18:42

Fast comparator threshold HEC set
to 0xff for all fees and asics to combat
  
  213   Sat Feb 19 20:08:43 2022 JM, CBBeam ON run 49Run started 19/2/22 21:05. Beam ON

Temperatures OK

System wide checks OK - white rabbit
 6x 
  212   Sat Feb 19 14:51:58 2022 JM, CBBurst high energy noiseNoticed bursts of high energy noise on
aida01 and aida02 during run 47 and 48.

Good events rate jumps from 10-20k
 2022-02-19_15-50-50-aida1-4-stat-logscale.png2022-02-19_15-47-13-aida1-2*H.png2022-02-19_15-49-48-aida2-1*H.png2022-02-20_14-01-40-aida1-2*H.png2022-02-20_14-02-55-aida1-1*H.png 
  211   Fri Feb 18 20:31:33 2022 JM, CBAlpha Background run 48Alpha background started with beam ON -
run47. Run started 16:49 18/2/22  
(beam subsequently found to be OFF)
 2022-02-19_14-45-25-leage-current.png 
  210   Fri Feb 18 13:03:02 2022 RSS, ML, CBAlpha background run4614:00

 

Check Leakage current: (see attachment
 11x 
  209   Fri Feb 18 11:07:52 2022 RSS, ML, CBAlpha background run4612:00

 

Check Leakage current: (see attachment
 11x 
  208   Fri Feb 18 08:58:08 2022 RSS, ML, CBAlpha background run4610:00

 

Check Leakage current: (see attachment
 11x 
  207   Thu Feb 17 18:19:16 2022 JM, CB, SDAlpha Background run 46Both GSI vacuum group and edinburgh ion
gauges OFF

Fees power cycled. All system checks
 2022-02-17_22-41-45-leakageCurrent.png2022-02-17_22-51-07-aida1-3*L.png2022-02-17_22-54-06-XYTotal.png2022-02-17_22-56-38-ExHist.png 
  206   Thu Feb 17 16:26:27 2022 JM, CB, SDGauges OFF, Pulser Movement testsEdinburgh group ion gauge turned OFF ->
decrease in leakage current from 10.05 uA
to 6.5 uA
 7x 
  205   Thu Feb 17 15:09:40 2022 JM,CB,SDAlpha background run4416:09

 

Check Leakage current: (see attachment
 8x 
  204   Thu Feb 17 13:12:19 2022 RSS, AGAlpha background run4314:00

 

Check Leakage current: (see attachment
 11x 
  203   Thu Feb 17 08:31:07 2022 RSS, AGAlpha background run4309:15

Check Leakage current: (see attachment
2)
 11x 
  202   Wed Feb 16 21:41:11 2022 JMRun 43 Alpha Background22:41

Check Leakage current: (see attachment
1) = 10.01 uA and falling
 8x 
  201   Wed Feb 16 21:27:31 2022 JMCryring signals, Pulser tests, Waveforms On 15/2/22 it was noted that the leakage
current increases when the motors are moved
IN. This is contary to tests conducted on
 11x 
  200   Wed Feb 16 15:27:53 2022 EM, JMRun 41 Pulser tests16:30

NOTE: Pulser is ON!

Check Leakage current: (see attachment
 11x 
  199   Wed Feb 16 12:43:05 2022 TP, RSSAlpha background run40 13:30

Check Leakage current: (see attachment
1)
 11x 
  198   Wed Feb 16 08:27:27 2022 TP, RSSAlpha background run4009:15

Check Leakage current: (see attachment
1)
 11x 
  197   Tue Feb 15 21:28:14 2022 JMNoisy ChannelsAll fees and asics checked to find noisy
channels. Channels are listed along with
the noise peak height for the low energy
 2022-02-15_22-17-51-aida1-3*L.png2022-02-15_22-23-12-aida1-4-stat-log.png 
  196   Tue Feb 15 14:59:37 2022 JM, CB, RJCPulser walkthrough16:00

Check Fee temperatures: all green
(see attachment 1)
 11x 
  195   Tue Feb 15 10:46:37 2022 RSS, LV, CBAlpha background run3711:30

Check Fee temperatures: all green
(see attachment 1)
 10x 
  194   Mon Feb 14 09:56:39 2022 CBShifters instructions 2022EMERGENCY SHUTDOWNS

1. CARME motors: Q key
on keyboard while on workspace 1 of appc218
 10x 
  193   Sun Feb 13 21:28:35 2022 JM, CBAlpha background Run 32, 35Alpha background gathered from 17:35 12/2/22
to 13:44 13/2/22 is run32. Run time ~20 hours.
Some alphas visible in aida1 1*L histograms
 6x 
  192   Sat Feb 12 19:48:38 2022 JM, CBGrounding and movement tests> Initial grounding see final grounding
from elog 187. ASIC settings for all - LEC
slow comparator 0x64. Note on 11/02/22 1.8*L
 11x 
  191   Thu Feb 10 09:12:41 2022 OH, CB, USHourly motor movementTo test effect of the motors on the leakage
current, they were cycled once per hour overnight
at approximately 50 minutes past the hour.
 220209_1014_leakage.png220210_1443_BiasFeeOn.png 
  190   Wed Feb 9 08:01:41 2022 OH, CB, G-HCResults from no beam overnight08:52 Overnight the DAQ was left running to
check if there was any individual radioactivity
in the Si.
 220209_0852_leakage.png220209_0900_leakage_shake.png 
  189   Tue Feb 8 08:13:53 2022 OH, CB, DFHopefully effect of beam tuning on detectors09:00 Detector still biased to 60V and leakage
current has been mostly stable overnight.
      Only minor fluctuations observed -
 9x 
  188   Mon Feb 7 08:09:50 2022 OH, CB and PHCARME Server setup and initial tests09:09 Arrived at GSI for comissioning beamtime.
      CARME currently in a stopped state,
with all FEEs powered off.
  
  187   Fri Feb 4 12:49:54 2022 TD, JMGrounding Tests and current status
JM plans to install new crimped, 3mm dia
copper drain wires (a la AIDA@DESPEC) this
 10x 
  186   Fri Feb 4 09:53:48 2022 JM, TD, OH (remotely)Alpha spectra overnightDAQ was left running last night from 19:30.
Detector bias 80V with a leakage current
~3.4 uA. Pulser OFF.
 8x 
  185   Thu Feb 3 22:05:33 2022 JM, TD, OH(remotely)Bias update and grounding9:30 Bias remained stable overnight - 60V
2.95 uA.

10:00 No grounding attached initailly.
  
  184   Wed Feb 2 21:53:32 2022 JM, TDDetector BiasFEE mounts for 5,6,7,8 disassembled to
access adaptor boards. No sign of debris
which could cause short on adaptor boards. 
 20220202_110757.jpg20220202_193636.jpg20220202_193651.jpgmotion.png 
  183   Tue Feb 1 14:43:20 2022 JM, TDDetector Bias, FEEsDetector is not biasing as it has in previous
tests. Last bias 15/1/22 see previous elogs,
max leakage current ~10 uA at 150V
 22-02-01_15-03-56_aida03pulserADCspectra.png2022-02-01_15-14-07_aida03_pulser_DAQserver.png2022-02-01_15-22-23aida03_waveforms_pulser.png2022-02-01_15-28-45aida03_waveforms_pulser2.png2022-02-01_15-54-57rates_aidaALL.png 
  182   Mon Jan 31 08:58:38 2022 OH, TD, JMcentos server configurationSteps taken:
- MIDAS_Releases, Embedded and Exports files
brought across from the previously working
 8x 
  181   Sat Jan 29 11:04:07 2022 JM, OHGrounding and PulserGrounding

Ground cables have been daisy chained
together from FEE to FEE. Ground cables are
 Silkscreen_Top.pdf 
  180   Thu Jan 27 21:33:40 2022 JM, OHAIDA config files, remote access, motor testPower, Ethernet and HDMI cables connected
to FEEs. To prevent cables coming out of
connectors, power and HDMI cables are zip
 20220127_101513.jpg 
  179   Thu Jan 27 15:24:02 2022 OH, JMAccess to Motors PI1. ssh <user>@lxpool.gsi.de
2. ssh <user or carme>@atppc022.gsi.de
3. ssh pi@CARMEmotorspi (Standard npg password)
  
  177   Thu Jan 27 15:19:18 2022 OH, JMEnabling internet access on the carme-gsi serverTo use both anydesk and firefox on the carme
server require an internet connection.
  
  176   Thu Jan 27 14:04:34 2022 OH, JMRemote access to CARME server1. ssh into lxpool network: ssh <user>@lxpool.gsi.de
2. ssh into atppc022.gsi.de: ssh carme@atppc022.gsi.de
(This is an rpi access server. Don't run
  
  175   Wed Jan 26 19:16:18 2022 JM, OHWater cooling, FEE MAC addressWater cooling has been connected to the
FEE's. Flow meter installed to outlet
manifold by way of two right angled pieces.
 20220126_162435.jpg20220126_162448.jpg20220126-142809.jpg 
  174   Sat Jan 15 15:38:25 2022 JM, OH, TDFEE installation, cable managementAll 8 FEEs have been installed in their
holders.

The damaged feedthrough does not
 20220114_104819.jpg20220114_105152.jpg20220114_105213.jpg20220115_133808.jpg20220115_133820.jpg 
  173   Sat Jan 15 11:28:10 2022 JMInventory 


Vaccum
DN250CF 1x gaskets
    
DN200CF 5x gaskets  
DN160CF 1x gaskets,
 20220115_162649.jpg20220115_162712.jpg 
  172   Fri Jan 14 10:00:18 2022 TD, OH, JMFriday 14 January
11.00 Per https://elog.ph.ed.ac.uk/CARME/170
and https://elog.ph.ed.ac.uk/CARME/171 issues
  
  171   Thu Jan 13 10:33:24 2022 JM, OH, TDAdaptor Board misallignmentThe ERNI connector is not central on the
adaptor boards causing misallignment with
the FEE. 
 20220112_160951.jpg20220113_145105.jpg20220113_145147.jpg 
  170   Wed Jan 12 20:07:20 2022 JM, OH, TDFEE holder installation4 FEE holders installed on CARME. Mounting
procedure devised due to limited working
space to install.
 10x 
  168   Tue Jan 11 12:45:15 2022 TD, JM, OHCoolant manifold installation + detector pin tests2x cooling water manifolds with 2x 8 ports
have been installed - see attachments 1 &
2
 20220111_113628.jpg20220111_113613.jpg20220111_111428.jpg 
  167   Mon Jan 10 20:52:53 2022 JM, TD, OHBaking tent removed, VI testsBaking tent, frame and trays fully
removed from CARME chamber. Removal of baking
frame required removing air lines from upper
 20220110_175547.jpg20220110_175811.jpgvi-curve.png 
  166   Tue Dec 7 09:39:59 2021 CB (remotely)Gate valves closedDry run complete.

YR09 section valves closed. Section
isolated. Manual valve between electron target
  
  165   Tue Nov 30 10:49:43 2021 CB (remotely) GVGate valve openedGSI vacuum division IE514 gauge connected.

Gleb reports gate downstream opened.
Vacuum goes up and recovers as expected.
 vacplot24.png 
  164   Sun Nov 28 15:57:45 2021 CB (remotely)Nov 2021 temperaturesAttached  211128164424_temperatures.zip 
  163   Fri Nov 26 10:01:45 2021 CB (remotely) MLPower cut in the CRYRING caveML reports power cut in CRYRING cave. Reasons
unknown. No effect on vacuum, but top valve
closed for safety reason. Ramping down temperature.
  
  162   Wed Nov 24 12:08:08 2021 CB + ML OGIon pumps onFound SIP power unit for D2000 #4 not functioning
correctly. Max current regardless of ion
element connected to.
 vacplot24.pngvacplot.pngCARMEtemps.png 
  161   Tue Nov 23 08:49:33 2021 CB + MLNEG activation completedFound temperatures and pressure stabilised
overnight. See attached.

12:00 Began activation of 3x UHV1400
 vacplot24.pngCARMEtemps.pngvacplot24-1.pngCARMEtemps-1.png 
  160   Mon Nov 22 08:06:01 2021 RSS CB + MLNEG activation starts08:20 Temperature of channels 1-3 and 5-6
were reduced to 120 degrees. Immediately
after, the conditioning of the NEGs was stopped
 IMG_5674.JPGCARMEtemps.pngvacplot.png 
  159   Fri Nov 19 12:03:51 2021 CB RSSConditionings NEGsIncreased conditioning temperature in D2000
#3 and 4 (behind detectors) to 150C from
130/140C. No appreciable change in temperature.
 CARMEtemps.pngvacplot.png 
  158   Thu Nov 18 13:50:51 2021 CB RSSThermocamera imagesUsed thermocamera provided by GSI beam
diagnostic division to take some pictures
of YR09. See attached.
 14x 
  157   Thu Nov 18 12:29:50 2021 CB RSSConditioning D2000 NEGsD2000 thermocouples report temperatures
around 100C (D2000 #1,2) and 120C (3,4).
1,2 are in the intermediate chamber, 3,4
 vacplot.pngCARMEtemps.png 
  156   Wed Nov 17 07:12:22 2021 RSS CB + ML (remotely)CARME baking with tape continues 17 NovCARME baking with heating tape continues

Left overnight at -

Ch1-3: 140 degrees
 7x 
  155   Tue Nov 16 12:05:13 2021 CB RSSCARME baking with tape continuesCARME baking with heating tape continues

Left overnight at 100C. Turned
up this morning at 9:00 to 120C.
 CARMEtemps.png20211116_132048.jpg20211116_155138.jpg20211116_155857.jpg 
  154   Fri Nov 12 08:54:11 2021 RSS ML + CB (remotely) NK AK NPFirst CARME baking attempt07:50 Small leaks (near the motors and
upper valve) were detected in the tent which
were covered with Al foil.
 Capture.PNG200W_heaters.svg40W_heater.svg 
  153   Thu Nov 11 14:01:00 2021 AK, MLHeater channel layoutsSchematic layout of heaters and channel
assignment attached. Table kindly provided
by AK. I hope the conversion from excel to
 2020.11.05_Cryring-YR09-baking-layout.pdf 
  151   Thu Nov 11 11:44:58 2021 RSS + ML OG + CB (remotely)CARME baking startedWith the help of OG, the baking tent was
built. MG started baking around 11:30 am
with a rate of 0.2 K/minute.
 IMG_5535.JPGIMG_5537.JPGIMG_5531.JPGIMG_5534.JPGIMG_5539.JPG 
  150   Wed Nov 10 18:38:16 2021 RSS TD + ML OG AK NKCARME wrapped in heating tapeHeating and electronic experts were in
CRYRING and were unhappy with the damaged
wire. Heaters were opened by OG, but no damage
 IMG_5514(1).JPGIMG_5517(1).JPGIMG_5518.JPGIMG_5520.JPGIMG_5521(1).JPG 
  149   Wed Nov 10 18:24:12 2021 RSSThermocouple labelling1. Detector

2. Chamber back

3. Strain relief
 labeling.JPG.svgLabelling.svgIMG_5512.JPG 
  147   Wed Nov 10 14:41:12 2021 TD RSS + CB (remotely)Wrapping CARME in heating tapeML reports that baking of the upstream section
(gas jet interaction chamber plus e-target)
has commenced - initially to 50 deg C to
  
  146   Tue Nov 9 15:03:29 2021 RSS + OGBurnt cables issuesUpper part of the frame was mounted. In
order to do so, the valve was closed, turbo
wire and hose were disconnected and then
 7x 
  145   Mon Nov 8 17:19:02 2021 RSS + OGNeg and ion cables connectedNeg and ion pump cables were labeled and
connected.

Kapton tape wrapped around the
 IMG_5480.JPGIMG_5483.JPGIMG_5488.JPG 
  144   Sat Nov 6 14:21:10 2021 CB RSSPreparation for bakeout tent mounting + to do for next weekConnected pneumatic hoses prepared by Gleb.
Opened flow to pressure reducer set at 2
bar. Ok. Attempted to operate pneumatic motors.
  
  143   Fri Nov 5 12:27:11 2021 CB RSS + DR NP ML USFirst pump down of YR09Tightened all flanges.

Added Pirani gauge and third IE514
to interaction chamber.
 20211105_131748.jpg20211105_135918.jpg20211105_135929.jpg20211105_140451.jpg20211105_150616.jpg 
  142   Wed Nov 3 16:39:01 2021 CB RSS + NP DR NK MLInteraction chamber lifted in placePrepared to move interaction chamber in
place. Ok CARME side, flange has M10 bolts.
On interaction chamber side i.e. bellows
 20211103_161553.jpg20211103_161813.jpg20211103_175457.jpg 
  141   Wed Nov 3 11:18:11 2021 CB RSS + DR NK MLLeak closedFound CARME at 1.0E-6 mbar. Beginning leak
test.

 
 20211103_110244.jpg20211103_110414.jpg 
  140   Tue Nov 2 12:45:36 2021 CB + DR NKIssues with CARME feetAttempted to close CARME as carefully as
possible.

Swapped out one foot for another
 20211102_134446.jpg 
  139   Mon Nov 1 14:48:16 2021 CB + ML DRCARME openedConfirmed leak as per previous Elog.

Tightened to 100 Nm - no effects.

Tightened to 130 Nm - bottom leak
  
  138   Sun Oct 31 13:55:13 2021 CB OHLeak testsFound CARME at 2E-7.

Closed valve on top of roughing
pump. Clamp was not tight. Pressure still
 20211031_155820.jpg 
  137   Sun Oct 31 08:05:15 2021 CB OH + DR MLCARME closed again + feedthroughs labeled(Fri 29 October)

Cleaned wire seal recess and labeled
thermocouples and flanges to identify p-n
 11x 
  136   Sun Oct 31 07:55:39 2021 CB JM + OHStrain relief mounted(Thu 28 October)

All strain relief extension plates
mounted behind the wires, using SS countersunk
 20211028_190026.jpg20211028_192251.jpg20211028_192210.jpg 
  135   Sun Oct 31 07:41:20 2021 CB JM + RSSWires plugged in DSSDs (Wed 27 October)

Started with top-most flange. Attemptedto
plug in MACOR lead in DSSD plug in preparation
 8x 
  134   Sun Oct 31 07:29:17 2021 CB JM + RSS OGDetectors mounted on plate in CARME(Wed 27 October)

Dismounted plate from rod. Dismounted
broken detectors from plate and placed back
 8x 
  133   Sun Oct 31 07:21:09 2021 CB JM RSSDetectors arrived in GSI(Tue 26 October)

Two new CARME DSSD arrived in GSI
and collected. Visually inspected both sides.
 6x 
  132   Fri Oct 29 15:09:27 2021 CB JM + RSS OG DRPreparation to mount new DSSDs(Mon 25 October - Tue 26 October)

Considered different strategies
to mount DSSDs inside CARME, while waiting
 6x 
  131   Sat Oct 23 12:58:11 2021 JMGSI vacuum and bakeout testing summaryAttachment 1 shows the pump-down of the
CARME chamber at GSI before installation
of kapton cabling inside the chamber and
 GSI_fullpumpdown.pngGSI_pumping.pngBakeout-elog.pngfit-elog.pngActivation-elog.png 
  130   Fri Oct 22 13:22:48 2021 TDCARME FEE64 adaptor PCB   10x 
  129   Fri Oct 22 13:11:26 2021 TDMSL type TTT14 assembly drawings & pin assignments   C-3434.pdfC-3517.pdf 
  128   Thu Oct 21 20:26:44 2021 JM TDThermocouple and Connector cablesNEG pump electrical connections tested
- all connections sound. 

Detector carriers have been redrilled
 10x 
  127   Mon Oct 18 16:25:11 2021 JM RSS TDNEG rotation + cable removalsKapton cabling and the broken ceramic detector
holder have been separated. Required holding
jacking plate in a vice and using lots of
 Screenshot_20211018-174141_Signal.jpg20211018_111130.jpg20211018_100015.jpg 
  126   Sun Oct 17 11:48:48 2021 TD RSSSunday 17 OctoberLooking downstream the RHS motor assembly
has  loose green/yellow (gnd?) see attachment
1
 14x 
  125   Sat Oct 16 17:25:47 2021 RSS TDBroken detectorsOne of the detectors was damaged while
mounting (see pictures 1-3).

Second detector was found already
 IMG_5098.JPGIMG_5097.JPGIMG_5096.JPGIMG_5106.JPGIMG_5105.JPG 
  124   Fri Oct 15 19:37:12 2021 RSS TD + DRFriday 15 OctoberRing seal is out. See picture 1.

Bellow (towards CARME) was installed
in the gas jet chamber. Attached are some
 8x 
  123   Thu Oct 14 15:54:47 2021 TD RSSThursday 14 OctoberAttachment 1 - what is function of the 4x
c/s holes indicated?
 IMG_5056.JPG.jpgIMG_5053.JPG 
  122   Wed Oct 13 15:28:22 2021 RSS TD + OGSplit funnelsSplit funnels installed on 4 (of 8) 2x78
way D connector feed-throughs.
 7x 
  121   Wed Oct 13 15:16:12 2021 TDOrientation of 2x 78 way D connector feedthroughs
Looking downstream
 20211013_152518.jpg20211013_152529.jpg20211013_152549.jpg20211013_152606.jpg 
  120   Wed Oct 13 12:06:09 2021 RSS TDFlanges cleanedRSS & TD had some success cleaning the COF600
flange surfaces of the staining and residues
observed when the downstream COF600 section
 12x 
  119   Wed Oct 13 11:59:23 2021 TD[How to] Open COF600 copper wire seals
Use the M10 jacking points provided top/bottom
and 
 20211013_103806.jpg20211013_103800.jpg 
  118   Tue Oct 12 13:54:21 2021 RSS TD + OD DRCARME openedWith the assistance of Oemer and Davide all
of the M22 bolts removed from the downstream
section of the CARME chamber. To separate
 20x 
  117   Tue Oct 12 09:22:37 2021 RSS TD + OG DRMotors problem solvedNeg and ion cables were taken off and were
put in the box.

Top support was taken off.
 IMG_4971.JPGIMG_4970.JPG 
  116   Mon Oct 11 11:24:16 2021 RSS TD MLValve support and cable labelingSplit funnels were given to Oemer for cleaning.
Have received them back after lunch.

Valve support is installed again
 IMG_4962.JPGIMG_4969.JPG.svgIMG_4968.JPG.svg 
  115   Sat Oct 9 09:47:33 2021 CBTo do list for next week0. Give split-funnels to OG or Grossmontage
to clean. Mount back foot support for gate
valves. Critical when we split.
 Capture.PNG 
  114   Sat Oct 9 09:44:36 2021 CB RSSHeaters removed + motors testsRemoved thermocouples, heaters, RE72 modules
and leftover baking tent. Support octagon
removed except topmost part which requires
  
  113   Fri Oct 8 17:56:35 2021 CB RSSMotors testAttempted first motor test in XHV. Wired
and connected limit switches and string potentiometer.

Set up raspberry pi to control
 20211008_184731.jpg20211008_184731.jpg 
  112   Thu Oct 7 08:40:09 2021 CB RSSCARME in XHVCARME reached 9E-12 this morning

Ion pumps on
  
  111   Wed Oct 6 15:36:14 2021 CB RSSNeg activation tests -3Attempted to activate 2xUHV1400 connected
to bottom C4, channel #2 using P 200 W, t
rise 30 min, t hold 90 min.
  
  110   Wed Oct 6 09:47:30 2021 CB RSSNeg activation tests -2Attempted activating 2xUHV1400 connected to
top C4, channel #3 with P 300 W (450 C?),
t rise 30 min, t hold 90
  
  109   Wed Oct 6 09:39:59 2021 PB CBOriginal dirty assembly of CARME internalsPB found pictures of the original dirty assembly,
before screws and components were shipped
to DL.
 7x 
  108   Tue Oct 5 17:30:01 2021 CB RSSNEG activation testsFound D2000 #1 activated and at 250C (25W)

to prevent getting dirty when other NEGs
 20211005_131259.jpg20211005_171403.jpg20211005_161317.jpg 
  107   Tue Oct 5 11:44:11 2021 CB, TD SAES manuals & cable drawingsNEG power
SIP power
UHV1400 operating instructions
 8x 
  106   Mon Oct 4 20:30:46 2021 RSS JM CB (remotely)CARME baking status -21
Current temperature ~95 C (on manual
mode)
See plot and screen attached.

Current
pressure 2.86E-10
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-10-04_21-28-28.pngScreenshot_from_2021-10-04_21-29-37.png 
  105   Mon Oct 4 09:19:11 2021 JM RSSActivation of NEG elements9:30

Ion pumps de-gassed by switching
on and off multiple times. Large pressure
 IMG_4880.JPGIMG_4881.JPGIMG_4882.JPGIMG_4883.JPG 
  104   Mon Oct 4 06:34:58 2021 RSS JM CB (remotely)CARME baking status -20
Current temperature ~110 C (on manual
mode)
See plot and screen attached.

Current
pressure 3.20E-8
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-10-04_07-33-14.pngScreenshot_from_2021-10-04_07-34-14.png 
  103   Sun Oct 3 08:36:01 2021 RSS JM CB (remotely)CARME baking status -19
08:36
Current temperature ~132 C (on
manual mode RE72-1: 132 C, RE72-2: 130 C)
See
plot and screen attached.

Current pressure
 Screenshot_from_2021-10-03_09-33-30.pngScreenshot_from_2021-10-03_09-34-24.png 
  102   Sat Oct 2 22:14:14 2021 RSS JM CB (remotely)CARME baking status -18
Current temperature ~132 C (on manual
mode RE72-1: 132 C, RE72-2: 130 C)
See plot
and screen attached.

Current pressure
 Screenshot_from_2021-10-02_23-12-09.pngScreenshot_from_2021-10-02_23-13-16.png 
  101   Sat Oct 2 08:26:49 2021 RSS JM CB (remotely)CARME baking status -17
Current temperature ~132 C (on manual
mode RE72-1: 132 C, RE72-2: 130 C)
See plot
and screen attached.

Current pressure
 Screenshot_from_2021-10-02_09-25-40.pngScreenshot_from_2021-10-02_09-24-44.png 
  100   Fri Oct 1 21:47:51 2021 CB (remotely)CARME baking status -16Current temperature ~132 C (on manual mode
RE72-1: 132 C, RE72-2: 130 C)
See plot and screen attached.
 screen.pngTemps.png 
  99   Fri Oct 1 07:17:46 2021 RSS JMCARME baking status -15
Current temperature ~132 C (on manual
mode RE72-1: 132 C, RE72-2: 130 C)
See plot
and screen attached.

Current pressure
 Screenshot_from_2021-10-01_08-17-02.pngScreenshot_from_2021-10-01_08-16-41.png 
  98   Thu Sep 30 18:16:52 2021 RSS JMCARME baking status -14
Current temperature ~132 C (on manual
mode RE72-1: 132 C, RE72-2: 130 C)
See plot
and screen attached.

Current pressure
 Screenshot_from_2021-09-30_19-18-44.pngScreenshot_from_2021-09-30_19-18-08.png 
  97   Thu Sep 30 06:29:39 2021 RSS JMCARME baking status -13
Current temperature ~130 C (on manual
mode)
See plot and screen attached.

Current
pressure ~4.07E-7 mbar
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-09-30_07-29-02.pngScreenshot_from_2021-09-30_07-28-09.png 
  96   Wed Sep 29 15:34:07 2021 RSS JMCARME baking status -12
Current temperature ~130 C (on manual
mode)
See plot and screen attached.

Current
pressure ~4.51E-7 mbar
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-09-29_16-32-50.pngScreenshot_from_2021-09-29_16-31-48.png 
  95   Wed Sep 29 13:13:51 2021 JM RSS PB(remotely)Detector frame assembley29/9/21

We have opened the cleaned parts
for assembley of the moving detector frames.
 new_carrier_simple_holes.PDFScreenshot_20210929-110343_Telegram.jpg20210930_164625.jpg20210930_164650.jpg 
  94   Wed Sep 29 09:27:38 2021 CB (remotely), RSS JM MLPower cutSudden and unexpected power cut at 10:02 German
time, affecting all the target hall.
  
  93   Wed Sep 29 06:49:41 2021 RSS JMCARME baking status -11
Current temperature ~130 C (on manual
mode)
See plot and screen attached.

Current
pressure ~6.08E-7 mbar
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-09-29_07-48-03.pngScreenshot_from_2021-09-29_07-48-36.png 
  92   Tue Sep 28 18:53:13 2021 RSS JMCARME baking status -10
Current temperature ~130 C (on manual
mode)
See plot and screen attached.

Current
pressure ~9.98E-7 mbar
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-09-28_19-54-16.pngScreenshot_from_2021-09-28_19-51-19.png 
  91   Tue Sep 28 12:18:54 2021 RSS JMCARME baking status -9
Current temperature ~130 C, was set
to 130 C on manual mode around 10:00 am
See
plot and screen attached.

Current pressure
 Screenshot_from_2021-09-28_13-17-51_1.pngScreenshot_from_2021-09-28_13-18-18.png 
  90   Tue Sep 28 06:40:22 2021 RSS JMCARME baking status -8
Current temperature ~120 C, increasing
See
plot and screen attached.

Current pressure
~1.07E-6 mbar
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-09-28_07-38-53.pngScreenshot_from_2021-09-28_07-39-22.png 
  89   Mon Sep 27 21:33:50 2021 CB (remotely)CARME baking status -7Current temperature ~87 C, increasing
See plot and screen attached.
Thermocouple on CARME foot side (1-4) may
 Temps.pngScreen.png 
  88   Mon Sep 27 17:53:35 2021 JM RSS Baking Jacket upgrade + NEG controllers connectedAdditional baking jacket sections for the
turbo section arrived today. Baking was halted
at ~11:00 to allow for the chamber to cool
 20210927_151650.jpg20210927_151706.jpg20210927_151721.jpg20210927_170139.jpg 
  87   Mon Sep 27 11:09:48 2021 CB (remotely)Temperature vs Pressure plotAttached.  Temps.pdf 
  86   Mon Sep 27 06:42:45 2021 RSS JMCARME baking status -6
Current temperature ~102 C. Was set
in the manual mode since last evening 18:54.
See
plot and screen attached.


Current
 Screenshot_from_2021-09-27_07-41-06.pngScreenshot_from_2021-09-27_07-41-39.png 
  85   Sun Sep 26 17:20:13 2021 RSS JM CB (remotely) CARME baking status -5
Current temperature ~105 C
See plot
and screen attached.


Current
pressure 6.08E-7 
See
https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?rtime=OK4kVZKB2Ug
 Screenshot_from_2021-09-26_18-19-26.pngScreenshot_from_2021-09-26_18-18-23.png 
  84   Sun Sep 26 07:41:00 2021 CB (remotely)CARME baking status -4Current temperature ~87C

See plot and screen attached.
 Temps.pngScreen.png 
  83   Sat Sep 25 19:01:50 2021 CB (remotely)CARME baking status -3Baking automatically stopped due to negative
gradient in on thermocouple for 10 minutes
straight. 
 Temps.PNG 
  82   Sat Sep 25 07:23:06 2021 CB (remotely)CARME baking status -2Current temperature ~90 C
However note setpoint is at 102 C. It appears
we are baking at full power, but too many
 temp_plot.pngtemps.png 
  81   Fri Sep 24 15:36:34 2021 CB (remotely)CARME baking statusCurrent temperature ~64 C

See plots attached
 Temp.pngTemps.png 
  80   Fri Sep 24 09:44:58 2021 JM MLVacuum gauge readoutThe analog readout of the Combivac controller
for the IE514 ion gauge has been set up,
readings are plotted to http://web-docs.gsi.de/~lestinsk/vacplot.php.
  
  79   Fri Sep 24 08:47:36 2021 JM RSS CB(Remotely)Baking Baking halted on 23/9/21 16:16 as connection
to TC08 module was lost. USB cable connection
to TC08 module appears to have been damaged
  
  78   Fri Sep 24 07:04:57 2021 RSS JMIE 514 pin arrangement and degas instructionsFabre (German)      
Color (English)

grau                        
 IE514_pin_arrangement.JPGdegas_function.jpg 
  77   Thu Sep 23 14:19:27 2021 CB (remotely)Checking baking remotely - instructions1. Connect to pi on CRYRING local network

ssh pi@192.168.207.127
 Temp.png 
  76   Thu Sep 23 13:31:12 2021 JM RSS MLIE514 Gauge and BakeoutCARME setup checked by vaccum group this
morning. 

Both IE514 gauges de-gassed. To
 20210923_113239.jpg20210923_134339.jpg20210923_134355.jpg20210923_135954.jpg 
  75   Wed Sep 22 14:44:51 2021 JM RSS MLCARME leak test + bakeout tentOn 21/9/21 CARME was connected to the leak
tester. Leak testing showed no apparent leaks,
extra time required to reach <1e-4 mbar
 20210922_145646.jpg20210922_145933.jpg20210922_151728.jpg20210922_152052.jpg20210922_152113.jpg 
  74   Wed Sep 22 08:30:08 2021 CB (remotely)CARME pressure during first XHV testCARME pressure moved to

https://uoe-my.sharepoint.com/:x:/g/personal/cbruno2_ed_ac_uk/EVbsVOubNHRLj0PKiFIvd00BClMJ6WSJ1UDAyLA2F3R4jA?e=hEoZt7
  
  73   Tue Sep 21 08:20:39 2021 MLCARME installations 




  
  72   Mon Sep 20 11:45:45 2021 JM RSS MLCARME installationsIon pump, RGA and additional gauge installed
on the chamber.

Our gauge is the one mounted above
 6x 
  71   Sun Sep 19 09:11:34 2021 CB (remotely)Baking RasPi statusAccessed Pi remotely 

( 1. Without the Internet, the Pi has no
  
  70   Fri Sep 17 16:42:25 2021 JM RSS ML + OGCARME Realignment + Thermocouple installationLaser surveying team worked till 11. Chamber
was too high by 3mm close to the jet target
and 6mm by the turbo pump (towards the dipole). 
 8x 
  69   Thu Sep 16 15:24:29 2021 JM RSSCARME vented + thermocouple feedthroughChamber has been vented back to atmosphere. 

Motor was able to be pulled back
to insert bloacking pin once at atmosphere.
 1.jpg2.jpg3.jpg 
  68   Sat Sep 11 16:01:44 2021 CB RSSPreparations for shutdownFound CARME pressure at 2E-7 mbar

Raspberry pi took pictures until 4 am and
 turbo_pump.pnglog_scale.png 
  67   Fri Sep 10 18:09:14 2021 CB RSS MLLeak test + baking system testLeak tested CARME via He leak tester + He

bottle. No leaks could be found. Some 
  
  66   Fri Sep 10 10:50:55 2021 CB RSS MLPressure after overnight pump downPressure found in 10-7 mbar range.

Decided to leak test anyway for safety.
 20210910_101131.jpg 
  65   Thu Sep 9 13:01:07 2021 CB RSS + OGAll feedthrough flanges mounted and motor rotatedMoved cables that touched neg pumps. See 
photos. Please bear in mind perspective.
Note avoiding touching chamber 
 20210909_111933.jpg20210909_112120.jpg20210909_112125.jpg20210909_133027.jpg 
  64   Wed Sep 8 17:03:07 2021 CB RSS + OG NBSix feedthrough flanges mountedContinued to mount flanges as per previous
ELOG entry.
Peter also remarked that the wires look a
 23x 
  63   Wed Sep 8 10:52:54 2021 CB RSS + OGFirst feedthrough flange mountedAssembled feedthrough flange with re-cut 
SS support bracket. M3 vented on the 
sides, M3x30 partly threaded on top. Top
 20210908_101743.jpg20210908_111958.jpg20210908_112002.jpg20210908_112006.jpg20210908_112010.jpg 
  62   Tue Sep 7 14:10:02 2021 CB RSS + OGStrain relief SS support re-drilledRe-drilled SS supports in order to fit M3
screws.
  
  61   Tue Sep 7 12:40:43 2021 CB ML + RHCARME survey preparationRudi and survey group representative came

to CARME. 
  
  60   Tue Sep 7 11:37:05 2021 CB RSS + OGUpdate on strain relief screw issuesTested every strain relief. M3 screws get
stuck at different points in each hole. Only
one good hole out of 16
  
  59   Mon Sep 6 14:13:17 2021 CB MLMotors mounted - first attemptMounted both  motors on CARME. Started 
with outside motor.
 20210906_113522.jpg20210906_113519.jpg20210906_115601.jpg20210906_152607.jpg20210906_143944.jpg 
  58   Sat Sep 4 15:54:50 2021 CB RSSMotor mounting preparationPrepared the motors to be mounted and 
found all components required. No issues.
 20210904_162517.jpg20210904_162520.jpg 
  57   Fri Sep 3 15:55:00 2021 CB RSSIssues with cable clampsAttempted to mount cable clamps for strain

relief on inner part of Allectra 
 20210903_154614.jpg20210903_162519.jpg 
  56   Fri Sep 3 14:14:40 2021 TDLeybold IE514 manual & calibration data   20210903_141201.jpgIonivac_Sensors_IE414_IE514.pdf 
  55   Fri Sep 3 08:14:51 2021 CB RSSIssues foreseeable splitting CARMEIn order to install the detector supports

and eventually install the detectors 
 7x 
  54   Fri Sep 3 08:12:39 2021 CB RSSPressure after overnight pump down03.09.2021   09:00   5.27E-7 mbar     
03.09.2021   13:00   4.08E-7 mbar       
           
 20210903_085646.jpgIMG_4487.JPG 
  53   Thu Sep 2 21:04:26 2021 CB RSS ML + DR OGGate valves mounted + pump downMounted both gate valves and support. Gate

valves could not be installed one bolt 
 6x 
  52   Thu Sep 2 10:41:16 2021 CB RSS + DR OGCARME connected to the CRYRINGConnected CARME to the CRYRING via tube 
plus bellows. See attach.
 20210902_114031.jpg 
  51   Wed Sep 1 17:14:16 2021 CB RSS + DR MLCARME mounted on the CRYRINGLifted CARME with Al support on the 
CRYRING. No issues during transportation.
 20210901_162435.jpg20210901_173059.jpg20210901_174157.jpg20210901_134635.jpg20210901_173059.jpg 
  50   Wed Sep 1 12:05:28 2021 CB RSSPreparation for CARME on CRYRING YR09Mounted additional cross member for motor

support. See attach 1
 20210901_125504.jpg20210901_125517.jpg 
  49   Tue Aug 31 18:56:35 2021 CBCARME status(ELOG does not allow more pictures to be added
to previous entry)
 9x 
  48   Tue Aug 31 18:34:41 2021 CB RSS + DR OGCARME on Al standLifted CARME off the floor and mounted feet
on sides. It was found impossible to put
four bolts for each foot
 20210831_144545.jpg20210831_171442.jpg20210831_171447.jpg20210831_171449.jpg20210831_171453.jpg 
  47   Tue Aug 31 11:55:11 2021 CB RSSLast preparations for CARME liftFound strut bolts in the bag with 
spherical washers. Mounted the struts and
 16304077162843806956479048661374.jpg16304077904321905824276870110392.jpg 
  46   Tue Aug 31 07:09:54 2021 CB RSS (rem) JMPreparation for mounting(30 August 2021)

The current state of YR09 is as per attach
 6x 
  45   Wed Aug 25 07:02:41 2021 RSS TD25-31 August
Pirani  IE514
mbar    mbar


25/8/21
08:00 0.0030 1.86e-8

----------------------------------------------------

26/8/21   09:00 
 19x 
  44   Wed Aug 18 11:58:49 2021 NTD RSSMisc fittings and fasteners plus gasket inventoryAttachments 1-3 fasteners, fittings found
amongst earlier shipments. I assume that
the STFC DL cleaned items are for the internal
 22x 
  43   Wed Aug 18 07:07:26 2021 RSS TD18-24 August
Pirani  IE514
mbar    mbar


18/8/21
08:00 0.0034 3.90e-8
18/8/21 17:00 0.0032
3.72e-8


 
 25x 
  42   Fri Aug 13 07:28:37 2021 RSS TDFriday 13-17 August Pirani  IE514
mbar    mbar
 23x 
  41   Thu Aug 12 09:16:42 2021 TD RSSThursday 12 August
Attachment 1 - IE414/514 feedthrough wiring
diagram
 13x 
  40   Wed Aug 11 12:30:40 2021 TD RSSWednesday 11 August
Attachments 1 & 2 - 2x SAES D-2000 re-fitted
to side ports
 8x 
  39   Tue Aug 10 12:22:56 2021 TD RSSTuesday 10 August
Attachments 1-3 - 2 of 4 SAES D2000 installed
at same ports used for STFC DL XHV tests
 20210810_115555.jpg20210810_115607.jpg20210810_115617.jpg 
  38   Mon Aug 9 12:36:00 2021 TD, RSS, ABDMonday 9 August
Attachments 1-5 - CARME shipment in CRYRING
hall
 7x 
  37   Mon Dec 7 14:29:12 2020 JMCARME packing up   20201207_122353.jpg20201207_113905.jpg20201207_110714.jpg 
  36   Fri Dec 4 16:49:36 2020 TDFriday 4 December   7x 
  35   Wed Nov 25 10:39:37 2020 TDWednesday 25 November
10.39
 7x 
  34   Tue Nov 24 12:24:01 2020 JMRGA scansRGA laptop passcode: tw%11&STA-
  

RGA scans set up and plotting data
 20201124_124107.jpg 
  33   Tue Nov 10 12:25:29 2020 JMCable harnessesThe length of the wire needed was estimated
with the aid of a scale image of the detectors
in the CARME chamber and foam model pieces.
 20201102_155336.jpgFigure_1.png20201102_154648.jpgPhotos.zip 
  32   Thu Oct 29 08:02:29 2020 CB, JM (remotely)CARME pressureAttached is the temperature plot for bakeout
period including tags for NEG activation
etc.
 20201029_080001.jpgBakeout_pump_down.png20201119_temps.png 
  31   Wed Oct 28 10:41:57 2020 TDWednesday 28 October
10.32
 6x 
  30   Mon Oct 26 10:35:05 2020 JM, CB(remotely)Cooling10:10 Pressure on the chamber = 3.1e-8mbar.
RE-72 temperatures are ~120-125C with set
limits at 80C. D2000 temperatures are
 Screenshot_from_2020-10-26_14-10-08.png20201027_0803_temps.png27102020_pump_down.png27102020_pump_down.png 
  29   Thu Oct 22 22:15:00 2020 CB (remotely)Cooling down after first NEG activationThu 22 October

22:15 Temperatures stables, slowly decreasing.
 7x 
  28   Thu Oct 22 10:39:40 2020 TDThursday 22 October
10.40
 19x 
  27   Mon Oct 19 13:57:52 2020 JMNeg ActivationNeg and Neg-Ion pumps have been connected
up to the control modules. Controller on
the right is connected to the D-2000s. Middle
 Photos.zip20201019_154921.jpg 
  26   Mon Oct 12 10:49:36 2020 JMFirst Bakeout of CARME with pumps (cont)12 October 

10:00 Bakeout temperatures stable.
Pressure on the backing line is 3e-7mbar
 temp6.png 
  25   Mon Oct 5 08:21:40 2020 CB (remotely), JMFirst bake of CARME with pumps (cont.)5 OCTOBER

08:21 Temperatures stable overnight. See
 6x 
  24   Wed Sep 30 08:10:36 2020 CB (remotely)First bake of CARME with pumps(NOTE: Raspberry Pi internal clock appears
to be on GMT, rather than GMT+1 due to daylight
saving.)
 19x 
  23   Mon Sep 28 13:04:27 2020 JMBakingI have (fingers crossed) got the baking
stepping up nicely now. I have used some
of the outer shell to act as a shield and
 20200928_081831.jpg20200928_130239.jpg 
  22   Sat Sep 26 09:31:46 2020 JM, CB (both remotely)Baking over weekendSat 26 Sep

09:15 Baking started automatic
mode
 temps.pngtemps2.pngHeaters.jpg20200927_1732_temps.png 
  21   Fri Sep 25 12:58:33 2020 JMFriday 25/09/2010:00   Vessel P = 3.99e-8 mbar, 
RGA P = 1.4e-6 mbar 

10:54   Vessel P = 3.89e-8
 Photos.zip 
  20   Thu Sep 24 10:04:58 2020 JM, TDThursday 24 September
Following overnight pumping by Leybold turbo
pump
 20200924_152852.jpgPhotos.zip 
  19   Wed Sep 23 13:34:32 2020 JM, TDWednesday 23 September
Connected Leybold Ionivac IE514 to Leybold
Combivac CM52 Vacuum Gauge Controller
 20200923_170441.jpg20200923_170455.jpg20200923_170415.jpg20200923_161415.jpg20200923_161402.jpg 
  18   Wed Sep 23 13:34:04 2020 JMTuesday 22 SeptemberTurbo-pump Issue approximately 13:00 22/9/20.

While moving the baking octagon
into position, the power connector became
  
  17   Mon Sep 21 09:51:57 2020 JMCARME StatusCooling of baking volume finished over
the weekend, attached are some plots of the
bakeout test. Bakeout2.png is the thermocouple
 Graphs.zip 
  16   Fri Sep 18 10:28:57 2020 JM, CB(remotely)Baking status10:28
Reducing temperature in steps. System cooling
down. See attached.
 20200918_1029_temps.png 
  15   Thu Sep 17 10:13:43 2020 JM, CB(remotely)Bakeout cooling and pumping of chamberThe Chamber has continued to pump overnight
and we have reached a pressure of 3.3e-6
mbar as of 10:15. Power cable for the hot
 Photos.zip20200917_1428_temp_last.png 
  14   Wed Sep 16 17:46:36 2020 JMPumping of ChamberA pump cart and leak cart have been connected
to the chamber via the top turbo at the back
of the chamber. An air line has also been
 Photos.zip 
  13   Wed Sep 16 08:52:03 2020 CB (remotely)Baking status 16-17 September16 September

08:50
 20200916_0850_temps.png20200916_0850_ctrl.png20200916_1500_temps.png20200916_2022_temps.png20200917_0820_temps.png 
  12   Tue Sep 15 08:39:26 2020 CB (remotely), JMBaking and Chamber status Tuesday 15 September

08:40
 20200915_0842_ctrl.png20200915_0842_temp.png20200915_152708.jpgimage007.jpg20200915_1920_temps.png 
  11   Mon Sep 14 12:07:40 2020 JM, CB (remotely)Baking statusMon 14 Sep 09:50

Jordan moved the TC08 picolog 2 away from
 20200914_1207_temps.png20200914_1207_ctrl.png20200914_1727_temps.png20200914_2000_temps.png 
  10   Sun Sep 13 08:06:25 2020 CB (remotely)Baking over the weekend -2Sun 13 Sep 08:06

Baking reached 93 C yesterday afternoon at
 20201309_0806_ctrl.png20201309_0806_plot.png 
  9   Sat Sep 12 08:38:52 2020 CB (remotely)Baking over the weekendSaturday 12 Sep 08:43

Remotely checked status of baking. See attached.
 20200912_0839_ctrl.png20200912_0839_plot.png 
  8   Thu Sep 10 11:34:30 2020 TD, JMThursday 10 September All neg feed-throughs have now been fully
installed, with ground tags 
and power wires crimped and attached to the
 20200910_112152.jpg20200910_112211.jpgPhotos_(1).zip 
  7   Wed Sep 9 21:01:48 2020 JMNeg Feedthroughs4/6 of the neg feedthroughs installed.
Continuity between the power pins, ground
pin and the chamber has been checked, we
 Photos.zip 
  6   Fri Sep 4 15:48:25 2020 JMBakeout test completedBakeout test completed. Maximum temperature
reached within baking volume was 120
degrees, with baking stopped by the program
 191214004923_temperatures.txtBakeout1.png 
  5   Wed Sep 2 17:01:49 2020 JMBakeout started and valve installationInitial bakeout started which will run
until friday, temperature had reached 44
degrees when I left the lab. 
 Photos.zip 
  4   Wed Aug 19 16:44:39 2020 JMNeg InstallsInternal neg installs completed and electrically
checked. 
 Photos_(1).zip 
  3   Tue Aug 18 17:35:20 2020 TDSAES UHV1400 pin assignmentUsing a digital multimeter confirmed continuity
for SAES-supplied 
power cable (Amphenol (circular) 6-pin plug
 NEG_POWER_user_manual.pdf20200813_121944_(1).jpg20200813_134548.jpgRFKIT9904220_(2).pdfRFKIT9905220_(2).pdf 
  2   Tue Aug 18 11:26:26 2020 JMWeek ending Friday 14/08/20Week ending friday 14/08/20

CARME chamber securely mounted
upon aluminium frame and support skis. Neg-ion
 Photo.zip 
  1   Mon Aug 17 08:16:16 2020 TDCARME Elog
Test
  
ELOG V3.1.4-unknown